HomeMy WebLinkAbout2008-12-03 Redevelopment Authority MinutesSOUTH BEND REDEVELOPMENT AUTHORITY
REGULAR MEETING
December 3, 2008
1:30 p.m.
Presiding: Jose Alvarez
1308 County-City Building
227 West Jefferson Boulevard
South Bend, IN 46601
The December 3, 2008 Regular Meeting of the Redevelopment Authority was called to order at
1:30 p.m. by its President, Jose Alvarez. There was a quorum present.
1. -ROLL CALL
Members Present: Mr. Jose Alvarez, President
Ms. Carolyn V. Pfotenhauer, Vice President
Mr. Ray Thomas, Secretary
Redevelopment Staff: Mr. Don Inks, Director of Economic Development
Mrs. Jenny Hullinger, Recording Secretary
Ms. Cheryl Greene, Legal Counsel
Others: Mr. Rich Hill, Baker & Daniels
Mr. Randy Rompola, Baker & Daniels
2. APPROVAL OF MINUTES
a. Approval of the minutes of November 19, 2008
Upon a motion. by Carolyn Pfotenhauer, seconded by Jose Alvarez, and
unanimously carried, the Authority approved the Minutes of the Regular Meeting
of November 19, 2008.
3. CLAIMS
a. Baker & Daniels
Century Center Bond $123,155.10
Mr. Inks said the total claim was over $136,000 and Baker and Daniels gave us a
10% discount to bring the amount down to $123,155.10. This is above and beyond
the letter we had brought to the Authority at the last meeting, which indicated that
the amount would not be more than $110,000. Almost immediately after the last
meeting Don- received a call from Randy Rompola wanting to correct the letter
because they had since totaled up their hours and they were in excess of the
amount stated in their letter. They then delivered the letter and billing you have.
Ms. Greene said the legal department reviewed the entries. She. said this was an
unusual transaction with an initial start of TIF related funding which then changed
to different financing. We then had a change in State law and issues related to the
County and the financial market. All of the entries are consistent with all of the
issues. Ms. Greene said the. legal department recommends approval of the claim.
The Redevelopment Authority
December 3, 2008 Meeting Minutes
Upon a motion by Ms. Pfotenhauer, seconded by Mr. Alvarez, the Authority ,
approved the claim, as presented.
Mr. Hill said he has never seen a situation like this one. in the more than twenty
years of his practice. He said if it had been another situation he might have
recommended stopping the process. He was hearing from the Board of Managers
of Century Center that if the bond was not sold there would be health and safety
issues as well as a loss of bookings. The work needed to be done. Some of the
problems that slowed the sale were bond insurers were down rated and the rating
agencies then took an entirely different approach. The kinds of information the
rating agencies were requesting was different from anything in the past. There was
a change in the structure of the financing because there was not enough TIF
money to use, and then there were questions on the scope of the financing from
the Hotel/Motel Tax Board. Baker & Daniels spent considerably more time than
anticipated on those issues. At certain times there was no bond market. There
were two considerations, one, that there was sufficient interest in bonds, and two,
the interest rate for bonds had to be reasonable. They were very happy that the
bond sold. and closed, it was one of the few that did. The work on the bond
actually took 400 hours over 7 months to complete. In May they had assumed it
would have been a quick transaction.
Mr. Rompola said if you looked at where we were in May, and if the State had not
held up the process because of TIF issues and property tax issues, the bond would
probably have sold before the summer with or without the TIF. It was the summer
when everything fell apart: the market, the rating agencies and the change in
interest rates. Baker and Daniels spent a lot of time in the. summer working on the
financing. Mr. Rompola said all of the time that was spent on the bond was not in
their accounting system when he provided the memo on the costs for the last
Authority meeting. There was more time spent before closing dealing with some
of the County issues.
Mr. Hill said the day of closing was the drop dead date for ordering some of the
equipment that was needed for the 2009 construction schedule.
Ms. Pfotenhauer said she reviewed the bill and saw that it was reasonable. She
was concerned that if we work with Baker and Daniels in the future that both
sides make a concerted effort to communicate more and an effort to really control
the costs, and that the estimates that we are given are as up-to-date as humanly
possible. Mr. Hill said he agreed and said in the future he would have more
communication with the Authority.
2
H:\WPDATA\AUTHORTY\12032008.MIN.DOC
The Redevelopment Authority
December 3, 2008 Meeting Minutes
4. NEXT MEETING DATE: December 17, 2008
5. ADJOURNMENT
There being no further business to come before the Redevelopment Authority the meeting
was adjourned at 1:40 p.m.
~._---
~~
e Alvarez, President
~~ /
Donald Inks, Director
H:\W PDATAW UTHORTY~12032008.MIN.DOC