Loading...
HomeMy WebLinkAboutTabled - Change Order No 2 - Dylan Dr Lighting Proj No 119-047 - Michiana ContractingBOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date: 7/7/2026 Name: Caitlin Wyant, EI Department of Public Works – Engineering Division BPW Date: 7/14/2026 Phone Extension: 7483 Required Prior to Submittal to Board BPW Attorney X Attorney Name Dept. Attorney Attorney Name Purchasing Check the Appropriate Item Type – Required for All Submissions Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O PCA No. PCA Chg. Order, No. 2 Traffic Control Resolution Other: Ease./Encroach Required Information Company or Vendor Name Michiana Contracting New Vendor Yes If Yes, Approved by Purchasing No MBE/WBE Contractor MBE WBE Completed E-Verify Form Attached Yes No Project Name Dylan Dr Lighting Improvements Project Number 119-047 Funding Source Light Up South Bend 2024, 2025; River West TIF Account No. PO #41225 Amount Terms of Contract Special Contract Provisions Purpose/Description See memo For Change Orders Only Amount of Increase Decrease $ 120,434.02 ($ ) Previous Amount $ 355,434.92 Current Percent of Change: Increase Decrease 33.88% ( %) New Amount $ 475,868.94 Total Percent of Change: Increase Decrease 40.11% ( %) Time Extension Amount: New Completion Date: To: Board of Public Works From: Caitlin Wyant; Project Engineer Subject: PN 119-047 CO#2 Date: July 14, 2026 Board members, The change order before you today is to account for unforeseen circumstances in the Dylan Drive Lighting Improvements project (#119-047). On Monday 6/1/2026, Michiana Contracting notified Engineering that crews had observed new fixtures on the north portion of Dylan Dr turning on and off intermittently. Upon investigation, it was discovered that circuit 1 wires underground were burnt and melted in multiple places and waterproof splices underground had been submerged in water, leading to failure (photos enclosed). At this time, Engineering directed Michiana Contracting to begin writing up a change order for staff consideration As the intent of this project was to upgrade the lights along Dylan Drive, this intent would not be properly fulfilled without the installation of new wire and fuses for these lights. Funding is available via Light Up South Bend 2024 & 2025 and River West TIF. Best, Caitlin Wyant Project Engineer Figure 1: Failure of waterproof splices (melting) Figure 2: Failure of one leg of C5 and improper wiring of this circuit CO #DATE 119-047-2 07/07/2026 City of South Bend, Public Works Engineering, Phone: (574) 235-9251 215 S. Dr. MLK Jr. Blvd., South Bend, IN 46601 Page 1 Subject: Change Order 2 BILL TO City of South Bend Public Works Engineering 215 S. Dr. MLK Jr. Blvd. Ste. 400 South Bend, IN 46601 PROJECT Dylan Drive Lighting Enhancements PROJECT #: 119-047 215 South Doctor Martin Luther King Junior Boulevard Suite 400 South Bend, IN 46601 DESCRIPTION Wire & fuse replacement for north side of Dylan Dr Item Qty Price/Unit Total 5 Conductor #4 6,095 $17.20/LFT $104,834.00 3 Conductor #10 1,585 $5.02/LFT $7,956.70 Lighting Connections 38 $201.14/EA $7,643.32 Subtotal $120,434.02 Tax: (0%)$0.00 Total $120,434.02 CO #DATE 119-047-2 07/07/2026 City of South Bend, Public Works Engineering, Phone: (574) 235-9251 215 S. Dr. MLK Jr. Blvd., South Bend, IN 46601 Page 2 REVISED BALANCE SUMMARY Original Contract Amount $339,642.00 Net Change by Previous Change Orders $15,792.92 Contract Amount Prior to this Change $355,434.92 Amount of this Change Order $120,434.02 Revised Contract Amount, Including this Change Order $475,868.94 Contractor Signature___________________________________________ Construction Manager Signature_______________________________________ CITY OF SOUTH BEND - BOARD OF PUBLIC WORKS Approved Date____________________ President____________________________________________ Member_____________________________________________ Member_____________________________________________ Member_____________________________________________ Member_____________________________________________