Contract No:R -36881 Change Order No.: 007 <br />INDIANA Department of Transportation Page: 1 <br />Construction Change Order and Time Extension Summary <br />Contract Information Contract No.: R -36881 Letting Date:09/13/2017 <br />District:LAPORTE DISTRICT AE:Forgey, Ryan PE/S:Carey, Michael Status:Draft <br />Change Order Information Change Order No.: 007 EWA: N or Force Acct: N <br />Date Generated: 00/00/0000 Date Approved: 00/00/0000 <br />Reason Code: CHANGED COND, Constructability Related <br />Description: Contract Completion Extension <br />Original Contract Amount $ 1,163,781.52 <br />Current Change Order Amount $ 0.00 Percent: 0.000 % <br />Total Previous Approved Changes $ 187,405.97 Percent: 16.103 % <br />Total Change To -Date $ 187,405.97 Percent: 16.103 % <br />Modified Contract Amount $ 1,351,187.49 <br />Time Extension Information <br />Date Initiated 00/00/0000 Date Completed 00/00/0000 <br />Original Contract Time SS Completion Date 11/02/2018 or SS Calendar/Work Days 0 <br />SP Date 00/00/0000 or SP Days <br />(SS = Standard Specification, SP = Special Provision) <br />Time Element Description: This extension of 40 days goes in collaboration with Change order #5. 176 calendar <br />days was added to the contract on CO#5; 95 days for the accidental discovery and 81 days for the time accounted <br />for the non -construction season between December 1 and March 31. But unknowingly those dates add up to 121 <br />days not 81. The difference of the error is the reason for the change order of 40 days. <br />Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00 <br />Previous Time Approved SS Days by AE:__ DCE: SCE: DDCM:_ <br />SS Days. ............................................. SP Days Value $ .................... ..- <br />Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0 <br />SS Date 00/00/0000 or SP Days 0 <br />