REGULAR MEETING DECEMBER 13 2016 392
<br />this Change Order, of $1,838,183.83. Additionally submitted was the Project Completion
<br />Affidavit indicating this new final cost of $1,838,183.83. Upon a motion made by Ms. Maradik,
<br />seconded by Ms. Fritzberg and carried, Change Order No. 7 (Final) and the Project Completion
<br />Affidavit were approved.
<br />APPROVE CHANGE ORDER NO 7 (FINAL] AND PROJECT COMPLETION AFFIDAVIT
<br />— WESTERN AVENUE CORRIDOR IMPROVEMENTS — PROJECT NO 114-033B (MAJOR
<br />MOVES/RWDA TIF)
<br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 7 (Final) on --
<br />behalf of Rieth-Riley Construction Co., Inc., 25200 State Road 23, South Bend, Indiana 46614
<br />indicating the contract amount be decreased by $17,690.18 for a modified contract sum,
<br />including this Change Order, of $955,346.70. Additionally submitted was the Project
<br />Completion Affidavit indicating this new final cost of $955,346.70. Upon a motion made by Ms.
<br />Maradik, seconded by Ms. Fritzberg and carried, Change Order No. 7 (Final) and the Project
<br />Completion Affidavit were approved.
<br />APPROVE CHANGE ORDER NO. 2 (FINAL) AND PROJECT COMPLETION AFFIDAVIT
<br />— FELLOWS. STREET AND DUBAIL STREET NEIGHBORHOOD IMPROVEMENTS —
<br />PROJECT NO. 116-041A (RWDA TIF)
<br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted Change Order No. 2 (Final) on
<br />behalf of Ainnarking Co., hie., PO Box 526, Rochester, Indiana 46975 indicating the contract
<br />amount be decreased by $2,116.40 for a modified contract sum, including this Change Order, of
<br />$54,217.75. Additionally submitted was the Project Completion Affidavit indicating this new
<br />final cost of $54,217.75. Upon a motion made by Ms. Maradik, seconded by Ms. Fritzberg and
<br />carried, Change Order No. 2 (Final) and the Project Completion Affidavit were approved.
<br />APPROVE PROJECT COMPLETION AFFIDAVIT — CENTURY CENTER BRIDGE LED
<br />LAMP RETROFIT - PROJECT NO 116-007A (HOTEL/MOTEL TAX)
<br />Mr. Gilot advised that Mr. Richard Estes, Engineering, has submitted the Project Completion
<br />Affidavit on behalf of Days Corporation, 55169 County Road 3, Elkhart, Indiana 46514, for the
<br />above referenced project, indicating a final cost of $4,653.00. Upon a motion made by Ms.
<br />Maradik, seconded by Ms. Fritzberg and carried, the Project Completion Affidavit was approved.
<br />APPROVE PROJECT COMPLETION AFFIDAVITS — T AWN CARE SERVICES — PROJEC"f
<br />NOS. 116-002A._B, AND C EDIT)
<br />Mr. Gilot advised that Mr. Toy Villa, Engineering, has submitted the Project Completion
<br />Affidavits on behalf of Caretaker Landscape & Lawn, PO Box 324, Michigan City, Indiana
<br />46360, for the above referenced projects, indicating a final cost as listed below:
<br />a) Project No. 116-002A
<br />(1) Final Contract Amount: $32,370
<br />b) Project No. 116-002B
<br />(1) Final Contract Amount: $69,090
<br />c) Project No.116-002C
<br />(1) Final Contract Amount: $2,280
<br />Upon a motion made by Ms. Maradik, seconded by Ms. Fritzberg and carried, the Project
<br />Completion Affidavits were approved.
<br />APPROVAL OF REQUEST TO ADVERTISE FOR THE RECEIPT OF BIDS — FIVE -
<br />THOUSAND (5 000) MORE OR LESS UNIVERSAL/NESTABLE RFFUSE CONTAINERS
<br />— SPEC A (2017 SOLID WASTE CAPITAL. LEASE) _
<br />In a memorandum to the Board, Mr. Matt Chlebowski, Central Services, requested permission to
<br />advertise for the receipt of bids for the above referenced items. Therefore, upon a motion made
<br />by Ms. Maradik, seconded by Ms. Fritzberg and carried, the above request was approved.
<br />WASTE CAPITAL LEASE)
<br />In a memorandum to the Board, Mr. Matt Chlebowski, Central Services, requested permission to
<br />advertise for the receipt of bids for the above referenced equipment. Upon a motion made by Ms.
<br />Maradik, seconded by Ms. Fritzberg and carried, the above request to advertise was approved.