HomeMy WebLinkAbout2018-09-14-Becks-Lake-Monthly-Progress-Report-No.-35VERITAS, LLC
September 14, 2018
United States Environmental Protection Agency
Region 5, Superfund Division
77 West Jackson Boulevard (SR -6J)
Chicago, Illinois 60604
Attn: Ms. Jenny Davison
Remedial Project Manager
Superfund Division
Re: Monthly Progress Report for August 2018
Beck's Lake NPL Site / LaSalle Park Area
Dear Ms. Davison:
On behalf of the City of South Bend and Honeywell International Inc., Veritas, LLC is pleased to
submit the Monthly Progress Status Report for the August 2018 reporting period as required by the
Consent Order dated October 2, 2015, as amended.
Please contact the undersigned should you have any questions.
Sincerely,
Richard T. Brown
Project Coordinator
rtb
Cc : Steven D. Murray, CPG Amec Foster Wheeler (Wood)
Chuck Geadelmann, Honeywell International Inc.
Stephen A. Studer, Esq. Krieg DeVault LLP
Kerry A. Dziubek, Esq. Arnold & Porter Kaye Scholer LLP
Stephanie Steele, Esq., City of South Bend
Anne Fuchs, City of South Bend
30845 Rockinghorse Lane
Niles, MI 49120
(574) 298-4943
Rick. Brown.Veritasllc@outlook.com
VERITAS, LLC
MONTHLY PROJECT STATUS REPORT FOR AUGUST 2018
BECK'S LAKE NPL SITE / LA SALLE PARK AREA
1.0 PROJECT STATUS AND PROGRESS TO DATE
• Geophysical survey completed.
• Sled hill investigation, sample collection, laboratory analysis, and validation completed.
• Beck's Lake water and sediment sample collection, laboratory analysis, and validation
completed.
• Expedited Area (Charles Black Recreation Center) investigation, sampling, laboratory
analyses and validation completed.
• Surface soil sampling, laboratory analyses and validation completed.
• Subsurface soil borings and sampling of soil and groundwater, laboratory analyses,
and validation completed.
• Soil gas vapor point installation completed, vapor sampling, laboratory analyses and
validation completed.
• Monitor well installation completed; monitor well sampling and gauging completed;
laboratory analyses and validation completed.
• All monitor wells (including two installed by others), vapor wells, and staff gauge
surveyed by licensed land surveyor.
• The Data Evaluation Summary Report for the Expedited Area was completed and
submitted to the Environmental Protection Agency (EPA) on November 30, 2016.
Comments were received on January 6, 2017 and addressed in the Draft Expedited
Area Remedial Investigation (EA RI) report.
• The Draft EA RI was submitted to the EPA on March 27, 2017. Comments were
received on April 28, 2017. The response to the EPA's EA RI comments was submitted
to the EPA on May 26, 2017, and indicated that in agreement with the EPA, a Final EA
RI would not be submitted. The results of the EA RI were incorporated into the LaSalle
Park Area (LPA) Focused RI report submitted to EPA on August 11, 2017.
• The Data Evaluation Summary Report for the LPA was submitted to the EPA on April
4, 2017. Comments were received from the EPA and the Indiana Department of
Environmental Management (IDEM) on May 16, 2017 and May 12, 2017, respectively.
Per May 26, 2017 correspondence, the comments were addressed in the LPA Focused
RI Report that was submitted on August 11, 2017.
Page 1
30845 Rockinghorse Lane
Niles, MI 49120
(574) 298-4943
Rick.Brown.Veritasllc@outlook.com
VERITAS, LLC
• The Data Evaluation Summary Report for the LPA was submitted to the EPA on April
4, 2017. Comments were received from the EPA and the Indiana Department of
Environmental Management (IDEM) on May 16, 2017 and May 12, 2017, respectively.
Per May 26, 2017 correspondence, the comments were addressed in the LPA Focused
RI Report that was submitted on August 11, 2017.
• Correspondence was received from the EPA on April 14, 2017, which outlined their
suggested approach for approval of the proposed Charles Black Recreation Center
(CBRC) building expansion. The response was submitted May 8, 2017.
• A draft Soil Management Plan (SMP) for managing soils during construction activities
at the CBRC was submitted to the EPA on July 7, 2017. EPA responded on July 28,
2017. After minor revisions, the SMP was re -submitted on August 18, 2017 and was
approved by the EPA on August 21, 2017. Expansion of the CBRC has begun and the
SMP has been implemented and will continue through the completion of soil
excavation activity and use of the SMP expanded into the park irrigation project.
• EPA held a local public meeting on September 6, 2017 focused on off-site residential
sampling.
• The Draft LPA RI report was submitted to the EPA on August 11, 2017. Comments
were received from EPA on September 12, 2017. Following an extension by EPA on
October 13, 2017 the revised RI report was submitted to EPA on October 20, 2017.
The RI report was conditionally approved by EPA on November 29, 2017.
• A revised schedule culminating in the submittal of the Feasibility Study Report was
submitted to the EPA on October 23, 2017 and discussed in November
teleconferences.
• The Remedial Action Objectives Technical Memorandum was completed and
submitted to EPA on January 5, 2018. EPA and IDEM comments were received March
8, 2018. Comments to be considered as appropriate in the ongoing development of
remedial alternatives and to be incorporated into the Feasibility Study.
• Re -development and re -sampling of groundwater from all monitor wells completed in
late January and early February 2018. Raw data results received on February 26,
2018 and forwarded to EPA via email. Validation later completed. Data was included
in the Screening Alternatives Technical Memorandum submitted to EPA April 9, 2018;
EPA has not commented as of the date of this Progress Report.
• EPA and IDEM comments on SLERA Attachment 4 received March 30, 2018;
response to comments and revised SLERA submitted to EPA on April 30, 2018. No
EPA response received as of the date of this Progress Report
• Draft Work Plan for Off -Site Waste Delineation Borings and Monitor Wells submitted
to EPA for review and approval on August 24, 2018.
30845 Rockinghorse Lane
Niles, MI 49120
(574) 298-4943
Rick.Brown.Veritasllc@outlook.com
VERITAS, LLC
Page
2.0 SUMMARY OF RELEVANT FINDINGS
• The exposure route and receptor of concern identified in the BHHRA is the inhalation
pathway (i.e., dust) for the construction worker. A Soil Management Plan was written,
approved by EPA, and implemented for managing this potential risk to CBRC
expansion and other construction workers.
3.0 SUMMARY OF CHANGES MADE TO FIELD ACTIVITIES
None this reporting period.
4.0 SUMMARY OF DIFFICULTIES ENCOUNTERED
None this reporting period.
5.0 SUMMARY OF ACTION TAKEN TO RECTIFY DIFFICULTIES
None required this reporting period.
6.0 SUMMARY OF ACTIVITIES TO BE PERFORMED IN AUGUST 2018
• EPA comments on the Screening Alternatives Technical Memorandum (SA TM) have
been put on hold by EPA pending PRP decision to extend sampling to outside of the
LPA. EPA to determine whether to proceed with Comparative Analysis Technical
Memorandum or Feasibility Study. Awaiting SMP Addendum approval by EPA to allow
for completion of irrigation system and other projects in LPA. Awaiting agency
comments on Draft Work Plan for off-site borings and wells.
7.0 KEY PERSONNEL CHANGES
• Richard Brown retired from WSP on June 29, 2018. The PRPs subsequently
requested he remain as Project Coordinator under Veritas, LLC.
• Project Manager and Field Supervisor R. Joseph Trojan resigned the employ of WSP
on June 29, 2018 and joined JPR Engineering.
30845 Rockinghorse Lane
Niles, MI 49120
(574) 298-4943
Rick. Brown.Veritasllc@outlook.com
VERITAS, LLC
8.0 DEVIATIONS FROM THE PROPOSED SCHEDULE
• Schedule on hold per EPA per Item 6.0
Page 3
30845 Rockinghorse Lane
Niles, MI 49120
(574) 298-4943
Rick. Brown.Veritasllc@outlook.com