1 a Document G7 1 TM 17 <br />uWii <br />Change Order <br />PROJECT: (Name and address) CONTRACT INFORMATION: CHANGE ORDER INFORMATION: <br />17043 - Erskine Clubhouse Renovation Contract For: General Construction Change Order Number: 06 <br />City Project #236563 Date: 8/28/2018 Date: 01/10/2019 <br />OWNER: (Name and address) ARCHITECT: (Name and address) CONTRACTOR: (Name and address) <br />Board of Public Works Gregory A. Kil & Associates, Inc. Ziolkowski Construction Co., Inc. <br />City of South Bend, IN <br />1316 County City Building (d/b/a) Kil Architecture / Planning 4050 Ralph Jones Drive <br />227 W Jefferson Boulevard 1126 Lincolnway East South Bend, IN 46628 <br />South Bend, IN 466011830 South Bend, IN 46601 <br />THE CONTRACT IS CHANGED AS FOLLOWS: <br />(Insert a detailed description of the change and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments <br />attributable to executed Construction Change Directives.) <br />Per the attached RCO #008 — add $2,173.00 to provide labor, material and equipment to remove and rebuild existing roof over proposed <br />snack bar area. <br />Per the attached RCO #011 — add $884.00 to provide labor, material and equipment to frame up a new stud wall in front of the existing <br />poured ledge.Wall to be covered with 5/8" drywall, taped, finished and painted. <br />Per the attached RCO #012 — add $3,519.00 to eliminate the original 10" and 14" spiral supply air duct and replace it with 18" and 20" spiral <br />duct thru the existing mechanical room door and connect to furnace plenum. Change the spiral grillsto the appropriate diameter along with <br />adding (2)two 30" x30" air grills to the mechanical room door for transfer from main area to mechanical room. Per RFI #027. <br />Per the attached RCO #013 — add $1,750.00 to provide labor, material and equipment to tuck point exterior fieldstone wall located on north <br />west corner of existing building. <br />Per the attached RCO #014 — add $908.00 to provide labor, material and equipment to tuck -point south east corner and north east corner, <br />Per the attached RCO #015 — add $890.00 to provide labor, material and equipment to tuckpoint west chimney. <br />Per the attached RCO #016 — add $420.00 to provide labor, material and equipment to relocate existing clean out that is located in the middle <br />of the proposed new door opening 002 per RFI # 021. <br />Per the attached RCO #017 — add $13,318.00 to provide labor, material and equipment to revise kitchen plumbing per RFI # 005. <br />Per the attached RCO #018 — add $628.00 to provide labor, material and equipment to place CMU block to infill the existing opening located <br />on the east side of porch and to allow for the proposed venting system to pass through the block above finished grade per RFI # 033. <br />Per the attached RCO #020 — add $1,866.00 to provide additional labor, material and equipment to remove loose concrete and cover concrete <br />steps with MG KRETE per RFI # 013. <br />Per the attached RCO #021- add $36,602.00 to have SSI and ACM to do removal and assessment services to remove lead paint located on <br />walls and basement floor; and to have SSI and ACM to do the removal and assessment services to remove asbestos containing materials. <br />Total increase for CO # 6 = $62,958.00. <br />The original Contract Sum was $ 907,000.00 <br />The net change by previously authorized Change Orders $ 17,184.00 <br />The Contract Sum prior to this Change Order was $ 924 184.00 <br />The Contract Sum will be increased by this Change Order in the amount of $ 62 958.00 <br />The new Contract Sum including this Change Order will be $ 987„142.00 <br />The Contract Time will be increased by Zero (0) days. <br />The new date of Substantial Completion will be March 22, 20t9 <br />AIA Document G701 TM — 2017. Copyright © 1979, 1987, 2000 , 2001 and 2017 by The American Institute of Architects. All rights reserved. WAIRII411llNG: "'ll"IIua <br />AIIAw> K)ocouumient, Is prot,ecteed by U,& Copyidght ILawea a¢nnd Ilintu*ii'miitiio nail "f rea:ties, Unaouikharlized repw°oaluctlion auiudistribution, arl' ii1filis MA' IDo uuurueint, m <br />aniy pou°ttoan of It, may me aouft liurnl sevem civil) and a,m°uamnfi naaf penafkua,a„ and Will Ihae procaectillied to the uirnaxi n'"Arn extent poua^aiilbIle umarmdeir t:ho Ilawwaa. This <br />document was produced by AIA software at 09:53:53 ET on 01/10/2019 under Order No. 4284250045 which expires on 01/1012020, and is not for resale, <br />User Notes: (3B9ADA4A) <br />