TO: Redevelopment Commission
FROM: Liz Maradik, Planner
SUBJECT: Professional Services Agreement with SmithGroupJJR - River Parks & Trails Plan
Staff requests Redevelopment Commission approval of a professional services agreement with SmithGroupJJR
in an amount not to exceed $248,800 (including reimbursement of up to $2,000 for pre- approved out -of-
pocket expenses) to complete a plan for the river parks & trails. The agreement continues through May 26,
2017.
The Department of Parks & Recreation, in conjunction with the Department of Community Investment, wishes
to develop a strategic plan for its river park and trail system, from Darden Road to Logan Street, with a focus
between Leeper Park and the Farmers Market. The plan will serve as a guide for making investment, use, and
design decisions within the system. The planning process will involve outreach to residents and stakeholders in
order to create a plan that is consistent with the community's goals, while also accounting for constraints and
opportunities.
227 W. JEFFERSON BLVD. SOUTH BEND, IN 46601 1 P: 574 - 235 -9371 1 FAX: 574 - 235 -9021 1 SOUTHBENDIN.GOV
AGREEMENT FOR PROFESSIONAL SERVICES
This Agreement For Professional Services (this "Agreement ") is entered into on July 28,
2016 (the "Effective Date "), by and between the City of South Bend, Department of
Redevelopment, acting by and through its governing body, the South Bend Redevelopment
Commission (the "Commission "), and SmithGroupJJR, Inc., a Michigan corporation with its
registered office address at 500 Griswold St., Suite 1700, Detroit, Michigan 48226 (the "Provider ")
(each a "Party" and collectively the "Parties ").
For and in consideration of the mutual covenants and promises contained herein, the Parties
agree as follows:
1. Services. The Provider will provide to the Commission the professional services
set forth in attached the Provider's proposal attached hereto as Exhibit A (the "Services "). The
Provider will execute its obligations under this Agreement in accordance with the prevailing
professional standard of care for projects of similar design and complexity.
2. Compensation. In exchange for the Provider's satisfactory performance of the
Services, and subject to the terms and conditions of this Agreement, the Commission will pay the
Provider a total sum not to exceed Two Hundred Forty -Six Thousand Eight Hundred Dollars
($246,800) (the "Contract Amount "). The Commission will pay the Contract Amount in
installments upon invoicing by the Provider based on a percentage of completion (each a "Contract
Installment "). The Commission will not be required to pay any Contract Installment if the
Commission is not satisfied with the Provider's performance under this Agreement or any default
or breach of this Agreement by the Provider exists, as the Commission may determine in its sole
discretion. The sum of all Contract Installments will not exceed the Contract Amount, and
reimbursement for expenses permitted under Section 3 below will not be included in the Contract
Amount.
3. Expenses. The Provider may seek reimbursement from the Commission in an
amount not to exceed Two Thousand Dollars ($2,000.00) for the Provider's out -of- pocket
expenses approved in writing by the Contract Administrator identified in Section 11 below. The
Provider agrees to seek the Contract Administrator's approval of such expenses before incurring
them. The Commission will not reimburse the Provider for any expense unrelated to the Provider's
performance of the Services defined in this Agreement or otherwise unnecessary, and the Contract
Administrator reserves the right to deny reimbursement of any expense as determined in her sole
discretion.
4. Term; Termination., Unless earlier terminated in accordance with its terms, this
Agreement will commence on the Effective Date stated above and end on May 26, 2017 (the
"Expiration Date "). Effective immediately upon delivery of a written termination notice to the
Provider, the Commission may terminate this Agreement, in whole or in part, for any reason, if
the Commission determines that such termination is in the best interest of the Commission. In
addition, in accordance with Ind. Code 6- 1.1 -18, payments are subject to appropriation by the
South Bend Redevelopment Commission. If the Commission makes a written determination that
funds are not appropriated or are otherwise unavailable to support the continuation of this
Agreement, it shall be cancelled. A determination by the Commission that funds are not
appropriated or are otherwise unavailable to support the continuation of performance shall be final
and conclusive. The Commission will not be required to pay any Contract Installment or be
otherwise liable for any cost associated with the Provider's performance of any Services after the
effective date of termination.
5. Remedies for Breach of Contract. Failure to complete the Services in accordance
with this Agreement may be considered a material breach. In the event of such breach, the
Commission may suspend all payments to the Provider and may pursue any and all remedies
available at law or in equity. The Provider shall repay to the Commission any portion of the
Contract Amount expended for matters not within the scope of the Services.
6. Point of Contact. The Contract Administrator identified in Section 11 below will
serve as the Commission's principal point of contact for purposes of this Agreement.
7. Relationship. The Provider shall at all times be an independent contractor for the
performance of the Services rather than an employee of the Commission, and no act or omission
to act by the Provider shall in any way bind or obligate the Commission. This Agreement is strictly
for the benefit of the Parties and not for any third -party or person. This Agreement was negotiated
by the Parties at arm's length and each of the parties hereto has reviewed the Agreement after the
opportunity to consult with independent legal counsel. Neither party shall maintain that the
language in the Agreement shall be construed against any signatory hereto. The Commission and
the Provider hereby renounce the existence of any form of agency relationship, joint venture, or
partnership between the Provider and the Commission and agree that nothing contained herein or
in any document executed in connection herewith shall be construed as creating any such
relationship between the Commission and the Provider.
8. Indemnification of Commission. The Provider hereby agrees to defend, indemnify,
and hold harmless the Commission, its officials, employees, and agents from any and all claims of
any nature which arise from the performance by the Provider under this Agreement and from all
costs and attorney fees in connection therewith, excepting for claims arising out of the negligence
of the Commission, its officials, directors, employees, and agents. The obligations of the Provider
under this Section shall survive the termination of this Agreement.
9. Indemnification of Provider. In the event documents prepared by the Provider are
incorporated by the Commission into a construction contract, the Provider will be provided an
opportunity to review the proposed general conditions of the construction contract. Any terms and
conditions that are beyond those normally and customarily provided by design professionals
similarly situated will not be a part of the Provider's obligations. Further, such general conditions
shall contain an indemnification provision extending from the construction contractor to both the
Commission and the Provider. Both the Commission and the Provider will be named as additional
insureds on such contractor's general liability insurance.
10. Limitation of Liability. Notwithstanding anything to the contrary and the fullest
extent permitted by law, the Commission agrees that the total liability of the Provider in connection
with this Agreement, whether in contract, tort, negligence, breach or otherwise, shall not exceed
2
the Contract Amount.
11. Notices. Any notice required or permitted to be delivered hereunder shall be
deemed to be delivered, whether or not actually received, when deposited in the United States
Postal Service, postage prepaid, registered or certified mail, return receipt requested, addressed to
the Commission or the Provider, as the case may be, at the address set forth below.
Provider:
SmithGroupJJR, Inc.
201 Depot St., Second Floor
Ann Arbor, MI 48104
Attn: Pat Doher
Commission:
Department of Community Investment
City of South Bend
227 W. Jefferson Boulevard, Suite 1400 S.
South Bend, IN 46601
Attn: Elizabeth Maradik
(the "Contract Administrator ")
12. Equal Opportunity The Provider shall comply with federal, state, and local law in
its hiring and employment practices and policies for any activity covered by this Agreement.
13. Entire Agreement; Amendment; Applicable Law. This Agreement sets forth the
entire agreement and understanding between the parties as to the subject matter hereof, and merges
and supersedes all prior discussions, agreements, and understanding of any and every nature
between them. This Agreement may be amended only by separate writing, signed by authorized
representatives of both the Provider and the Commission. This Agreement will be construed and
interpreted according to the laws of the State of Indiana.
14. Assi n� The Provider shall not assign or subcontract the whole or any part of
this Agreement or its obligations hereunder without the prior written consent of the Commission.
15. Non - Collusion. The undersigned attests, subject to the penalties of perjury, that he
is the Provider and that he has not entered into or offered to enter into any combination, collusion,
or agreement to receive or pay, and that he has not received or paid, any sum of money or other
consideration for the execution of this Agreement other than that which appears upon the face
hereof. The Provider agrees that he will execute and submit to the Commission and any other
appropriate bodies, an affidavit in the form attached hereto as Exhibit B.
16. Drug -Free Workplace. The Provider hereby agrees to make a good faith effort to
provide and maintain a drug -free workplace. The Provider will give written notice to the
Commission within ten (10) days after receiving actual notice that the Provider or an employee of
the Provider within the State of Indiana has been convicted of a criminal drug violation occurring
in the workplace.
17. E- Verifv. The Provider hereby certifies that it does not and will not knowingly
employ or contract with an unauthorized alien, nor retain any employee or contract with a person
that the Provider subsequently learns is an unauthorized alien. The Provider agrees that he /she /it
shall enroll in and verify the work eligibility status of all of the Provider's newly hired employees
through the E- Verify program as defined by Ind. Code 22- 5- 1.7 -3.
IN WITNESS WHEREOF, the Parties hereto have caused this Agreement for Professional
Services to be effective as of the Effective Date stated above.
South Bend Redevelopment
Commission, governing body of the
City of South Bend Department of
Redevelopment
IC
Marcia I. Jones, President
ATTEST:
Donald E. Inks, Secretary
SmithGroupJJR, Inc.,
a Michigan corp ation
By:
A
Patrick M. Doher, Senior Vice President
1800.000000154435040.004
11
EXHIBIT A
Scope of Work
[See attached.]
TECHNICAL APPROACH
lr
I
r
4V r•
City of South Bend Riverfront Parks &Trails Master Plan
�
,
3
lr
I
r
4V r•
City of South Bend Riverfront Parks &Trails Master Plan
Project Understanding
The City of South Bend Parks and Recreation (City)
has a strong commitment to provide high quality parks
and recreation amenities to enhance the quality of life of
the community it serves. The City has a unique asset in
the St. Joseph River with numerous public and private
land uses located along the river banks. SmithGroupJJR
understands that the City desires to develop a strategic,
cohesive plan for its riverfront park and trail system with a
focus on the downtown area.
the proposed Riverfront Parks & Trails Master Plan will
build upon recent efforts completed by the City, including
but not limited to the: City of South Bend 5 -Year Park
Master Plan (2014 -2018) and the 2014 Community
Needs Assessment Findings. The outcome of the proposed
planning process will be a framework for the City in
making investment, use and design decisions within the
Riverfront Parks & Trails system.
SmithGroupJJR envisions a planning process that is
transparent, inclusive and inviting to the community
and stakeholders. This will require regular, focused input
. 1�`
gathered through strategically scheduled meetings and
work sessions in each of the project phases with various
city, stakeholder and public representatives. As outlined
further in the Technical Approach, SmithGroupJJR will
kick off the process by meeting with the Project Team and
will regularly check in throughout the process to ensure
that the project is meeting the objectives of the City. This
will facilitate a swift but appropriate decision - making
process, a thorough consideration of alternatives and
costs, and the timely completion of the planning process,
which will help move the project towards implementation.
The Riverfront Parks & Trails Master Plan will accomplish
many goals. It must serve as a guide for reinforcing
the parks as a network of facilities; ensure desirable,
multifunctional and unique public open space to serve
the needs of local residents; provide a framework for
sustainable development of the riverfront that can
enhance the image of South Bend; establish design
standards for the riverfront parks system to be viewed as
a cohesive network and detail conceptual designs for key
locations within the downtown area that can be advanced
to implementation.
Technical Approach
Developing a comprehensive Riverfront Parks &
Trails Master Plan requires engagement of a broad
range of stakeholders as well as a thorough analysis of
existing conditions and opportunities. These activities
feed into the development of recommendations and
implementation strategies that draw on local expertise,
national best practices, and sound methods.
The scope of work presented below is organized over the
course of three major tasks:
• Task 1: Project Initiation
• Task 2: Analysis & Opportunities (Information
Gathering)
• Task 3: Master Plan Development
Each of these tasks consists of a number of sub -tasks
described in detail below, and collectively brings together
a robust community engagement strategy, thorough
analysis, and an in -depth process for developing key
strategies and approaches for plan implementation.
This proposed project technical approach represents the
Consultant Team's collective experience, but we welcome
the opportunity to adjust this approach to best meet the
City's needs and expectations.
Task I: Project Initiation
Task 1 will be focused around understanding and
articulating a shared vision and direction for the
South Bend riverfront park system. A broad range of
stakeholders and public will be engaged early on in the
process to provide their local knowledge and insights, and
to shape the direction of the plan moving into subsequent
phases.
1.1— Project Team Kick -off Meeting
The "Project Team" will consist of Consultants and
key City staff from Parks & Recreation, Community
Investment, Public Works, and other departments that
play a role in development of the plan. Team Meetings
will typically be attended by at least one present
consultant team member, with additional members
brought in as needed or accessing the meeting remotely
via conferencing technologies. Team Meetings are
anticipated to be 2 hours, although may be shorter or
longer depending on the materials being presented. An
initial kick -off meeting will be held to discuss project
process and schedule as well as goals, objectives, and
expectations that will help guide actions and decisions of
the Consulting Team.
Deliverable: Meeting notes
1.2 — Public Involvement Plan
An integral task to the master planning process is
developing an appropriate and sound public engagement
strategy to solicit community input on how South Bend's
parks, recreation programs, open space, trails and cultural
resources meet the needs of residents into the fiiture.
A general approach for this will be discussed in the kick-
off team meeting, which will include:
• Identification of key stakeholders & potential focus
group members
• Outreach and communication strategy for public
engagement
• Sequence and logistics for community workshops
• City & consultant team responsibilities
We use a variety of potential engagement techniques
including some non - traditional methods to allow for all
participants and groups to be comfortable in providing
input. Sam Centellas, Organizational Consultant for
OutSight Design & Consulting, and member of our
project team, will serve as a translator and liaison to
the Latino community. Sam has extensive community
engagement experience and a history in South Bend as an
educator, mentor and activist. Having bilingual written
and spoken presentation materials will help improve
participation and facilitate an inclusive process.
Our team is experienced in creating a social media
presence through a comprehensive Facebook page, as
well as Twitter and other social media outlets. We will
post, and link to project updates, plans, and exciting
information to keep the community involved in the
process or provide relevant content to the City for use
on their own social media platforms. We have used this
approach as a low cost method of tapping into social
media, communicating important project information,
building community enthusiasm, and soliciting public
input.
Our team also collaborates with mySidewalk, a social
media platform, and MetroQuest, public involvement
software, both built to streamline the dispersal of project
information, facilitate community involvement, and
sustain engagement and momentum in a project. We will
review these, and other, media tools with South Bend to
determine if they are appropriate and they fit within the
project budget.
June 17, 2016 City of South Bend i Riverfront Parks & Trails Master Plan ? s
Specific public engagement meetings or workshops that
will be incorporated include:
Stakeholder Focus Groups
Over the course of the project, stakeholders will be
engaged through multiple rounds of focus groups
meetings during the Community Visit sessions. These
interviews will help identify key community values and
goals relative to the Parks and Trails system and will
allow feedback on alternatives and recommendations.
Stakeholder groups may include the following types of
groups, and will be determined as part of the Public
Involvement Plan:
• Elected officials & community representatives
• Key business or institutional leaders
• City administration
• Key partners & philanthropic organizations
• City & non -city agency staff
• Youth & school related organizations
Pop -Up Workshops
Potential non - traditional methods to facilitate public
input that could be incorporated into the Public
Involvement Plan include small, informal pop -up
workshops at events within the park system or elsewhere
within the City like popular community events or farmer's
markets. Kiosks soliciting feedback could be strategically
located within existing parks to encourage users to post
input. We will look for opportunities to schedule these
workshops in coordination with the community visits.
Community Forums
Community forums will serve to present information
and gather feedback from citizens at large. The purpose
for these meetings will be to ensure opportunities for the
general public to discuss their priorities and perceptions
surrounding the parks and recreation system. The forums
will also afford the opportunity to subtly educate the
public on the operation of the City's park system. It is
important to have initial meetings early in the process to
generate interest and excitement. It will be important to
get maximum media exposure to inform citizens of the
purpose and importance of the meetings and clearly note
time and locations. We suggest advance meetings with the
local news outlet to facilitate project articles and meeting
notices.
Responsibilities: For all public and stakeholder meetings
over the course of the project, the Consultant Team will
be responsible for developing primary meeting content
and facilitating community meetings and focus groups.
City staff and /or community leaders will be responsible
for contacting individual stakeholders and representatives,
and coordinating logistics, timing and communications
for planned meetings.
Deliverable: Public Involvement Strategy Memo
1.3 — Project Schedule Development
In conjunction with creating the Public Involvement Plan,
we will work with the City to develop the appropriate
schedule that includes the various public meetings
identified as well as allow for time for the project team to
design develop content and for associated City review of
materials prior to sharing with the public. Key milestones
for each phase of the project will be identified.
Deliverable: Project Schedule
Task 2: Analysis & Opportunities
(Information Gathering)
2.1— Data Collection
The Consultant Team will work with City staff to acquire
data necessary to conduct the analysis tasks and other
project needs identified in this scope of work. As part of
the RFP, the City has provided substantial background
information including plans such as the City of South
Bend 5 -Year Park Master Plan, 2014 Community Needs
Assessment Findings, among others. It is anticipated that
additional data will be needed from the City and may
include, but is not limited, to the'following:
• AutoCAD or ArcGIS base files
• Utility infrastructure within & around riverfront parks
• St. Joseph River hydraulic information
2.2 — Gaps and Future Needs Analysis
The Consultant Team will evaluate the City of South
Bend 5 -Year Park Master Plan (2014 -2018) and the 2014
Community Needs Assessment Findings to initiate further
discussion with the Project Team, identified stakeholders
and the public in order to specifically target the gaps and
future needs for the riverfront parks and trails systems.
2.3 — Community Visit #1
City /Stakeholder Workshop
The Consultant Team will facilitate City and key
stakeholders workshops to evaluate the vision for
the overall riverfront parks and trails system with
particular focus on those located in the downtown
area. During this workshop, the Consultant Team will
guide a PET Assessment to determine which elements
should be Preserved, Enhanced or Transformed, gain
an understanding of the community values from an
internal perspective, as well as discuss known priorities for
recreation facilities and programming, parks, trails and
open space development needs of the City.
Community Forum + Pop -up Workshop
The Consultant Team will facilitate a community forum
and pop -up workshop to present a high level overview
of the current South Bend parks and trails system,
review of previously completed studies and plans, and
solicit feedback on the desired future vision for the park
system. In addition, community members will be asked
to share issues and opportunities they see that influence
the future success of the park system. It is anticipated
at the community forum that an overview presentation
(approximately 30 minutes) will help orient community
members to the scope of the strategic planning activities,
why they are necessary and important, and how the
documents will be used to inform decision making. The
pop -up workshop(s) will be conducted at another location
with a less formal presentation attempting to collect
similar information.
Deliverable: Meeting notes
2.4 — Opportunities & Constraints Analysis
After Community Visit #1, the Consultant Team
will assemble and review all existing information and
integrate the insights from the City, stakeholders, and
the community. The Consultant Team will complete
an issues analysis that will synthesize, categorize, and
organize the critical issues relating to park improvement
and connectivity. This analysis will address at least the
following elements:
• Parks, recreation, & programming for both current &
anticipated needs
• Transportation systems & potential connections/
linkages
• Public Infrastructures — on -site & adjacent public
utilities including water service; sanitary sewer, &
storm sewer
• River characteristics — depths, currents, water level
fluctuation, seasonal patterns. & shoreline treatment
• Historical & cultural resources — both along the river
& within adjacent neighborhoods & commercial areas
Natural resources
Environmental concerns
Deliverable: The Consultant Team willgenerate a brief
Opportunities and Constraints memorandum with
supporting graphics. A City representative will distribute the
memo to the Project Team for its review and constructive
input.
2.5 — Community Visit #2
Community Visit #2 will be an extended 2 -3 day
community visit, where the consultant team will be
present in South Bend for a focused and intensive series of
work sessions. The community visit will include a focused
planning session with the Project Team, special workshop
sessions with key stakeholders, a community forum and
pop -up workshops. The anticipated meetings for this
community visit are described below.
Project Team Meeting (Draft Parks & Trails Master
Plan + Conceptual Plan Alternatives)
The Project Team will meet to discuss feedback from
the Opportunities and Constraints memorandum and
review initial draft master plan options as developed by
the Consulting Team prior to the community visit. Draft
design standards and Branding and Signage Strategy
options will also be shared with the Project Team.
June 17, 2016 City of South Bend / Riverfront Parks &Trails Master Plan
Based on the results of the Project Team meeting, the
Consultant Team will spend dedicated time further
developing a draft parks and trails master plan as well as
up to three (3) conceptual design alternatives each for
Howard Park, Seitz Park and a section of the Blue Ways
Trail. These elements will address the program and vision
and be developed and illustrated in a series of plans and
associated graphics that can be presented to the public for
feedback.
Deliverables: Alternatives plans, sketches, cross sections, and
graphics for public presentation
City/Stakeholder Workshop
The Consultant Team will review the draft Riverfront
Parks & Trails Master Plan and Conceptual Plan
Alternatives with the Project Team and identified
stakeholder groups in a series of meetings. Feedback will
be collected and refinements will be made in order for the
Consultant Team to present at the Community Forum
and Pop -up Workshop the following day.
Community Forum + Pop -up Workshop
The Opportunities and Constraints Analysis, draft
Riverfront Parks & Trails Master Plan, and Conceptual
Plan Alternatives will be presented at a community forum
and at a pop -up workshop at an existing event in the City.
The goal of these events will be to seek public input and
arrive at a preferred direction for the Riverfront Parks &
Trails Master Plan as well as the conceptual plans of the
three identified parks.
Deliverable: Meeting notes
Task 3: Master Plan Development
3.1 — Preliminary Riverfront Parks &Trails Master
Plan
With input from Community Visit #2, the Consultant
Team will develop the preliminary Riverfront Parks
& Trails Master Plan. The design will incorporate our
assessment of the social, physical, and environmental
drivers impacting successful redevelopment of the
riverfront area.
The plan will identify the infrastructure required to
support proposed uses including, but not limited to
vehicular, bicycle, and pedestrian circulation, parking,
stormwater management, and riverfront access. To best
explain the intended character of the redevelopment, the
Project Team will prepare illustrations and use precedent
images from other places to illustrate the Plans most
important and intriguing aspects.
38 www.smith9roupjjr.com
The parks and trail concepts will incorporate and address:
• . Placement of buildings & facilities
• Trails & sidewalks
• Playgrounds
• Seating
• Trees & landscape
• Natural features & habitats
• Lighting
• Signage
• Public art
Deliverable: Preliminary Riverfront Parks e'r Trails Master
Plan for public presentation
3.2 — Preliminary Conceptual Plans for Downtown
Focus Areas
After vetting the Conceptual Plan Alternatives with the
City, stakeholders and public at Community Visit #2,
preliminary conceptual plans for Howard Park, Seitz Park
and a portion of the Blue Ways Trail on the east side of
the St. Joseph River will be developed to a level of design
that can quickly be engineered and implemented for
construction in 2017.
Preliminary cost estimates will be developed for the three
focus areas.
Deliverable: Preliminary Conceptual Plans for Downtown
Focus Areas for public presentation and preliminary cost
estimates for three focus areas
3.3 —Preliminary Implementation Strategy
Critical to any successful parks and trails plan is the ability
to outline the action steps necessary to move the plan
from concepts into reality. Experience tells us that there
are two critical factors to making this happen: clarity
around outcomes and roles of involved parties; and careful
consideration and planning relative to the resources
required (financial and otherwise) to make the policy
or development vision happen. The Project Team will
provide recommendations, including:
• Prioritization of realistic & catalytic projects &
development types
• Cost estimates for priority actions & short term
projects
• Regulatory permitting requirements
• Short, intermediate & long -term phases
Deliverable: Preliminary Implementation Strategy for public
presentation
3.4 — Preliminary Design Standards and Branding
and Signage Strategy
Upon feedback received during Community Visit #2, the
Consultant Team will further refine the design standards
and branding and signage strategy. Design standards will
address at a minimum: trail design, sidewalk design, site
furnishings, landscape, signage use, design principles
for new structures and parking areas. The intent is that
these standards can be applied to all parks managed by
the City of South Bend Parks & Recreation Department.
Adding to the consistent theme throughout the riverfront
parks, the Consultant Team will develop a branding and
standard signage strategy addressing park name signage,
directional and wayfinding signage, and facilities signage.
Deliverable: Preliminary Design Standards and Branding �r
Signage Strategy far public presentation
3.5 — Community Visit #3
The Consultant Team will meet with the Project Team,
stakeholder groups and the community through a
community forum and pop -up workshop to review
the preliminary Riverfront Parks & Trails Master Plan,
conceptual plans for the three focus areas, implementation
strategy, design standards, and branding and signage
strategy. Feedback will be solicited on all items to be
incorporated into the final plans and strategies.
Deliverable: Meeting notes
3.6 — Final Riverfront Parks & Trails Master Plan
and Conceptual Plans
Given the feedback and input from the Project Team,
stakeholder groups, and the community during
Community Visit #3, the Consultant Team will refine the
Riverfront Parks & Trails Master Plan and Conceptual
Plans for the three focus areas. The final plans will
communicate the vision and recommendations in graphic
format (color rendered plan, character cross sections /3D
renderings).
Cost estimates for the three focus areas will be revised per
plan changes.
Deliverables: Final Riverfront Parks & Trails Master Plan
and Conceptual Plans far Downtown Focus Areas far public
presentation. Final cost estimates for the three focus areas.
3.7 — Community Visit #4
Community Forum
The Consultant Team will present the final Riverfront
Parks & Trails Master Plan, Conceptual Plans for the three
focus areas, implementation strategy, design standards,
and branding and signage strategy during the final
community visit. This will be the last formal opportunity
for community members to react and comment on the
revised plans and strategies.
Deliverable: Meeting notes
3.8 — Master Plan Documentation
The Consultant Team will prepare a full draft of the
Riverfront Parks & Trails Master Plan. This draft will
include all a summary of the planning process and build
linkages to the City of South Bend 5 -Year Park Master
Plan.
A draft of the Riverfront Parks & Trails Master Plan
will be circulated to the Project Team and other vital
stakeholders for their review (as determined by the City).
The review period is typically 2 -3 weeks in duration, after
which time the Consultant Team will collect comments.
A meeting with the Project Team will be held to review
received comments and if necessary decide to how to
resolve and discrepancies between them. The Consultant
Team will then refine the plan into a final draft for
acceptance by the City.
Deliverable: Riverfront Parks & Trails Master Plan Report
• In both digital & hard copy format (PDF, original docu-
ment file & S hard copies)
• All relevant materials that were used in previous phases �r
presentations
• Digital copies of allgraphics produced during the process
June 17, 2016 City of South Bend / Riverfront Parks &Trails Master Plan 39
EXHIBIT B
Contractor's Affidavit
[See attached.]
When the prospective Contractor is unable to certify to any of the statements below, it shall attach an explanation to this Affidavit.
CONTRACTOR'S NON - COLLUSION AND NON - DEBARMENT AFFIDAVIT,
CERTIFICATION REGARDING INVESTMENT WITH IRAN, EMPLOYMENT ELIGIBILITY
VERIFICATION, NON - DISCRIMINATION COMMITMENT AND CERTIFICATION OF USE
OF UNITED STATES STEEL PRODUCTS OR FOUNDRY PRODUCTS
(Must be completed for all quotes and bids. Please type or print)
STATE OF _Michigan )
) SS:
Washtenaw COUNTY )
The undersigned Contractor, being duly sworn upon his /her /its oath, affirms under the penalties of perjury that:
1. Contractor has not, nor has any other member, representative, or agent of the firm,
company, corporation or partnership represented by him, entered into any combination, collusion
or agreement with any person relative to the price to be bid by anyone at such letting nor to
prevent any person from bidding nor to induce anyone to refrain from bidding, and that this bid
is made without reference to any other bid and without any agreement, understanding or
combination with any other person in reference to such bidding. Contractor further says that no
person or persons, firms, or corporation has, have or will receive directly or indirectly, any
rebate, fee, gift, commission or thing of value on account of such sale; and
2. Contractor certifies by submission of this proposal that neither contractor nor any of its
principals are presently debarred, suspended, proposed for debarment, declared ineligible, or
voluntarily excluded from participation in this transaction by any Federal department or agency;
and
3. Contractor has not, nor has any successor to, nor an affiliate of, Contractor, engaged in
investment activities in Iran.
a. For purposes of this Certification, "Iran" means the government of Iran and any agency or
instrumentality of Iran, or as otherwise defined at Ind. Code § 5 -22- 16.5 -5, as amended from
time -to -time.
b. As provided by Ind. Code § 5 -22- 16.5 -8, as amended from time -to -time, a Contractor is
engaged in investment activities in Iran if either:
i. Contractor, its successor or its affiliate, provides goods or services of twenty million
dollars ($20,000,000) or more in value in the energy sector of Iran; or
ii. Contractor, its successor or its affiliate, is a financial institution that extends twenty
million dollars ($20,000,000) or more in credit to another person for forty -five (45)
days or more, if that person will (i) use the credit to provides goods and services in
F- Non - Collusion Non - Debarment Affidavit Non Iran Form 2012
the energy sector in Iran; and (ii) at the time the financial institution extends credit, is
a person identified on list published by the Indiana Department of Administration.
4. Contractor does not knowingly employ or contract with an unauthorized alien, nor retain
any employee or contract with a person that the Contractor subsequently learns is an
unauthorized alien. Contractor agrees that he /she /it shall enroll in and verify the work eligibility
status of all of Contractor's newly hired employees through the E- Verify Program as defined by
I.C. 22- 5- 1.7 -3. Contractor's documentation of enrollment and participation in the E- Verify
Program is included and attached as part of this bid/quote; and
5. Contractor shall require his/her /its subcontractors performing work under this public
contract to certify that the subcontractors do not knowingly employ or contract with an
unauthorized alien, nor retain any employee or contract with a person that the subcontractor
subsequently learns is an unauthorized alien, and that the subcontractor has enrolled in and is
participating in the E- Verify Program. The Contractor agrees to maintain this certification
throughout the term of the contract with the City of South Bend, and understands that the City
may terminate the contract for default if the Contractor fails to cure a breach of this provision no
later than thirty (30) days after being notified by the City.
6. Persons, partnerships, corporations, associations, or joint venturers awarded a contract by
the City of South Bend through its agencies, boards, or commissions shall not discriminate
against any employee or applicant for employment in the performance of a City contract with
respect to hire, tenure, terms, conditions, or privileges of employment, or any matter directly or
indirectly related to employment because of race, sex, religion, color, national origin, ancestry,
age, or disability that does not affect that person's ability to perform the work.
In awarding contracts for the purchase of work, labor, services, supplies, equipment, materials,
or any combination of the foregoing including, but not limited to, public works contracts .
awarded under public bidding laws or other contracts in which public bids are not required by
law, the City, its agencies, boards, or commissions may consider the Contractor's good faith
efforts to obtain participation by those Contractors certified by the State of Indiana as a Minority
Business ( "MBE ") or as a Women's Business Enterprise ( "WBE ") as a factor in determining
the lowest, responsible, responsive bidder.
In no event shall persons or entities seeking the award of a City contract be required to award a
subcontract to an MBE /WBE; however, it may not unlawfully discriminate against said
WBE /MBE. A finding of a discriminatory practice by the City's MBE /WBE Utilization Board
shall prohibit that person or entity from being awarded a City contract for a period of one (1)
year from the date of such determination, and such determination may also be grounds for
terminating the contact for which the discriminatory practice or noncompliance pertains.
7. The undersigned contractor agrees that the following nondiscrimination commitment
shall be made a part of any contract which it may henceforth enter into with the City of South
Bend, Indiana or any of its agencies, boards or commissions.
F- Non - Collusion Non - Debannent Affidavit Non Iran Form 2012
Contractor agrees not to discriminate against or intimidate any employee or applicant for
employment in the performance of this contract with privileges of employment, or any matter
directly or indirectly related to employment, because of race, religion, color, sex handicap,
national origin or ancestry. Breach of this provision may be regarded as material breach of
contract.
I, the undersigned bidder or agent as contractor on a public works project, understand my
statutory obligations to the use of steel products or foundry products made in the United States
(I.C. 5- 16 -8 -1). I hereby certify that I and all subcontractors employed by me for this project will
use steel products or foundry products on this project if awarded. I understand that violations
hereunder may result in forfeiture of contractual payments.
I hereby affirm under the penalties of perjury that the facts and information contained in the foregoing bid for
public works are true and correct.
Dated this —� day of J'L 20J
SmithGrou JJR, Inc.
Con cto idder it
Signature of Contractor /Bidder or Its Agent
Patrick M. Doher, Senior Vice President
Printed Name and Title
Subscribed and sworn to before me this day of C , 20
My Commission Expires 3 h S/ 17
!�
Notary Pu lic
County of Residence Kim TFIEASTER
NOTARY PUBLIC, STATE OF IW
COUNTY OF JACKSON
MY COMMISSION EXPIRES Mu 16, 2018
ACTING IN COUNTY OF
F- Non - Collusion Non - Debarment Affidavit Non Iran Form 2012
A� �®
CERTIFICATE OF LIABILITY INSURANCE
DATE IYYYY)
I
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
/2016
o7 /25 /zols
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.
IMPORTANT: If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to
the terms and conditions of the policy, certain policies may require an endorsement. A statement on this certificate does not confer rights to the
certificate holder in lieu of such endorsement(s).
PRODUCER
CONTACT
NAME:
Marsh USA Inc.
PHONE FAX
One Towne Square, Suite 1100
IA /C (A /C No):
E-MAIL
ADDRESS:
Southfield, MI 48076
Attn: detroit.certrequest @marsh.com
EACH OCCURRENCE
$ 1,000,00
INSURER(S) AFFORDING COVERAGE
NAIC #
INSURERA: Hartford Casualty Insurance Company
29424
J21060 -- SIR -16 -17 MI -Ann SA1M2.
INSURED
SmithGroupJJR,lnc.
INSURERS : N/A
N/A
INSURER C: N/A
N/A
201 Depot Street, Second Floor
INSURER D: Hartford Insurance Company of the Midwest
37478
Ann Arbor, Ml 48104 -1019
INSURER E: Lloyd's of London
1122000
INSURER F :
COVERAGES CERTIFICATE NUMBER: CHI- 006641139 -01 REVISION NUMBER:3
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
ILTR
TYPE OF INSURANCE
AD�I
Sjgggn
POLICY NUMBER
(MM /DDNYYYI
(MM/DDIYYYYI
LIMITS
A
X
COMMERCIAL GENERAL LIABILITY
83 UUN LP2277
05/15/2016
05/15/2017
EACH OCCURRENCE
$ 1,000,00
CLAIMS -MADE M OCCUR
PREMISES (Ea occurrrence)
$ 300,00
MED EXP (Any one person)
$ 10,00
PERSONAL & ADV INJURY
$ 1.000,001
GEN'L
AGGREGATE LIMIT APPLIES PER:
GENERAL AGGREGATE $ 2,000,001
1
POLICY PE O LOC
R
PRODUCTS - COMP /OP AGG
$ 2,000,001
$
OTHER:
AUTOMOBILE
LIABILITY
COMBINED SINGLE LIMIT $
fEa accident)
BODILY INJURY (Per person)
$
ANY AUTO
ALL OWNED SCHEDULED
AUTOS AUTOS
BODILY INJURY (Per accident)
$
PROPERTY DAMAGE
(Per accident)
$
NON -OWNED
HIRED AUTOS AUTOS
$
I
UMBRELLA LIAB
OCCUR
EACH OCCURRENCE
$
HCLAIMS-MADE
AGGREGATE
$
EXCESS LIAR
DED I I RETENTION $
$
D
WORKERS COMPENSATION
AND EMPLOYERS' LIABILITY
ANY PROPRIETOR /PARTNER /EXECUTIVE YNI❑N
OFFICER /MEMBER EXCLUDED?
(Mandatory in NH)
NIA A
83 WE PP2105
AZ, CA, CO, DC, GA, IL, KS, ME, MN,
MO, NC, PA, TX, WI
05/15/2016 05/1512017
I
X STATUTE ER I
E.L. EACH ACCIDENT
$ 1,000,00
E.L. DISEASE EA EMPLOYEE
$ 1,000,001
If yes, describe under
DESCRIPTION OF OPERATIONS below
E.L. DISEASE - POLICY LIMIT $ 1,000,001
E
Architects & Engineers
FINPA1500129
09/15/2015
09/15/2016
Each Claim/General Agg 1,000,00
Professional Liability
Self- Insured Retention $1,150,00
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES (ACORD 101, Additional Remarks Schedule, may be attached if more space is required)
City of South Bend, Indiana is included as additional insured where required by written contract with respect to general liability.
City of South Bend, Indiana
Dept. of Community Investment - Contract Administrator
227 W. Jefferson Blvd., Ste. 1400 S.
South Bend, IN 46601
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
ACCORDANCE WITH THE POLICY PROVISIONS.
AUTHORIZED REPRESENTATIVE
of Marsh USA Inc.
John C Hurley
@ 1988 -2014 ACORD CORPORATION. All rights reserved.
ACORD 25 (2014/01) The ACORD name and logo are registered marks of ACORD