HomeMy WebLinkAboutagenda item 2015 1210 rdc 03bClaims submitted Explanation of Project
Redevelopment Commission Claims submitted December 10, 2015 for approval
324 RIVER WEST DEVELOPMENT AREA
DLZ
Torti Gallas And Partners
Kolata Enterprises, LLC
Rich and.Associates, Inc.
Weaver Consultants Group
L.L. Geans Construction Co.
BSCO, Inc.
AEP
RealAmerica Development
Majority Builders Inc.
Rieth Riley Construction
Abonmarche
American Structurepoint, Inc.
429 FUND RIVER EAST DEVELOPMENT AREA
Abonmarche Consultants
Walsh & Kelly, Inc.
430 FUND SOUTH SIDE TIF AREA #1
DLZ
Subtotal by Column
530.00 Engineering
8,723.40 Downtown Mixed Used Block City
1,575.00 Contractual Services -Environmental
13,976.00 Parking Study for Downtown
1,,545.58 Ivy Tower
23,400.00 Excavation, tear out, and concrete work
128,078.00 Equipment Purchase for Nella Corp.
1,615.82 Franklin & Stull St.
21,330.00 The LaSalle Apartments
268,291.87 Ignition Pk Infrastructure, Ph 1C: Division B
1,312,312.14 Memorial North Parking Lot
1,723.75 Ignition Pk lnfrastruction, Ph 1C /Ignition Pk, Building 1 & 2
19,486.95 Ignition Pk lnfrastruction, Ph 1C -Div. B
500.00 Colfax & Hill Drainage Improvements
12,174.17 Hill St. Alley Improvements
1,022.00 Ireland RW Acquisition
$1,816,284.68