Project Plan of Work Schedule <br />We could start work on the project within two weeks of a notice to proceed, allowing for the state <br />demolition notification hold period. <br />During this period we will install erosion control systems and secure the site. <br />We would begin demolishing the remaining portions of the building and separating wood from brick <br />and block. All metal that can be recovered will be recycled. All of the debris will be removed within <br />three weeks. <br />We would then remove all concrete floors, footers, and basement foundations. We can have all <br />material hauled away from the site and recycled within two weeks. <br />The basement area and all voids will be filled in and compacted with approved fill material to be <br />hauled in from off site. The disturbed area will be finished graded with a layer of topsoil. We will <br />then hydroseed the area for erosion control. This will be completed in one week. <br />The entire project will be completed within six weeks of an actual start date. <br />