At its August 25, 2026 meeting, the Board of Public Works approved the Final
Change Order for this project, for an additional eighteen (18) Days. The final contract
amount is $49,995.
In addition, the Project Completion Affidavit for this project was approved in the
amount of $49,995. Copies of the Change Order and Project Completion Affidavit are
enclosed for your records.
Sincerely,
/s/Hillary Horvath
Hillary Horvath, Clerk
We deliver services that empower everyone to thrive!!
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS DIVISION OF ENGINEERING
TO: Hillary Horvath, Clerk
Board of Public Works
FROM: Zak Tebell, Project Engineer
SUBJECT: Change Order: 125-026A Marshall Park Tennis Court Resurface
DATE: 8/20/2026
Change Order #1 for the Marshall Park Tennis Court Resurface includes a change in project timeline but no change in the Project’s budget. Arnt Asphalt Co. has requested an additional 18 days due to inclement weather, specifically colder temperatures lasting longer into the spring and a high level of rain. The material used requires a window of multiple warm weather days without rain in a row in order to meet installation specifications.
Please Respond with any questions (EXT. 9358)
1
$49,995.00
$ 0.00
$49,995.00
$
$49,995.00
0.00 %
0.00 %
CONSTRUCTION MANAGER
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
City, State, Zip
Printed Name and Title
Company Name
Address
Member
Member
Approved Date:
President
Member
Member
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO:
SUBJECT OF CHANGE ORDER:
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:8/20/2026
125-026A
Marshall Park Tennis Court Resurface
9/09/2025
Extension of Project completion date due to inclement weather.
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is Increased
0.00Decreased
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time 6/19/2026
0 days
RECOMMENDED FOR
Extension of date/time by previous change orders
Date/time extension by this change order 18 days
New completion date/time 7/7/2026
CONTRACTOR
Contractor Signature
Luke Holliday- Sales
Arnt Asphalt Sealing Inc.
2763 Sodus Parkway
Sodus, MI, 49126
8/18/2026
BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM
Date: 8/18/2026
Name: Zak Tebell Department of Public Works – Engineering Division
BPW Date: 8/25/2026 Phone Extension: 9358
Required Prior to Submittal to Board
BPW Attorney X Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA Chg. Order, No. Traffic Control Resolution
Other: Ratify Emergency
Contract Ease./Encroach
Required Information
Company or Vendor Name Arnt Asphalt Sealing Inc.
New Vendor Yes If Yes, Approved by Purchasing No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Marshall Park Tennis Court Resurface
Project Number 125-026A
Funding Source PR-00042762 Account No. 430-10-102-121-444000--PROJ00000624
Amount $49,995.00
Terms of Contract Project Completion Affidavit for Marshall Park Tennis Court Resurfacing
Project
Special Contract Provisions N/A Purpose/Description Closeout of Marshall Park Tennis Court Resurfacing Project.
For Change Orders Only
Amount of Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase Decrease
%
( %)
Time Extension Amount:
New Completion Date:
X 1(F)