Contract No:R -39513 INDIANA <br />Change Order No:002 Department of Transportation <br />Date:07/27/2018 <br />Page: 3 <br />Contract: R -39513 <br />Project: 1600075 - State;160007500LC4 <br />Change Order Nbr: 002 <br />Change Ordar Description: Additional cost and time extension for root removal. <br />Reason Code: CHANGED COND, Constructability Related <br />Oi.N PCN PLN Item Code unit Unit Prise CtJ Qty Comment Amount Change <br />0041 1600075 0040 105.06007 LS 10,990.040 1.000 G Amounl:$ 10,990.04 <br />Item Description: ADDITIONAL <br />Supplemental DescdptlonI., Cost for tool removal <br />Supplemental Descdption2: <br />Total Value for Change Order 002 = S 10,990.04 <br />Milestone Time Adjustment <br />Mileslons Nbc 01 <br />Milestone Description. INTERMEDIATE COMPLETION DATE 1 <br />Original Completion dt: 09/07/201 a Adj comp) dt 09/2112018 Ad) No. of Days 14 <br />Explanation. The Intermediate Completion Date to complete all of the concrete work on this project needs to be extended 14 calendar <br />days due to the delays caused by the extreme amount of root removal encountered on this project, mainly along <br />Woodside, Oakside, and Eckman Sts. This 14 days Includes the time Involved removing the roots as wall as The time <br />needed to Import and replace the borrow material to fill the voids left by the root removal. <br />Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended. <br />General or Standard Change Order Explanation <br />This change order adds a new lump sum item to cover the cost Incurred by the contractor for the removal of the extreme number and size of the <br />tree roots encountered on this project, mainly along Woodside, Oakslde, and Eckman Sts. This work Involves the actual root removal as well as <br />the hauling away of this debris. This change order also Includes a time extension of 14 calendar days to the Intermediate Completion Date of <br />9107118. The time delays involve the extra work for the root removal along with the time It takes to import and replace the borrow material to till <br />the voids left by this removal. <br />Change Order Explanation for Specific Line Item <br />H....... .. H a...... ...... a} •+Ha } a H a R H+Y H++f a a t R H a a aY tt H H.... .....1. H.. Ma.......... <br />k <br />It Is the intent of the parties that this change order Is full and complete compensation for the work describe above. <br />Notltication and consent to this chancre order Is herebv acknowtedoed. <br />Contractor <br />Date: <br />Signed By: ) ): <br />a... N a. a.......... —*....++..............tat. a......... H....... H........A.......... t+,.. <br />NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system. <br />