HomeMy WebLinkAboutChange Ordger No 3 & PCA - 2025 CCMG Proj No 125-004A - Milestone Contractors LP
July 28, 2026
Thaddeus Horvath
Milestone Contractors, L.P.
24358 State Road 23
South Bend, IN 46614
akrueger@milestonelp.com ; thorvath@milestonelp.com
RE: Change Order No. 3 (Final)/Project Completion Affidavit
2025 CCMG - Project No. 125-004A
Dear Thaddeus:
At its July 28, 2026 meeting, the Board of Public Works approved the Final Change
Order for this project, be decreased by $65,434.81. The final contract amount is
$2,120,719.96.
In addition, the Project Completion Affidavit for this project was approved in the
amount of $2,120,719.96. Copies of the Change Order and Project Completion Affidavit
are enclosed for your records.
Sincerely,
/s/Hillary Horvath
Hillary Horvath, Clerk
6/29/2026
BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM
Date 07/15/2026
Name Kyle Ludlow Department Public Works
BPW Date 07/28/2026 Phone Extension 9157
Review and Approval Required Prior to Submittal to Board Diversity Compliance and Inclusion Officer Officer Name
BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. 3 PCA Chg. Order, No. Traffic Control Resolution Other: Ease. /Encroach
Required Information
Company or Vendor Name Milestone Contractors North, LLC
New Vendor Yes If Yes, Approved by Purchasing No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name 2025 CCMG
Project Number 125-004A
Funding Source 265-436008Account No. PR-00040469 PO-0038604
Amount $2,120,719.96
Terms of Contract
Purpose/Description _Project Closeout
For Change Orders Only
Amount of Increase Decrease
$
($65,434.81) Previous Amount $
Current Percent of Change: Increase Decrease
%
(2.99%)
New Amount $ 2,120,719.96
Total Percent of Change: Increase Decrease
%
(0.81%)
Time Extension Amount: 0 New Completion Date: