Loading...
HomeMy WebLinkAboutPersonnel & Finance Committee Report - 3rd Quarter 2014CITY OF SOUTH BEND, INDIANA PERSONNEL & FINANCE PROGRESS REPORT — DOLLARS SPENT September 30, 2014 Funding Project (amount and Q1 Q2 Subtotal Q4 (Projected) Grand Total (report 3/24) (report 7/9) (report 11/7) source) $3.3 Million Fund $0 spent; Add'I $1,118,961 Adsp 227 *; $657,115 spent; $244,000 f enc /spent for nt Vacant & $3,228,519 Fund encumbrance in $86,715 spent; enc on $4,554,565 demo (opening bid $6.7 million Jan but reduced add'I $1,147 750 deconstruction Abandoned 212 &HOME; to $380,827 in encumbrance in $2,545,489 spent or scheduled for encumbered or Housing $178,410 Donation encumbered 11/20); $600,000 spent Fund 217 May to reflect process * ** more enc; enc /spent for Tota1C�'6.7i�ni11ion0 proper funding $559,400 enc in rehab source process $4.2M Fund 412; $4.2 million from Smart $1.7 Fund 426 but $0 spent; $95, 100 $73,926 spent; $972,960 spent; Fund 412 Streets/ 2- changed to $1.6M encumbered; $1,798,861 enc.; $1,817,213 $4,047,351 Add'I $150,000 encumbered or Way Streets based on lower cash $111,340 add'I $446,119 encumbered; spent or encumbered spent; expect to use (Downtown) than expected encumbrance in enc. in process $1,183,252 enc encumbered the $1.6M from TotalC$5.89nillionM process in process Fund 426 in 2015 TotaIZ5.82nillionM Private funding for Anti - Violence Group Violence -0- -0- -0- -0- -0- -0- Intervention Workforce $69,911 Fund 404 ** $0 spent; $69,911 $69,911 spent -0- $69,911 -0- $69,911 spent Development encumbered spent Encumber remaining $1.95M Fund 227; $0 spent; $0 $38,890 spent; $258,300 $1,991,700 for $2,250,000 Corridors $300,000 Fund 412 $0 s ent; 0 p $ encumbered; $219,410 spent or Corridor encumbered or Totalll$Z250,0000 encumbered $258,300 enc. In encumbered encumbered streetscape spent process improvements — bid opening 10/23/14 *Includes $300,000 for deconstruction * *Funds encumbered in 2013, but won't be spent until 2014. ** *Opening bids for deconstruction in July. Sewer bond and capital funds 642, 647, 659, 661, 665 Funding Project (amount and Q1 Q� Q3 Subtotal Q4 (Projected) Grand Total (report 3/24) (report 7/9) (report 11/7) source) 311 Call $479,949 from Fund $93,751 $120,088 $112,689 $326,528 $110,000 $436,528 Center 101 -104 Infrastructure $1.1 million from $1.1 million (Curbs & Fund 404/202 $101,010 $102,296 $432,561 $635,867 $464,113 encumbered or Sidewalks) spent No 2014 Sewer Bond to be issued — The CSO LTCP will be reconsidered n/a n/a n/a n/a n/a n/a based on need in 2015 *Includes $300,000 for deconstruction * *Funds encumbered in 2013, but won't be spent until 2014. ** *Opening bids for deconstruction in July. Sewer bond and capital funds 642, 647, 659, 661, 665 Personnel & Finance Progress Report Question Responses for 3rd Quarter 2014 • Curbs & Sidewalks - 51.100.000 from Fund 4041COM /Fund 202 MVH How many applications do we have pending? (Jan 2014) There are 114 properties in the current year's program to be addressed this year. Of those, 58 are being done by the internal curb & sidewalk concrete crew and 56 are being done under contract. (July 2014) There are currently no applications pending for the 2014 program. Of the 114 application that were active as of January 2014, 14 applicants have requested to leave the program mainly due to financial concerns. Of the remaining applicants 50 are being serviced by the City crew and 50 are being serviced by the City's contractor. When will work begin? (Jan 2014) Weather permitting our internal crew will begin working in mid - April. Contract will be let in April with work proceeding by mid -May. (July 2014) The City crew began work in the first week of April. The City awarded the 2014 Curb & Sidewalk contract to Premium Concrete on May 27, 2014. A pre- construction meeting was held on June 3rd and they are proceeding with their work on July 14. A schedule for the internal work is currently in place, and somewhat dynamic due to weather considerations. A schedule will be developed and secured from Premium Concrete (the City's contractor) to ensure that they are finishing their work in a timely manner. How many residents have we served? 2011 = 40 properties 2012 = 56 properties 2013 = 58 properties 2014 = 93 properties (November 2014) For 2014, 93 properties will be served by the program between contract and in -house crews. Please see attached list of 2014 progress to date. The highlighted locations are still under construction. • Vacant & Abandoned - $2 Million from Fund 227 (Loss Recovery) How many homes remain from the original report? The number of properties currently on the V &A list total 1252. This is due to continuous updates occurring. The outcomes as of 10/8/2014 are as follows, and this count appears on the website and is updated regularly. Count of houses: 197 Houses Repaired 319 Houses Demolished 4 Houses Deconstructed 6 CDC Partner Houses 62 State Blight Elimination Program 18 Houses under Contract for Demolition 6 Houses under contract for deconstruction 612 Tota I What is our average cost per demolition? Prior to June 24, 2014 the average cost per demolition was $6,004. This amount is reflected in the three existing demolition contracts which cover a total of 219 properties. The winning bid from the June 24, 2014 Board of Public Works meeting for 81 properties had an average cost of $14,170. Taking this last bid into account and the previous 3 contracts, the new average is $8,209. Work is progressing on the next anticipated bid award date of November 20, 2014 with an expectation that there will be 100 -110 properties included. It is expected that the average cost may increase to an amount closer to $15,000. The increase can likely be attributed to: the limited number of demolition contractors available to work with and familiar with residential demolition; the number of those contractors which will still be under contract with the City for demolition work; the amount of asbestos and thus environmental disposal costs. Per Renovation? The 187 houses repaired have all been done by private owners. This information is not available to the City. The 6 properties being rehabbed by Partners are as follows: the NNN has 2; Habitat 1; SBHF 2; and the NNRO 1. Once the properties are close to completion the amounts of the rehabs will be known and shared. How much was budgeted for the Deconstruction program? $300,000 What fund was used? Fund 227 Loss Recovery How is that program going? The Board of Public Works award date of July 22, 2014 resulted in 1 bid response from Jackson Services. As of 10/8/2014, 2 properties have been deconstructed. The total amount of the bid for 10 properties was $244,000. • Anti - Violence How much was budgeted for this program? There is currently no public funding associated with the Group Violence Intervention Strategy (GVI). Funding is provided by private donations. What fund was used? None How are we measuring progress? The following KPI's are reported every month: Total Part 1 Crimes Aggravated Assault- Firearm Persons Shot The activities in connection with the Group Violence Intervention Strategy have been extensive. The group has worked with David Kennedy and other officials from John Jay College (JJC) on anti - violence strategies. The City has hosted officials from JJC and members of the GVI working group have made several trips to Chicago to witness the work done there. In addition, three members of the South Bend Police Department and an Assistant U.S. Attorney from the South Bend office were able to attend a convention in New Orleans to learn from other cities doing this kind of work. • Corridors What was the amount budgeted for work on LWW and Western? $2,250,000 What fund was to be used? Fund 412 - $300,000 (Engineering) The Board of Public Works has awarded a $258,300 contract to CHA Consulting to complete surveys, traffic studies, and construction documents for the conversion of Lincoln Way West and Western Avenue to three -lane streets with on- street parking. No Civil City funding is being used to pay for the development of the West Side Corridors Plan. The $160,000 cost of the plan is being funded by the Urban Enterprise Association ($150,000) and the Redevelopment Commission ($10,000). Fund 227 - $1,950,000 (Implementation) What has been done so far? Torti Gallas and Partners has completed the WesffideWain3treetsTlan, the revitalization plan for Lincolnway West and Western Avenue. The plan was developed through a series of public input sessions. The plan contains short- and long -term implementation strategies, and it prioritizes projects and project areas. Adoption of the plan by the Area Plan Commission and the Common Council will be sought this fall. Work toward implementing some of the plan's short -term tasks has already begun. Torti Gallas is being engaged to develop zoning changes for the corridors that will help reinforce the plan's land use and design concepts. Work on the potential zoning amendments will proceed through early next year. Engineering consultant CHA has completed traffic analysis and construction documents to restripe Lincolnway West from four lanes to three lanes with on- street parking and bicycle accommodations. As part of the project, trees will be added along that street's entire length. These Lincolnway improvements are out for bid, with bids being opened October 23 with award anticipated on October 28 for about $1.4M. Tree planting is expected to begin this fall, and the balance of the improvements will be completed in spring 2015. CHA is beginning work to design a similar scope of improvements along Western Avenue to be bid and implemented in 2015. Through the County Commissioners tax sale process, the City has begun work to acquire up to 138 properties along the corridors to facilitate commercial and housing redevelopment and park space expansion; properties are to be in the City's control in spring 2015. In coordination with the City, the Greater South Bend - Mishawaka Association of Realtors implemented a Better Block project on October 17 -18 that included a pop -up bakery /coffee shop, dog park, farmers market, art gallery, vendor space, and temporary landscaping in the 2900 block of Western Avenue to demonstrate plan concepts and possibilities. The South Bend Mutual Homes project, a housing co -op, was selected to receive tax credits. This funding will allow for the construction of 18 new homes in the Lincoln Park neighborhood that further support the implementation of the West Side Main Streets Plan. • 2 Way Streets (Downtown) What was amount budgeted for downtown and Jefferson? $5,803,849: Fund 412: Jefferson Improvements: $1,540,000 Downtown improvements and concept development: $2,660,000. Fund 426: - $1,603,849 What funds were to be used? Fund 412 - $4,200,000 Fund 426 - $1,603,849 What has been done so far? William and Lafayette: William St. has been opened to two -way traffic. Work continues on Lafayette Blvd. which is expected to be opened to two -way traffic by the end of October. Tree installation is currently underway. The project award amount is $782,927. Jefferson Blvd: Jefferson Blvd. has been opened to traffic after partial closure during project implementation. The contractor has completed work on new sidewalks, lighting and travel lane configuration. All streetscape elements (benches, trashcans & bike racks) have been installed. The last of the trees are being installed during the week of October 13. The project award amount is $1,535,873. Bartlett St.: JPR has completed approximately 60% of the project construction drawings and continues to make progress in order to bid the work in phases. The street straightening is expected to be awarded in 2014 for completion in 2015. Work on the roundabout is expected to begin towards the end of 2015 and completed in 2016. The JPR engineering contract is in the amount of $400,325. Traffic Modeling: A contract to model future traffic flow and traffic volumes for the downtown area was awarded to American Structurepoint in July at an amount of $271,710. This will help Engineering staff in making decisions on signal improvements, left turn lanes, stop sign conditions etc as the Smart Streets initiative progresses. Marion Roundabout and Street Realignment: A contract to begin engineering work on the roundabout at Marion and Michigan as well as the realignment of Main St. by Marion was awarded to Lawson Fisher at an amount of $619,350. The engineering documents are about 10% completed. Madison and Marion Conversion: An engineering contact for the conversion of Marion and Madison Streets into two -way was awarded to the Troyer Group in the amount of $79,205. Work is roughly 30% completed. • 311 Call Center Is 311 providing a high level of customer service for our residents? 311 provides a higher level of customer service, communication, and information to our residents within condensed timeframes. Because information is readily accessible, the need to transfer calls to additional personnel is not necessary in most instances. Service levels which need improvement are identified, documented, and a swift plan of action for correction is implemented. This results in increased service levels for our residents. Has a centralized 311 center reduced administrative costs in other areas? Because 311 is staffed with some existing City staff reassigned and committed to perform above and beyond normal expectations, administrative costs have been reduced. With each additional department's launch, expectations will continue to surpass normal output due to process improvements and greater efficiencies. Centralization also fosters team atmosphere across City departments and reduces our exposure to breaks in services. • CSO LTCP The 2014 budget revenues included the issuance of a $21 Million Bond (Fund 665) for the CSO LTCP. Do we anticipate that the size of the bond be modified? It has been discussed and decided not to issue a Sewer Bond for 2014 based on need in 2014. However, there is discussion surrounding a bond issue for 2015 in place of this. Further discussion to be had later in 2014. If so, how will the budget be impacted by this adjustment? n/a • Workforce Development What other workforce programs are we financially supporting? Initial funding for the SMART program (manufacturing training) of $69,911 from COIT came through a mid -year appropriation in late 2013. Based on the program's success we would like to consider expanding the funding amount in 2015 budget. The highlights of the project to date are as follows; ■ Two classes were held ■ To date, a total of 25 people were trained; 15 earning a certification ■ 7 are still in process of finishing program ■ 20 are employed fulltime; 4 are still searching We have partnered with WorkOne and the School Corporation on a Federal YouthBuild grant in the amount of $1.1 million. This grant would provide construction skills training to approximately 72 at -risk young adults over a 2 year period. This is an income based program that focuses on leadership development, GED /High school completion and hands on construction training. DO staff is currently engaged with multiple partners to develop a structure whereby we are able to provide an adequate labor pool to the construction /skilled trades industry. This demand is being driven largely by the pressure being forced on the industry as a result of the $700 million in projects that have been announced by Notre Dame. How much are we providing for these programs? Initial funding of $69,911 from COIT came through a mid -year appropriation in late 2013. Based on the program's success we would like to consider expanding the funding amount in 2015 budget. 2014 CURB AND SIDEWALK PROGRAM Address Street Date Paid Start Date Completion Date City Premium Council District 2101 Berkley Place 12/13/2013 5/22/2014 5/23/2014 X 1 806 Bryan 6/11/2013 4/15/2014 4/16/2014 X 1 1510 Kinyon 5/15/2013 4/16/2014 4/18/2014 X 1 413 W Marion 5/20/2013 4/22/2014 4/23/2014 X 1 1129 Riverside Dr. 1/15/2014 9/16/2014 9/11/2014 X 1 725 N. Scott Street 12/4/2013 9/18/2014 9/12/2014 X 1 525 Carroll (South St. Side) 7/11/2014 9/26/2014 11/26/2014 X 2 817 W. Colfax Ave 2/17/2014 9/23/2014 9/22/2014 X 2 825 W. Colfax Ave 2/17/2014 9/23/2014 9/22/2014 X 2 831 W. Colfax Ave 2/17/2014 9/23/2014 9/22/2014 X 2 609 Columbia 5/14/2013 10/31/2014 9/30/2014 X 2 2622 Prast Blvd 12/16/2013 9/26/2014 11/14/2014 X 2 928 N Sheridan 11/1/2013 5/20/2014 5/21/2014 X 2 509S 25th 5/13/2013 8/29/2014 8/21/2014 X 3 925S 27th 5/28/2013 9/4/2014 8/27/2014 X 3 1022S 28th 5/31/2013 9/17/2014 8/29/2014 X 3 925S 28th 6/7/2013 9/9/2014 9/8/2014 X 3 742S 29th 5/23/2013 8/26/2014 9/2/2014 X 3 738S 29th 5/23/2013 8/26/2014 9/2/2014 X 3 1322S 30th 8/1/2013 9/19/2014 9/19/2014 X 3 1113S 31st 6/10/2013 10/8/2014 9/19/2014 X 3 1117S 31st 6/10/2013 10/10/2014 9/19/2014 X 3 733S 31st 7/16/2013 8/25/2014 11/26/2014 X 3 633 S. 31st Street 12/5/2013 9/25/2014 9/3/2014 X 3 802S. 31st Street 12/23/2013 10/3/2014 9/11/2014 X 3 930S 32nd 6/3/2013 10/16/2014 9/22/2014 X 3 934S 32nd 6/13/2013 10/21/2014 9/22/2014 X 3 1234 S. 32nd 3/6/2014 8/28/2014 10/13/2014 X 3 1233S 33rd 5/31/2013 10/29/2014 9/22/2014 X 3 837S 36th 6/5/2013 8/25/2014 8/29/2014 X 3 Address Street Date Paid Start Date Completion Date City Premium Council District 1155 Altgeld 12/10/2013 10/8/2014 10/15/2014 X 3 1207 E Altgeld 6/5/2013 11/14/2014 10/7/2014 X 3 1710 E. Calvert 5/28/2013 10/3/2014 9/26/2014 X 3 3517 EJefferson 3/14/2014 8/21/2014 8/27/2014 X 3 721S Logan 5/23/2013 8/25/2014 8/28/2014 X 3 717S Logan 5/24/2013 8/25/2014 8/28/2014 X 3 1253 Longfellow 6/24/2013 8/5/2014 8/7/2014 X 3 1331 Longfellow 12/10/2013 6/26/2014 7/24/2014 X 3 1339 Longfellow 12/16/2013 6/26/2014 7/24/2014 X 3 1323 Longfellow 12/17/2013 6/26/2014 7/24/2014 X 3 1327 Longfellow 2/6/2014 6/26/2014 7/24/2014 X 3 1402S. Michigan 2/6/2014 9/29/2014 9/17/2014 X 3 932 Milton 5/14/2013 10/6/2014 9/26/2014 X 3 3105 Pleasant St 6/17/2013 8/28/2014 9/3/2014 X 3 1022 Roberts 12/3/2013 8/27/2014 8/27/2014 X 3 1331 Sunnymede Avenue 3/6/2014 1 7/17/2014 7/22/2014 X 3 Prepared by Marcia Qualls 11/5/2014 Page 1 1335 Sunnymede Avenue 3/6/2014 7/14/2014 7/22/2014 X 3 1519 Sunnym ede Avenue 6/2/2014 7/14/2014 7/18/2014 X 3 506S. Twyckenham 7/12/2013 7/21/2014 7/24/2014 X 3 413S. Twyckenham 7/1/2014 7/22/2014 7/25/2014 X 3 1417 Wall 6/3/2013 8/19/2014 8/13/2014 X 3 1415 Wall 6/12/2013 8/13/2014 8/13/2014 X 3 1321 Wall 5/14/2013 4/9/2014 4/15/2014 X 3 1430 E. Wayne 8/13/2013 5/29/2014 6/20/2014 X 3 1319 E. Wayne North 6/7/2013 5/28/2014 5/30/2014 X 3 631 W Angela Blvd. 5/21/2013 8/14/2014 8/15/2014 X 4 701 W. Angela Blvd. 6/13/2013 8/14/2014 8/15/2014 X 4 1832 Campeau 6/3/2014 8/28/2014 11/26/2014 X 4 1137 Campeau 6/10/2013 10/1/2014 X 4 Address Street Date Paid Start Date Completion Date City Premium Council District 318 N Esther 6/3/2013 7/25/2014 8/13/2014 X 4 133 N. Esther Street 12/11/2013 7/23/2014 8/6/2014 X 4 327 N. Hill Street 6/3/2014 9/11/2014 9/8/2014 X 4 714 N Ironwood 5/22/2013 8/19/2014 8/20/2014 X 4 213 N Ironwood 5/16/2013 8/18/2014 8/22/2014 X 4 217 N Ironwood 5/16/2013 8/18/2014 8/22/2014 X 4 1610 McKinley 1/21/2013 8/11/2014 8/13/2014 X 4 813 E. Miner Street 6/3/2014 8/29/2014 9/8/2014 X 4 732 Northwood Dr. 5/13/2013 8/11/2014 8/15/2014 X 4 120 N Notre Dame Ave 5/27/2014 9/19/2014 9/30/2014 X 4 205 N. St. Louis 12/6/2013 11/20/2014 9/25/2014 X 4 417 Wakewa 12/10/2013 9/15/2014 9/12/2014 X 4 302 Walsh 7/14/2014 8/29/2014 9/4/2014 X 4 1627 E. Washington 6/4/2014 7/25/2014 8/7/2014 X 4 1330 E Washington 5/22/2013 7/30/2014 8/4/2014 X 4 1159 Altgeld 6/5/2014 10/8/2014 10/15/2014 X 5 1314 Byron 5/29/2013 10/16/2014 10/16/2014 X 5 5424 Cotswold 5/17/2013 4/30/2014 5/2/2014 X 5 1340 Echo Drive 2/3/2014 10/14/2014 10/20/2014 X 5 6723 Hillenbrand 2/4/2014 10/24/2014 11/26/2014 X 5 1215 E Irvington 6/17/2013 11/12/2014 10/9/2014 X 5 1001 E. Irvington 2/3/2014 10/10/2014 10/10/2014 X 5 1968 Thornhill 5/20/2013 5/6/2014 5/18/2014 X 5 1211 E. Victoria 12/16/2013 11/5/2014 10/8/2014 X 5 5435 York Rd 6/3/2013 4/29/2014 4/30/2014 X 5 3829 Belle Vista 6/17/2013 10/17/2014 11/14/2014 X 6 522S. Bendix Dr. 12/6/2013 10/3/2014 10/23/2014 X 6 5265. Bendix Dr. 12/17/2013 10/3/2014 10/23/2014 X 6 753 Camden 6/10/2013 11/3/2014 10/2/2014 X 6 Address Street Date Paid Start Date Completion Date City Premium Council District 2225S Dorothy 6/9/2013 10/22/2014 8/20/2014 X 6 802 Dundee 6/7/2013 11/3/2014 9/30/2014 X 6 706S. Kaley 12/19/2013 11/3/2014 10/7/2014 X 6 609 Liberty 12/23/2013 10/10/2014 10/24/2014 X 6 1629S. Scott Street 1/2/2014 10/24/2014 11/14/2014 X 6 Prepared by Marcia Qualls 11/5/2014 Page 2 SPECIAL PROJECTS Address Street Orgination Start Date Completion Date City Premium Council District 703 Allen Council 9/26/2014 X 1 Sheridan DCI Unfinished Project 8/18/2014 X 2 Western Ave Fire Station #6 11/26/2014 X 2 1330/1332 Lincolnway East Youth Services Bureau 10/9/2014 X 3 Mishawaka Ave Council 8/14/2014 X 3 Notre Dame & Napoleon 311 Concern 8/25/2014 X 4 Byron & Springbrook 311 Concern 11/26/2014 X 5 Prepared by Marcia Qualls 11/5/2014 Page 3