Department of Public Works Report
March DPW Report April 1st-3oth
BPW Awarded Contracts
(April 2025)
One bid Awarded
BPW Meeting April 8, 2025 Bids
Harrow Drive Drainage Improvements
Project No. 125-002A
Company: Milestone Contractors
Amount: $197,800
MBE - 2.56%
WBE - 5.11%
Rejection of Bids/Quote for April 2025
No rejections took place
Project Completion Affidavits
One (1) project closed out
BPW Meetings April 8 & 22 , 2025thnd
2024 Curb & Sidewalk - Division 4 – Project No. 124-009 - Company: Rieth Riley - Final Contract Amount: $82,607
MBE/WBE Final %: MBE - 2.5% WBE - 13.2%
Inclusive Procurement Contracting Board
Department of Public Works Report
April DPW Report April 1 -30th 2025st
Project Name Company
Final
Contract
Amount
MBE Goal% WBE Goal%MBE Final
Amount
WBE Final
Amount
MBE/WBE
OVER/UNDER
%
2024 Curb &
Sidewalk - Div 4 Rieth Riley $82,607 2.47 15.05%2.5%13.2%MBE - .038%
WBE - 1.8%
Self-performing MBE/WBE Prime
Under percentage