HomeMy WebLinkAboutAppropriation - Capital Expenditures for year 2002, $1,600,000 from the County Option Income Tax FundORDINANCE No.
9316-02
Passed by the Common Council of the City of South Bend, Indiana
March 25,
Attest:
Attest:
C~
G{~
20 02
Presented by me to the Mayor of the City of Soutli Bend, Indiana
March 26, 20 ~2
City Clerk
President of Common Council
Ciry Clerk
Approved and signed by me March 26, 20 02
ORDINANCE NO. ` 3 ~ ~ - 0
AN ORDINANCE OF THE COMMON COUNCIL OF THE CITY OF SOUTH BEND,
INDIANA, APPROPRIATING FUNDS FOR CAPITAL EXPENDITURES FOR THE FISCAL
YEAR 2002 - $1,600,000 FROM THE COUNTY OPTION INCOME TAX FUND
STATEMENT OF PURPOSE AND INTENT
The City of South Bend through its C.O.I.T. fund anticipate making capital
improvements to its municipal facilities building during fiscal year 2002 and has determined that
it is necessary and appropriate to make payment of these expenses and to appropriate sufficient
funds from the C.O.I.T. fund of the City.
The specific capital improvements and expenditures the City anticipates making and the
capital funds from which appropriations are made to support those expenditures are identified
hereafter.
NOW, THEREFORE BE IT ORDAINED BY THE COMMON COUNCIL OF THE
CITY OF SOUTH BEND AS FOLLOWS:
SECTION I. The following amount shall be and hereby are appropriated in the fiscal
year 2002 and ordered set apart within the following designated capital funds for the payment of
municipal facilities building design costs.
FUND AMOUNT
COUNTY OPTION INCOME TAX FUND (Fund # 404) 1,600,000
SECTION II. If any one or more of the provisions of this ordinance or of the subparts of
the previous Section I shall for any reason be held to be invalid, illegal, or unenforceable in any
respect, such invalidity, illegality or unenforceability shall not affect any other provision hereof,
and this ordinance shall be construed as if such invalid, illegal or unenforceable provision was
not contained therein.
SECTION III. This ordinance shall be in full force and effect from and after its passage
by the Common Council and approval of the Mayor.
~~ /
Member, Common Council
1st READING 3` ~\1OZ
PUBLIC HEARING "3-LS_DZ
3 rd READING 3 _ Z$-OL
NOT APPROVED
REFERRED
^,s-ED 3~L5 -a 2.
_ .. ~.-c. ~.~.- .._.~ .....~
i .,~~:
~, ~'~~~ ~ ~ ZOQ~
!! 4
q
COMMITTEE REPORT
TO THE COMMON COUNCIL OF THE CITY OF SOUTH BEND:
Your Committee of the Whole, to whom was referred:
BILL NO.
18-02 A BILL OF THE COMMON COUNCIL OF THE CITY OF SOUTH BEND,
INDIANA, APPROPRIATING FUNDS FOR CAPITAL EXPENDITURES
FOR THE FISCAL YEAR 2002 - $1,600,000 FROM THE COUNTY
OPTION INCOME TAX FUND
Respectfully report that they have examined the matter and that in their opinion, this bill
is being recommended to the full Council with a favorable recommendation.
Karl King
Chairman
COUNTY-CITY BUILDING
SOUTH BEND, INDIANA 46601-1830
CITY OF SOUTH BEND STEPHEN J. LiJECKE, MAYOR
PHONE 574/ 235-9216
FAx 574/235-9928
TDD 574/ 235-5567
DEPARTMENT OF ADMINISTRATION AND FINANCE
FREDERICK B. OLLETT, III
CONTROLLER
March 5, 2002
City Council President Roland Kelly
City Council
4"'Floor, County-City Building
South Bend, Indiana 46601
RE: $1.6 Million Appropriation -Professional Services
Development of Police and Fire Facilities
Dear Councilman Kelly:
The attached appropriation Ordinance is for $1.6 million. When combined with the $400,000
appropriation for professional services fees for the Police and Fire stations in the previously
approved 2002 Capital Improvement Plan(CIP), this brings the total appropriations for this purpose
to $2 million.
You asked whether DLZ was the only firm approached about designing the project and
whether the city should consider competitive cost proposals for the architectural and engineering
professional services. The design work was initiated in 2001 with a Qualification Based Selection
(QBS) process. We invited numerous firms who had submitted qualification and experience
statements that were relevant to police and fire stations to submit written proposals. Those were
evaluated by two representatives each of the Police ,Fire and Public Works Department. The best
three joint ventures were given the opportunity to make more extensive oral presentations and
concept proposals Upon completion of the short list review, the successful team was
DLZ/Zimmerman. DLZ is a local architectural and engineering firm with a significant number of
engineers and architects. They strategically teamed on this project with Zimmerman Design from
Wisconsin. Zimmerman has a wealth of experience on police and fire stations. The fees for
DLZ/Zimmerman are in the range for the type of project by size and by complexity. It is important
to remember that good engineering mid architectural services saves money in the long run, since
the big dollars are in the construction. The better the set of plans and specifications that are put
together, the less likelihood of contractors covering risks for unknowns or being in a strong position
to negotiate additional change orders after award. For that reason, we discourage the use of
competitive cost bidding on engineering and architectural services and make our selection based on
the best fit for the project in terms of qualifications and experience and then negotiate a reasonable
price within standards of the design industry.
CATHERINE A. HUBBARD-SHEAR LIZ ROWS THOMAS SKARBEK SUSAN WALLACE ROBERTt~LLEN
DIRECTOR DIRECTOR DIRECTOR MANAGER DIRECTOR
HUMAN RESOURCES CTTYFINANCE BUDGETING & FINANCIAL REPORTING BENEFITS INFORMATION TECHNOLOGY
During 2001, the DLZ/Zimmerman team, working with the Police, Fire and~Public Works
staff, completed the programming and schematic design portion of the professional services. The
analysis evaluated six alternatives, which we will review in detail again on March 18. The
recommended option was Option No. 4, which called for remodeling of the existing facility to serve
the Police Department needs and construction of a new Central Fire station and administrative
offices at an alternate site.
It is customary upon completion of the programming and schematic design phases to go into
design development and then construction documents (plans and specifications). The bidding process
will come next and then the construction phase (including shop drawing review and resident prof ect
inspection services). The Police Station and the Fire Station projects are estimated at construction
costs of about $16.1 million and total project costs at $ 18.8 million. The design fees are $ 1.37
million or 8.5 percent of construction which is typical for a project of this scope and complexity
(industry range is 8 -12 percent). The other soft costs are in acceptable industry ranges again as a
percent ofconstruction---the largest item is construction inspection and shop drawing review which
is the balance of the $ 2 million for professional architectural and engineering services. The
construction services fees are under $ 600,000 which is 3.5 percent of construction-for comparison
sake the state routinely permits construction engineering services at 15 percent of construction for
highway projects. The other soft costs are things like furniture ,fixtures and equipment to make the
stations function as optimal work environments.
The Fire Station is on the critical path as the first item that must be done. It will take us until
this summer to complete design plans and specifications to put the project out to bid. It will then
take twelve months to construct the facility. The Police Station remodeling must await "some empty
pegs in the pegboard" through the vacation of some of the Fire Department space from the Municipal
Services Facility. The design will take us until the Fall of 2002. Public bidding will take a couple
months and construction of the Police Station is expected to take 18 months.
We look forward to presenting the work to date, current status and proposal for where we go
from here on the Police and Fire Stations. Rick Ollett will present the financing plan. Gary Gilot,
Chief Taylor, Chief Bennett and Carl Littrell will be available to answer technical questions on the
project. We will also ask our lead architect on the proj ect, Steve Kromkowski of DLZ, to be present
to assist with the presentation and answer any questions you may have.
If you have any questions or need more information in anticipation of the March 18 work
session on this project, please contact either Rick or Gary as appropriate.
Sincerely,
~•
Frederick B. Ollett III, City Controller
c: Mayor Steve Luecke
City Council Members
Gary Gilot, Public Works
Steve Kromkowski, DLZ Indiana
Chief Luther Taylor, Fire Department
Chief Larry Bennett, Police Department
Carl Littrell, City Engineer