Construction Manager shall inform the Owner and Architect in the event that the estimate of the Cost of the Work exceeds <br />the latest approved Project budget and make recommendations for corrective action. <br />§ 3.1.6.3 If the Architect is providing cost estimating services as a Supplemental Service, and a discrepancy exists <br />between the Construction Manager's cost estimates and the Architect's cost estimates, the Construction Manager and the <br />Architect shalt work together to reconcile the cost estimates. <br />§ 3,1.7 As the Architect progresses with the preparation of the Schematic Design, Design Development and Construction <br />Documents, the Construction Manager shall consult with the Owner and Architect and make recommendations regarding <br />constructability and schedules, for the Architect's review and the Owner's approval. <br />§ 3.1.8 The Construction Manager shall provide recommendations and information to the Owner and Architect regarding <br />equipment, materials, services, and temporary Project facilities. <br />§ 3.1.9 The Construction Manager shall provide a staffing plan for Preconstruction Phase services for the Owner's review <br />and approval. <br />§ 3.1.10 if the Owner identified a Sustainable Objective in Article 1, the Construction Manager shall fulfill its <br />Preconstruction Phase responsibilities as required in AIA Document E234TM-2019, Sustainable Projects Exhibit, <br />Construction Manager as Constructor Edition, attached to this Agreement, <br />§ 3.1.11 Subcontractors and Suppliers <br />§ 3.1.11.1 If the Owner has provided requirements for subcontractor procurement in section 1.1.14, the Construction <br />Manager shall provide a subcontracting plan, addressing the Owner's requirements, for the Owner's review and approval. <br />In addition, in accordance with Indiana Code 5-32 the Construction Manager may prequalify potential subcontractors <br />based on written criteria developed by the Construction Manager and approved by the Owner. Approval shall not be <br />unreasonably withheld. Upon approval, the written criteria shall become the Owner's established and published bidder <br />p req ual i fit cat i o n criteria for the Project. The Construction Manager shall bid and award first -tier subcontracts in <br />accordance with Indiana Code 5-32 and 36-1-12. <br />§ 3.1.11.2 The Construction Manager shall develop bidders' interest in the Project, including, but not limited to, outreach <br />events and or meetings as suggested by the Owner. <br />§ 3.1.11.3 The processes described in Article 9 shall apply if bid packages will be issued during the Preconstruction Phase. <br />§ 3.1.12 Procurement <br />The Construction Manager shall prepare, for the Architect's review and the Owner's acceptance, a procurement schedule <br />for items that must be ordered in advance of construction. The Construction Manager shall expedite and coordinate the <br />ordering and delivery of materials that must be ordered in advance of construction. If the Owner agrees to procure any <br />items prior to the establishment of the Guaranteed Maximum Price, the Owner shall procure the items on terms and <br />conditions acceptable to the Construction Manager. Upon the establishment of the Guaranteed Maximum Price, the <br />Owner shall assign all contracts for these items to the Construction Manager and the Construction Manager shall <br />thereafter accept responsibility for them. <br />§ 3.1.13 Compliances with Laws <br />The Construction Manager shall comply with applicable laws, statutes, ordinances, codes, rules and regulations, and <br />lawful orders of public authorities applicable to its performance under this Contract, and with equal employment <br />opportunity programs, and other programs as may be required by governmental and quasi -governmental authorities. <br />§ 3.1.14 Other Preconstruction Services <br />Insert a description of any other Preconstruction Phase services to be provided by the Construction Manager, or reference <br />an exhibit attached to this document. <br />(Describe any other Preconstruction Phase services, such as providing cash flow projections, development of a project <br />information management system, early selection or procurement of subcontractors, etc) <br />Init. AIA Document A133 — 2019. Copyright ® 1991, 2003, 2009, and 2019. All rights reserved. "The American Institute of Architects," "American Institute of Architects," <br />"AIA," the AIA Logo, and "AIA Contract Documents" are trademarks of The American Institute of Architects. This document was produced at 16-00-21 ET on <br />I V080023 under Order No_2114477497 which expires on 110012024, is not for resale, is licensed for one-time use only, and may only he used in accordance with <br />t the AIA Contract Documents® Terms of Service. To report copyright violations, a -mail docinfo@aiacontracts.corn <br />User Notes: (1447978347) <br />