HomeMy WebLinkAboutChange Order No 1 - Coquillard Safe Routes to School - Proj No 114-0061316 COUNTY-Crry BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND. INDIANA 46601-1830
CITY OF SOUTH BEND PETE BUTTIGIEG, MAYOR
BOARD OF PUBLIC WORKS
July 12, 2016
Mr. Christien Reynolds
EQDOT LaPorte District
315 E. Boyd Blvd
LaPorte, IN 46350
PHONE 574/235-9251
FAx 574/235-9171
RE: Change Order No. 1 — Coquillard Safe Routes to School — Project No. 114-066
Dear Mr. Reynolds:
The Board of Public Works, at its meeting held on July 12, 2016, approved the above
referenced Change Order for an increase of $2,184.00, bringing the current contract amount
to $496,828.00.
Enclosed is a copy of the Change Order for your records.
If you have any further questions regarding this matter, please call this office at (574) 235-
9251.
Sincerely,
Linda M. Martin, Clerk
Enclosure
GARY A. GILOT DAVID P. RELOS ELIZABETH A. MARADIK JAMES A. MUELLER THERESE J. DORAU
,itract No:R -37498 Change Order No.: 001
INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract Information Contract No.: R -37498 Letting Date:09/02/2015
District:LAPORTE DISTRICT AE:Reynolds, Christien PE/S:Forgey, Ryan Status:Draft
Change Order Information Change Order No.: 001
EWA: Y or Force Acct: N
Date Generated: 06/09/2016 Date Approved: 00/00/0000
Reason Code: ERRORS & OMISSIONS, Item Related
Description: Add Pay Item for Construction Sign, A
Original Contract Amount $ 494,644.00
Current Change Order Amount $ 2,184.00
Percent: 0.442 %
Total Previous Approved Changes $ 0.00
Percent: 0.000 %
Total Change To -Date $ 2,184.00
Percent: 0.442 %
Modified Contract Amount $ 496,828.00
Time Extension Information
Date Initiated 00/00/0000 Date Completed 00/00/0000
Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description:
Current Time Extension SS Days 0 SP Days 0 SP Days Value $ 0.00
Previous Time Approved SS Days by AE: DCE: SCE: DDCM:
SS Days SP Days Value $
Revised Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SS Date 00/00/0000 or SP Days 0
Contract NOR -37498
Change Order No:001
Contract:
Project:
Change Order Nbr:
Change Order Description:
Reason Code:
INDIANA
Department of Transportation
R -37498
1400635 - State: 140063500LC4
001
Add Pay Item for Construction Sign, A
ERRORS & OMISSIONS, Item Related
Date:07/06/2016
Page: 3
CLN PCN PLN Item Code Unit Unit Price CO City Comment Amount Change
0039 1400635 0039 801-06640 EACH 156.000 14.000 C Amount:$ 2,184.00
Item Description: CONSTRUCTION SIGN A
Supplemental Description l:
Supplemental Description2:
Total Value for Change Order 001 = $ 2,184.00
Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended.
General or Standard Change Order Explanation
Construction Sign Type A was listed in the plans but a pay item was missing from the schedule of pay items. Construction Signs Type A are
needed for the project and shall be placed throughout the project. The contractor has requested this change order due to signs being called out
on plans but no pay Item for them.
Change Order Explanation for Specific Line hem
It is the intent of the parties that this change order is full and complete compensation for the work describe above.
Notification and consent to this change order is hereby acknowledged,
Contractor.,Peke_ J2'let, .1 /j/
_ �,.4 Signed By: $A( 00/N
Date,
NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system.
Contract NOR -37498 INDIANA
Change Order No:001 Department of Transportation
APPROVED FOR LOCALP&6AC NNCY
ID
Board of Public Works_
(SIGNATURE) (TITLE) (DATE)
A-t._ JUL,� 2 �J hA--
(SIGNATURE) (TITLE)
SUBMITTED FOR CONSIDERATION
PE/S
Date:07/06/2016
Page: 4
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Approval Level Name of Approver Date Status
Board of "C Works
JUL 1 2016
Don Dietz
From: Rob Nichols <rnichols@rieth-riley.com>
Sent: Tuesday, April 26, 2016 3:56 PM
To: Roger Nawrot; Don Dietz
Subject: Metronet Relocation
Don/Roger,
As discussed in today's meeting, the cost for us to do the relocation of the Metronet is $5,200/day. We expect it to take
a total of three days for a total of $15,600.
Thanks,
Rob
2UUA94UX Coxsmnow Co.. Ims
Robert Nichols
Cell: (574)210-0858
This e-mail and any attachments thereto, are intended only for use by the addressee(s) named herein and may
contain legally privileged and/or confidential information. If you are not the intended recipient of this e-mail (or
the person responsible for delivering this document to the intended recipient), you are hereby notified that any
dissemination, distribution, printing or copying of this e-mail, and any attachment thereto, is strictly prohibited.
If you have received this e-mail in error, please respond to the individual sending the message, and permanently
delete the original and any copy of any e-mail and printout thereof.
LAWSON-FISHER ASSOCIATES P.C. Job # 3i 7 2? Sheet —of_
525 WEST WASHINGTON AVENUE
SOUTH BEND, INDIANA essoi By � � Date
Ck'
N2.� ��Ir` / d Date
Project tC Subject {ail o T % A
5 aOKOXI Sf-✓ Lvtc4w... J
C al-t6-- 0 t'% F tc (S rc• S Lt au
30
RGv%d W
Mr. Ryan S. Forgey, P.E.
Troyer Group
550 Union Street
Mishawaka, IN 46544
RE: R-37498-A Coquillard Project
Change Order No. 1 - Construction Signs, Type — A, Revision No. 2
Dear Mr. Forgey,
June 24, 2016
The following is Rieth-Riley's cost for Temporary and Mobile Construction Signs, Type -A.
Type -A signs were not included in the original contract and are required at each intersection for
maintenance of traffic safety during construction.
Item #
Qty
Unit
Description
Unit Price
Total
39
14
EA
Construction Sign, Type A
$156.00
$2,184.00
TOTAL
$2,184.00
Attached is all the documentation which supports this pricing. Please let me know if you have
any questions or require any additional information.
Respectfully,
Rv-4; ew A,va.ra a -
Ruben Alvarado
Estimator/Project Manager
Rieth-Riley Construction
25200 S.R. 23 • SOUTH BEND, INDIANA 46614 • TELEPHONE: (574) 288-8321 • FAX: (574) 233-3464
06-24-'16 09:46 FROM- TCS Office
\Traffic
5747727002 T-590 1`0001/0001 F-799
Change Order # 1 Revised
Letting Date CO Date Contract Number
/Control
S Specialists, Inc
9/2/201ti5/31/2016 R-37498-A
Project Location
Attn: Rubin Alvarado
Safe School Route
Rieth- Riley ( South Bend)
Coquillard School, St John School, & Kennedy Center
St. Jose h Co.
REP I Quote Valid Start Date
Completion Datel
Closure Date
Closure Days
Calendar Days
TJT 45 Days
63
Line Item Number Description
Quantity
Unit Price
Total
C01-1 801-06640 Construction Sign, A
1
1
14 Ea.
$134.00 Ea.
$1.876.00
GENERAL NOTES:
1 -Above Quote is based on plans and specifications at time of bid. Calendar days maybe adjusted upon request
2. Quote Valid for 45 calendar days ONLY. Contracts awarded after 45 days may require a requote.
3. Changes by Engineer/Contractor require approved change order.
4. Items not paid by owner will be invoiced to contractor at a daily rate, based on adjusted Item unit price.
5. Contact TCS, Inc for re -quote if all items are not accepted,
6. Bid Bond not included, add 1% of total if required.
Signatory Contractor of LIUNA, Certified WBE, Member of ATSSA & BBB
305 W. Hamilton Dr. Knox, IN 46534
574-772-7001 Office
574-772-7002 Fax
219-916-5585 Tracey Cell
219-916-4613 Barry Cell
tcsinc .tcspecialists net
6/24/2016
App ved By: Tra y Triska Date
Accepted By:
Date
Page i of 1
Date
Name
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
7-5-2016
Blair Bennett
Department Engineering
Division/Bureau Public Works
BPW Date 7-12-2016 Phone Extension 5998
Required Prior to Submittal to Board
Legal ® Attorney Name: Michael Schmidt
Controller ❑ Controller review is required for all Contracts $5,000.00 or more and
greater than one year in length per the City Purchasing Policy
Purchasing ❑
I Check the Appropriate Item Type — Required for All Submissions
❑
Agreement
❑ Contract ❑ Proposal ❑ Addendum
❑
Professional Services
❑ Resolution
❑
Bid Opening
❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑
Quote Opening
❑ Quote Award
®
Change Order No. 1
❑ C/O & PCA No. ❑ PCA
❑
Ease/Encroach.
❑ Traffic Control:
❑
Other:
Company or Vendor Name
New Vendor
MBE/WBE Contractor
MBE/WBE Contractor Requested
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Purpose/Description
Amount of X Increase
❑ Decrease
Previous Amount
Current Percent of Change:
New Amount
Total Percent of Chance:
Copy
Original
❑
❑
❑
❑
❑
❑
Information
INDOT
❑ Yes ® No ❑ If Yes, Approved by
❑ MBE ❑ WBE
❑ No ❑ Yes Name of Company
Coquillard Safe Routes to School
ENG: 114-066 INDOT: DES# 1400635
251-0608-380.10-99
$494,644.00
It
Sidewalk Replacement in area surround Coquillard Primary
Center
❑ Required Contractor's Certification Forms Attached (Non -
Collusion, Non -Discrimination, Non -Debarment, E-Verify, Iran, etc.)
ired For
2,184