HomeMy WebLinkAboutAppropriating $22,000.00 Cumulative Sewer Building and Sinking FundORDINANCE No. 5703 -74
Passed by the Common Council of the City of South Bend,
IRENE K. GAMMON
Presented by me to the Mayor of the City of South Bend, Indiana
K
Approved and signed by me L lt�d4 a v,
Clerk
Of Common Council
IRENE K. GAMMON
Clerk
ORDINANCE NO. S-1703-174/
AN ORDINANCE APPROPRIATING THE SUM OF
$22,000.00 FROM THE CUMULATIVE SEWER
BUILDING AND SINKING FUND.
WHEREAS, engineering studies have been completed
outlining certain sanitary sewer projects; and
WHEREAS, funds are now needed for engineering
surveys, plans, estimates and specifications for said project;
and
WHEREAS, a Cumulative Sewer Building and Sinking
Fund has been established.
NOW, THEREFORE, BE IT ORDAINED by the Common Council
of the City of South Bend, Indiana:
SECTION I. That the sum of $22,000.00 be appropria-
ted from the Cumulative Sewer Building and Sinking Fund for
the project and in the amount set forth below:
Project CS8 -1974 - Portage Rd. - Brick Road Trunk
Sanitary Sewer
Engineering Cost - - $22,000.00
SECTION II. This Ordinance shall be in full force
and effect from and after its passage by the Common Council, its
approval by the Mayor and the fulfillment of all statutory
requirements.
1st READING
PUBLIC HEARING
2nd READING
NOT APPROVED
REFERRED
PASSED
?- 8 -AI/
7 -aa -7�(
'7- as -7^IL
-) - a a - '7 '1
Member of he Common Council
FILED IN CLERK'S OFFICE
JUL 1 1974
Irene Gammon
CITY CLERK, SOUTH BEND, IND.
ioC
CITY OF SOUTH BEND
South Bend, Indiana 46601
Jerry J. Miller
Mayor
Rollin E. Farrand, Sr., P. E.
Director, Public Works
Members of the Common Council
South Bend, Indiana
Gentlemen:
Reply To: Bureau of
Design & Administration
July 1, 1974
There are currently many projects both public and private planned for the
area to the Northwest of the present City Limits. Two of the more obvious
public projects are the bypass and the proposed Cleveland Road extension.
As this area develops, the need for sewers and other utilities develops
naturally.
To anticipate this development, we are now asking you to appropriate
$22,000.00 to fund the engineering study and the preparation of construction
plans for a trunk sewer extending from the termination of the "Cleveland
Road Sewer" at Portage Avenue and Cleveland Road to Brick Road and the
Bypass. We anticipate construction costs of $350,000 to,$400,000 for this
sewer.
This sewer will ultimately service the area north of the Toll Road to the
State Line. This area is located within the proposed Northwest Annexation.
The proposed sewer routing is consistent with the "Community Facilities and
Public Utilities Plan" prepared for the Area Plan Commission.
Based on the above, we recommend that you appropriate the requested funds
and in turn, confirm a contract entered into (subject to appropriation of
funds) between the City and Kent Kaser and Associates to provide the required
engineering.
Very truly yours,
Rollin E. Farrand, P.E.
Dire r
David A. Wells, P.E. - Manager
Bureau of Design & Administration
DAW /mkm
Tolm itur Irpar#
XV tkt Tamarou Touuril of Or tau# of §bw# Vrub:
Your Committee of the Whole
to whom was referred
AN ORDINANCE APPROPRIATING THE SUM OF
$22,000.00 FROM THE CUMULATIVE SEWER
BUILDING AND SINKING FUND (Portage Road —
Brick Road Trunk Sanitary Sewer).
Respectfully report that they have examined the matter and that in their opinion the Ordinance Should be
recommended favorably to the Common Council.
Odell Newburn
Chairman
......... . rneu..... co.