Add Alternate 2 - Collet St. Keller to Marquette
<br />Engineer's Estimate
<br />Selge Construction
<br />Item
<br />No.
<br />Description
<br />Unit
<br />Quantity
<br />Unit Price
<br />Amount
<br />Unit Price
<br />Amount
<br />201
<br />Removals and Clearing
<br />1
<br />LS
<br />$30,000.00
<br />$30,000.00
<br />$59,925.00
<br />$59,925.00
<br />202.
<br />Concrete Curb, Remove
<br />240
<br />LFT
<br />$10.00
<br />$2,400.00
<br />$10.00
<br />$2,400.00
<br />203.
<br />Concrete Sidewalk, Remove
<br />111
<br />SYD
<br />$20.00
<br />$2,220.00
<br />$10.00
<br />$1,110.00
<br />204.
<br />Concrete Approaches, Remove
<br />17
<br />SYD
<br />$20.00
<br />$340,00
<br />$25.00
<br />$425.00
<br />205.
<br />Existing Water Service, Potholing
<br />20
<br />EA
<br />$750.00
<br />$15,000.00
<br />$1,025.00
<br />$20,500.00
<br />206.
<br />Temporary Erosion and Sediment Control
<br />1
<br />LS
<br />$5,000.00
<br />$5,000.00
<br />$1,000.00
<br />$1,000.00
<br />207,
<br />Compacted Aggregate, No. 53, 6"
<br />337
<br />SYD
<br />$14.50
<br />$4,886.50
<br />$30.25
<br />$10,194.25
<br />208.
<br />HMA for Patching, 8"
<br />320
<br />SYD
<br />$40.00
<br />$12,800.00
<br />$84.00
<br />$26,880.00
<br />209.
<br />PCCP for Approaches, 6"
<br />17
<br />SYD
<br />$100.00
<br />$1,700.00
<br />$155.00
<br />$2,635.00
<br />210,
<br />Standard Curb
<br />240
<br />LFT
<br />$45.00
<br />$10,800.00
<br />$71.00
<br />$17,040.00
<br />211.
<br />Concrete Sidewalk, 4"
<br />111
<br />SYD
<br />$70.00
<br />$7,770.00
<br />$115.00
<br />$12,765.00
<br />212.
<br />Water Service, 1", Long Side
<br />10
<br />EA
<br />$7,500.00
<br />$75,000.00
<br />$9,185.00
<br />$91,850.00
<br />213.
<br />Water Service, 1", Short Side
<br />10
<br />EA
<br />$6,000.00
<br />$60,000.00
<br />$8,685.00
<br />$86,850.00
<br />214.
<br />Mulched Seeding, Type U
<br />444
<br />SYD
<br />$5.00
<br />$2,220.00
<br />$9.20
<br />$4,084.80
<br />Alternate 2 Total $230,136.50
<br />$337,659.05
<br />Add Alternate 3 - Elmer St. - Beraan to Pershina
<br />Engineer's Estimate
<br />Selge Construction
<br />Item
<br />No.
<br />Description
<br />nit U
<br />Quantity
<br />Unit Price
<br />Amount
<br />Unit Price
<br />Amount
<br />301
<br />Removals and Clearing
<br />1
<br />LS
<br />$30,000.00
<br />$30,000.00
<br />$27,425.00
<br />$27,425.00
<br />302.
<br />Concrete Curb, Remove
<br />132
<br />LFT
<br />$10.00
<br />$1,320.00
<br />$10.00
<br />$1,320.00
<br />303.
<br />Concrete Sidewalk, Remove
<br />61
<br />SYD
<br />$20.00
<br />$1,220.00
<br />$10.00
<br />$610.00
<br />304.
<br />Concrete Approaches, Remove
<br />17
<br />SYD
<br />$20.00
<br />$340.00
<br />$25.00
<br />$425.00
<br />305.
<br />Existing Water Service, Potholing
<br />11
<br />EA
<br />$750.00
<br />$8,250.00
<br />$1,025.00
<br />$11,275.00
<br />306.
<br />Temporary Erosion and Sediment Control
<br />1
<br />LS
<br />$5,000.00
<br />$5,000.00
<br />$1,000.00
<br />$1,000.00
<br />307.
<br />Compacted Aggregate, No. 53, 6"
<br />180
<br />SYD
<br />$14.50
<br />$2,610.00
<br />$30.25
<br />$5,445.00
<br />308.
<br />HMA for Patching, 8"
<br />163
<br />SYD
<br />$40.00
<br />$6,520,00
<br />$84.00
<br />$13,692,00
<br />309.
<br />PCCP for Approaches, 6"
<br />17
<br />SYD
<br />$100.00
<br />$1,700.00
<br />$155.00
<br />$2,635.00
<br />310.
<br />Standard Curb
<br />132
<br />LFT
<br />$45.00
<br />$5,940.00
<br />$71.00
<br />$9,372.00
<br />311.
<br />Concrete Sidewalk, 4"
<br />61
<br />SYD
<br />$70.00
<br />$4,270.00
<br />$115.00
<br />$7,015.00
<br />312.
<br />Water Service, 1", Long Side
<br />6
<br />EA
<br />$7,500.00
<br />$45,000.00
<br />$9,185.00
<br />$55,110.00
<br />313.
<br />Water Service, 1", Short Side
<br />5
<br />EA
<br />$6,000.00
<br />$30,000.00
<br />$8,685.00
<br />$43,425.00
<br />314.
<br />Mulched Seeding, Type U
<br />244
<br />SYD
<br />$5.00
<br />$1,220.00
<br />$10.90
<br />$2,659.60
<br />Alternate 3 Total $143,390.00
<br />$181,408.60
<br />2of5