RE: Change Order No. 3 (Final)/Project Completion Affidavit
Angela Blvd. Roadway Improvements - Project No. 122-059R
Dear Daniel:
At its June 23, 2026 meeting, the Board of Public Works approved the Final
Change Order for this project, be decreased by $82,475.18. The final contract amount is
$3,317,684.
In addition, the Project Completion Affidavit for this project was approved in the
amount of $3,317,684. Copies of the Change Order and Project Completion Affidavit are
enclosed for your records.
Sincerely,
/s/Hillary Horvath
Hillary Horvath, Clerk
June 23, 2026
4/27/2026
June 23, 2026
BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM
Date 06/08/2026
Name Kyle Ludlow Department Public Works
BPW Date 06/23/2026 Phone Extension 9157
Review and Approval Required Prior to Submittal to Board Diversity Compliance and Inclusion Officer Officer Name
BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. 3 PCA Chg. Order, No. Traffic Control Resolution Other: Ease. /Encroach
Required Information
Company or Vendor Name Milestone Contractors North, LLC
New Vendor Yes If Yes, Approved by Purchasing No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Angela Blvd. Roadway Improvements
Project Number 122-059R
Funding Source REDA TIF and River East Residential TIF Account No. Div. 1: PR-24760 with PO-27696 & Div. 2: PR-24761 with PO-27675
Amount $3,317,684.00
Terms of Contract
Purpose/Description _Project Closeout
For Change Orders Only
Amount of Increase Decrease
$
($)82,475.18 Previous Amount $3,400,159.18
Current Percent of Change: Increase Decrease
%
(2.43%)
New Amount $ 3,317,684.00
Total Percent of Change: Increase Decrease
2.37%
(%)
Time Extension Amount: 0 New Completion Date: