INTER -OFFICE MEMORANDUM <br />DEPARTMENT OF PUBLIC WORKS <br />DIVISION OF ENGINEERING <br />TO: Board of Public Works <br />FROM: Toy Villa <br />Bureau of Public Construction <br />SUBJECT: Ironwood Drive Pavement Rehabilitation and Intersection <br />Project Number 117-071A <br />DATE: August 7, 2018 <br />Herewith is an explanation for the change order #3 being submitted. <br />The reason(s) for the change order request is as follows: <br />. Time extension due to waiting on the manufacture and delivery of traffic signal <br />Mast Arm Poles (MAP). The contractor submitted the order immediately <br />following approval but the supplier has an extensive lead time. After installation <br />of the MAPs the concrete sidewalk around the pole bases will be poured. <br />The cost for the work will be increased by $0.00. <br />This represents an increase of 0.00% for this change order. <br />This represents an increase of 32 days to the contract for this change order. <br />