MICiLELS 0 <br />March 26, 2019 <br />City of South Bend, IN <br />227 West Jefferson Blvd <br />South Bend, IN 46601 <br />Attention: Linda Martin <br />Reference: Main & Jefferson Earthwork <br />Project # 119-022 <br />South Bend, IN <br />Michels has reviewed the "50% Construction Documents" drawings S100,S301 dated January 28, 2019 including <br />the geotechnical report dated April 10, 2018 and offer the following pricing for Earth Retention: <br />±285 wall feet cantilevered soldier pile and lagging along North & East Property line ............ $284,000 <br />** VE ** 1285 wall feet cantilevered sheeting along North & East Property line ..,...„..,.„„„,,.„,, $239,000 <br />Unit Pricing mAdd/Deduct wall feet. <br />** Deduct $375/1,17 for earth retention less than 285 wall feet ; Add $565/LF for additional earth retention beyond <br />285 wall feet. <br />lirClttelc d in the E'ar tlr Retention <br />1. One mobilization of one drive rig to install sheeting for the earth retention system. Additional <br />mobilizations will be charged @ $35,000/ea. <br />2. Shop drawings and calculations stamped by an Indiana licensed Professional Engineer. <br />3. Furnish and install ±285 wf of earth retention inside the North and East property line. <br />4. Earth retention to be installed to 2' below existing grade and abandoned in place. <br />5. 1285 WF of two wire safety fence without toeboard is included. Removal and maintenance of the safety <br />cable is excluded. <br />6. Payment and Performance Bond. <br />In addr„th;rrr icy the altychesed Bid Pi°rrrrrrsr�mi �i��at�°r°eiI �'a.r)Oil 'L))Is flier �6110nrin , is to be )rr���trf��N <br />1. Dry, firm, and level access for our piling rig and equipment is to be furnished and maintained by others. <br />Benches and slopes into the sidewalk/public way per our requirements will be required by others. <br />2. All above ground and underground asphalt, concrete, utilities, rock removal, power lines, etc., to be <br />removed by others. The site must be ready for continuous operation. Obstruction delays defined as any <br />object which impedes, damages, or causes misalignment of piling utilizing the equipment on site will be <br />charged at $1,650/hr. Obstruction free sheeting line a minimum of 18" below top of sheet elevation is <br />to be prepared prior to mobilization. <br />3. Unlimited headroom 4' clear is required by others. OSHA clearances for power lines are required by <br />others. Removal of any obstructions (i.e. planters, trees, traffic pole lights,boxes etc.) that impede the <br />ability to install or deliver material and/or equipment is required by others. <br />4. Flagging and traffic control for anything other than our equipment and material deliveries is excluded. <br />5. Dewatering and pumping, if required, by others per our design requirements. Winter conditions are <br />excluded. <br />6. Maximum excavation is to 14' below existing grade. <br />7. Vibration monitoring is excluded. We intend to install the piles using conventional impact and/or vibratory <br />hammers. Some noise and vibration will be transferred to the surrounding structures. Pre -construction <br />survey of existing structures is excluded. <br />8. Layout, surveying and grades are by others. Corners and intermediate points are required by others. <br />9. Trimming of earth retention system is excluded. Intent is to install 2' below existing grade. <br />10. AutoCAD drawing files for design are required by others at no cost to Michels. <br />