Laserfiche WebLink
Execution Work Plan <br />Bowen's Operation Team <br />Operation Manager: Chris Manges <br />Project Manager: Pat Stanford <br />Superintendent: Tony Abitua <br />Bowen propose to start work late September to early October, with a 29 week schedule. <br />Work to be performed. <br />1. Install environmental silt fence and protect inlets <br />2. Demo work on existing tanks and concrete <br />3. Demo work on masonry block for overhead doors and wall penetrations <br />4. Demo existing concrete spill pad and curb and stoop <br />5. Demo existing 1" Chlorine and %" Fluoride line <br />6. Excavate form and pour new Engine Generator and Mau foundations <br />7. Excavate form and pour new chemical unloading area <br />8. Excavate and install new chemical lines to vault <br />9. Remove existing coatings <br />10. Pour new tank and equipment pads <br />11. Place new coatings <br />12. Install new tanks and equipment <br />13. Install new roll up doors and man doors <br />14. Infill new masonry block <br />15. install new piping and all electrical for new tanks and equipment <br />16. Install new fire suppression and extinguishers <br />17. Install new guard railing and guard posts <br />18. General cleanup <br />