§ 3.2.8 The Owner shall authorize preparation of revisions to the Contract Documents that incorporate the agreed -upon <br />assumptions and clarifications contained in the Guaranteed Maximum Price Amendment. The Owner shall promptly <br />furnish such revised Contract Documents to the Construction Manager. The Construction Manager shall notify the Owner <br />and Architect of any inconsistencies between the agreed -upon assumptions and clarifications contained in the Guaranteed <br />Maximum Price Amendment and the revised Contract Documents. <br />§ 3.2.9 The Construction Manager shall include in the Guaranteed Maximum Price all sales, consumer, use and similar <br />taxes for the Work provided by the Construction Manager that are legally enacted, whether or not yet effective, at the time <br />the Guaranteed Maximum Price Amendment is executed. <br />§ 3.3 Construction Phase <br />§ 3.3.1 General <br />§ 3.3.1.1 For purposes of Section S. l .2 of A201-2017, the date of commencement of the Work shall mean the date of <br />commencement of the Construction Phase. <br />§ 3.3.1.2 The Construction Phase shall commence upon the Owner's execution of the Guaranteed Maximum Price <br />Amendment or, prior to acceptance of the Guaranteed Maximum Price proposal, by written agreement of the parties. The <br />written agreement shall set forth a description of the Work to be performed by the Construction Manager, and any <br />insurance and bond requirements for Work performed prior to execution of the Guaranteed Maximum Price Amendment. <br />§ 3.3.2 Administration <br />§ 3.3.2.1 The Construction Manager shall schedule and conduct meetings to discuss such matters as procedures, progress, <br />coordination, scheduling, and status of the Work. The Construction Manager shall prepare and promptly distribute <br />minutes of the meetings to the Owner and Architect. <br />§ 3.3.2.2 Upon the execution of the Guaranteed Maximum Price Amendment, the Construction Manager shall prepare and <br />subin"tt to the Owner and Architect a construction schedule for the Work and a submittal schedule in accordance with <br />Section 3.10 of A201-2017. <br />§ 3.3.2.3 Monthly Report <br />The Construction Manager shall record the progress of the Project. On a monthly basis, or otherwise as agreed to by the <br />Owner, the Construction Manager shall submit written progress reports to the Owner and Architect, showing percentages <br />of completion and other information required by the Owner. <br />§ 3.3.2.4 Daily Logs <br />The Construction Manager shall keep, and make available to the Owner and Architect, a daily log containing a record for <br />each day of weather, portions of the Work in progress, number of workers on site, identification of equipment on site, <br />problems that might affect progress of the work, accidents, injuries, and other information required by the Owner. <br />§ 3.3.2.5 Cost Control <br />The Construction Manager shall develop a system of cost control for the Work, including regular monitoring of actual <br />costs for activities in progress and estimates for uncompleted tasks and proposed changes. The Construction Manager <br />shall identify variances between actual and estimated costs and report the variances to the Owner and Architect, and shall <br />provide this information in its monthly reports to the Owner and Architect, in accordance with Section 3.3.2.3 above. <br />ARTICLE 4 OWNER'S RESPONSIBILITIES <br />§ 4.1 Information and Services Required of the Owner <br />§ 4.1.1 The Owner shall provide information with reasonable promptness, regarding requirements for and limitations on <br />the Project, including a written program which shall set forth the Owner's objectives, constraints, and criteria, including <br />schedule, space requirements and relationships, flexibility and expandability, special equipment, systems, sustainability <br />and site requirements. <br />§ 4.1.2 Prior to the execution of the Guaranteed Maximum Price Amendment, the Construction Manager may request in <br />writing that the Owner provide reasonable evidence that the Owner has made financial arrangements to fulfill the Owner's <br />obligations under the Contract. After execution of the Guaranteed Maximum Price Amendment, the Construction <br />Manager may request such information as set forth in A201-2017 Section 2.2. <br />Init. AIA Document A133 — 2019. Copyright ® 1991, 2003, 2009, and 2019. All rights reserved. "The American Institute of Architects," "American Institute of Architects," <br />"AIA," the AIA Logo, and "AIA Contract Documents" are trademarks of The American Institute of Architects. This document was produced at 16:00:21 ET on <br />7 f1080023 under Order No_2114477497 which expires on 110012024, is not for resale, is licensed for one-time use only, and may only he used in accordance with <br />t the AIA Contract Documents® Terms of Service. To report copyright violations, a -mail docinfo@aiacontracts.com- <br />User Notes: (1447978347) <br />