Laserfiche WebLink
This is Exhibit D, Engineer's Project <br />Schedule, referred to in and part of the Short <br />Form of Agreement between Owner and <br />Engineer for Professional Services dated <br />February 14, 2017. <br />Engineer's Project Schedule <br />A. After receiving a written notice to proceed the Engineer shall: <br />1. 7 Calendar Days Complete Field Topographic Survey. <br />2. 7 Calendar Days Provide survey data to the Owner in CAD format <br />after completion of field topographic survey. <br />Exhibit D, Engineers Project Schedule <br />EJCDC E•520 Short Form of Agreement Between Owner and Engineer for Professional Services. <br />Copyright 02009 National Society of Professional Engineers for EJCDC. All rights reserved. <br />Pace 1 <br />