HomeMy WebLinkAboutChange Order No 2 - YSB SB Thrive Subdivision Proj No 123-011 - Rieth-Riley Construction
April 28, 2026
Mr. Garrett VanParys
Rieth-Riley Construction Co., Inc.
25200 State Road 23
South Bend, IN 46614
gvanparys@rieth-riley.com
RE: Change Order No. 2 – Youth Services Bureau/South Bend Thrive Subdivision and
Off-Site Improvements – Project No. 123-011
Dear Mr. VanParys:
At its April 28, 2026 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $90,378.77 and an additional three-hundred
and four (304) days, bringing the revised contract amount to $3,537,249.26.
Enclosed is a copy of the Change Order for your records.
Sincerely,
/s/ Hillary Horvath
Hillary Horvath, Clerk
April 28, 2026
Page 1 of 3
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Hillary Horvath, Clerk
Board of Public Works
FROM: Jacob M. Klosinski, PE, Assistant City Engineer
SUBJECT: Change Order No. 2
123-011 Youth Services Bureau & South Bend Thrive Subdivision and
Offsite Improvements.
DATE: April 21, 2026
The Division of Engineering requests the Board of Public Works approval of Change Order No. 2
for Project No. 123-011 Youth Services Bureau & South Bend Thrive Subdivision and Offsite
Improvements. Change Order No. 2 encompasses adjustments to the balance of underruns and
overruns for unit price work identified in the original contract as well as some additional scope of
work that was required to complete both water main work on McKinley, communication conduit,
and electrical conduit adjustments based on code requirements and American Electric Power
conduit routing requirements for the lighting circuit.
Summary: Change Order No. 2 Items, Underrun (Credits) and Overrun (Increase)
UNDERRUNS
7 7: Structure Backfill (Undistributed) $ 1,125.60
9 9: Storm Sewer Pipe Remove $ 117.15
11 11: Concrete Approaches and Sidewalk Remove $ 1,267.56
16 16: Structure Fence Remove $ 9,467.01
22 22: HMA Pavement Base 440 LBS/SYS $ 5,684.58
25 25: PCCP for Approaches 9 Inches $ 2,160.00
26 26: PCCP for Approaches 6 Inches $ 2,082.08
28 28: Concrete Curb 6 Inch $ 2,260.50
31 31: Sodding Stormwater Ponds $ 16,473.00
32 32: Sodding $ 1,418.34
33 33: Trees 2.5 Inch Caliper $ 21,615.00
34 34: Storm Sewer Pipe RCP 12 Inch $ 739.36
35 35: Storm Sewer Pipe RCP 18 Inch $ 2,769.97
36 36: Storm Sewer Pipe PVC C900 12 Inch $ 753.00
38 38: Storm Sewer Catch Basin 30 Inch Dia. $ 7,308.18
40 40: Sanitary Sewer Pipe PVC 8 Inch $ 2,032.35
44 44: Water Main Pipe DI 8 Inch $ 635.14
54 54: Water Service DI 6 Inch $ 6,273.48
55 55: Water Service Copper 2 Inch $ 11,739.36
Page 2 of 3
56 56: Water Service Copper 1-1/2 Inch $ 5,258.82
57 57: Water Service Copper 1 Inch $ 2,945.35
59 59: Connection to Existing Water Main 6 Inch Priva $ 3,845.42
74 74: Maintain Wastewater Service $ 4,650.00
TOTAL CREDIT FOR UNDERRUNS $ 112,621.25
OVERRUNS
20 20: Compacted Aggregate Base No. 53 $ 22,681.88
21 21: HMA Pavement Base 880 LBS/SYS $ 53,958.00
23 23: HMA Pavement Intermediate 275 LBS/SYS $ 6,934.04
24 24: HMA Pavement Surface 165 LBS/SYS $ 7,951.58
27 27: Concrete Curb and Gutter 6 Inch $ 2,561.50
29 29: Concrete Sidewalk 4 Inch $ 1,926.00
30 30: Concrete Curb Ramp $ 6,867.00
39 39: Storm Sewer Manhole 48 Inch Dia. $ 7,340.66
47 47: Fitting DI 11.25 Degree Bend 8 Inch $ 1,650.66
64 64: Conduit HDPE 3 Inch (Lighting) $ 565.00
65 65: Conduit HDPE 2 Inch (Lighting) $ 725.00
66 66: Handhole (Lighting) $ 8,800.00
67 67: Electrical Wiring (Lighting) $ 4,626.00
76 76: Conduit HDPE 3 Inch (Telecommunications) $ 2,109.00
77 77: Handhole (Telecommunications) $ 2,548.00
TOTAL INCREASE FOR OVERRUNS $ 131,244.32
CHANGE ORDER NO. 2 ITEMS
101 Added 4" Water Laterals $ 27,634.14
102 Added McKinley Fire Hydrant $ 4,120.00
103 Slussers Seedong for Ponds $ 12,104.76
106 Slussers Tree - 1.75" Cal. $ 7,280.00
107 Slussers Tree - 2" Cal $ 11,500.00
108 Footer/Rubble Pile Removal $ 9,116.80
TOTAL INCREASE FOR CHANGE ORDER NO. 2 ITEMS $ 71,755.70
SUMMARY
UNDERRUNS $112,621.25 CREDIT / DEDUCT
OVERRUNS $131,244.32 INCREASE
CHANGE ORDER NO. 2 ITEMS $ 71,755.70 INCREASE
NET CHANGE ORDER NO. 2 $ 90,378.77 NET INCREASE
Page 3 of 3
PROJECT COST SUMMARY
Original Contract: $3,326,371.58
Change Order No. 1 $ 120,499.45 (Increase 3.62%)
Change Order No. 2 $ 90,378.77 (Increase 2.72%)
Total Increase to Contract for Change Orders: $ 210,878.22
Total Increase in Percentage from Original Contract: 6.34%
Final Contract Amount: $3,537,249.26
The remaining balance of the project will be covered through the Division of Water Works,
Water Works, Infrastructure Mains, Account 622-06-604-620-442007. Contact Jacob M.
Klosinski at the Division of Engineering at Ext. 9496 for questions regarding this project.
Page 1 of 3
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Hillary Horvath, Clerk
Board of Public Works
FROM: Jacob M. Klosinski, PE, Assistant City Engineer
SUBJECT: Change Order No. 2
123-011 Youth Services Bureau & South Bend Thrive Subdivision and
Offsite Improvements.
DATE: April 21, 2026
The Division of Engineering requests the Board of Public Works approval of Change Order No. 2
for Project No. 123-011 Youth Services Bureau & South Bend Thrive Subdivision and Offsite
Improvements. Change Order No. 2 encompasses adjustments to the balance of underruns and
overruns for unit price work identified in the original contract as well as some additional scope of
work that was required to complete both water main work on McKinley, communication conduit,
and electrical conduit adjustments based on code requirements and American Electric Power
conduit routing requirements for the lighting circuit.
Summary: Change Order No. 2 Items, Underrun (Credits) and Overrun (Increase)
UNDERRUNS
7 7: Structure Backfill (Undistributed) $ 1,125.60
9 9: Storm Sewer Pipe Remove $ 117.15
11 11: Concrete Approaches and Sidewalk Remove $ 1,267.56
16 16: Structure Fence Remove $ 9,467.01
22 22: HMA Pavement Base 440 LBS/SYS $ 5,684.58
25 25: PCCP for Approaches 9 Inches $ 2,160.00
26 26: PCCP for Approaches 6 Inches $ 2,082.08
28 28: Concrete Curb 6 Inch $ 2,260.50
31 31: Sodding Stormwater Ponds $ 16,473.00
32 32: Sodding $ 1,418.34
33 33: Trees 2.5 Inch Caliper $ 21,615.00
34 34: Storm Sewer Pipe RCP 12 Inch $ 739.36
35 35: Storm Sewer Pipe RCP 18 Inch $ 2,769.97
36 36: Storm Sewer Pipe PVC C900 12 Inch $ 753.00
38 38: Storm Sewer Catch Basin 30 Inch Dia. $ 7,308.18
40 40: Sanitary Sewer Pipe PVC 8 Inch $ 2,032.35
44 44: Water Main Pipe DI 8 Inch $ 635.14
54 54: Water Service DI 6 Inch $ 6,273.48
55 55: Water Service Copper 2 Inch $ 11,739.36
Page 2 of 3
56 56: Water Service Copper 1-1/2 Inch $ 5,258.82
57 57: Water Service Copper 1 Inch $ 2,945.35
59 59: Connection to Existing Water Main 6 Inch Priva $ 3,845.42
74 74: Maintain Wastewater Service $ 4,650.00
TOTAL CREDIT FOR UNDERRUNS $ 112,621.25
OVERRUNS
20 20: Compacted Aggregate Base No. 53 $ 22,681.88
21 21: HMA Pavement Base 880 LBS/SYS $ 53,958.00
23 23: HMA Pavement Intermediate 275 LBS/SYS $ 6,934.04
24 24: HMA Pavement Surface 165 LBS/SYS $ 7,951.58
27 27: Concrete Curb and Gutter 6 Inch $ 2,561.50
29 29: Concrete Sidewalk 4 Inch $ 1,926.00
30 30: Concrete Curb Ramp $ 6,867.00
39 39: Storm Sewer Manhole 48 Inch Dia. $ 7,340.66
47 47: Fitting DI 11.25 Degree Bend 8 Inch $ 1,650.66
64 64: Conduit HDPE 3 Inch (Lighting) $ 565.00
65 65: Conduit HDPE 2 Inch (Lighting) $ 725.00
66 66: Handhole (Lighting) $ 8,800.00
67 67: Electrical Wiring (Lighting) $ 4,626.00
76 76: Conduit HDPE 3 Inch (Telecommunications) $ 2,109.00
77 77: Handhole (Telecommunications) $ 2,548.00
TOTAL INCREASE FOR OVERRUNS $ 131,244.32
CHANGE ORDER NO. 2 ITEMS
101 Added 4" Water Laterals $ 27,634.14
102 Added McKinley Fire Hydrant $ 4,120.00
103 Slussers Seedong for Ponds $ 12,104.76
106 Slussers Tree - 1.75" Cal. $ 7,280.00
107 Slussers Tree - 2" Cal $ 11,500.00
108 Footer/Rubble Pile Removal $ 9,116.80
TOTAL INCREASE FOR CHANGE ORDER NO. 2 ITEMS $ 71,755.70
SUMMARY
UNDERRUNS $112,621.25 CREDIT / DEDUCT
OVERRUNS $131,244.32 INCREASE
CHANGE ORDER NO. 2 ITEMS $ 71,755.70 INCREASE
NET CHANGE ORDER NO. 2 $ 90,378.77 NET INCREASE
Page 3 of 3
PROJECT COST SUMMARY
Original Contract: $3,326,371.58
Change Order No. 1 $ 120,499.45 (Increase 3.62%)
Change Order No. 2 $ 90,378.77 (Increase 2.72%)
Total Increase to Contract for Change Orders: $ 210,878.22
Total Increase in Percentage from Original Contract: 6.34%
Final Contract Amount: $3,537,249.26
The remaining balance of the project will be covered through the Division of Water Works,
Water Works, Infrastructure Mains, Account 622-06-604-620-442007. Contact Jacob M.
Klosinski at the Division of Engineering at Ext. 9496 for questions regarding this project.
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 04-20-2026
Name: Jacob M. Klosinski, PE Department of Public Works – Engineering Division
BPW Date: 04-28-2026 Phone Extension: 9496
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Michael Schmidt
Dept. Attorney Attorney Name Michael Schmidt
Purchasing Ashley Rzepka / Mickey Lovy
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 002 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Rieth-Riley Construction (V-00001411)
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name
Youth Services Bureau / South Bend Thrive Subdivision and Off-site
Improvements
Project Number DFO PROJ-00000465; BPW Project No.123-011; PO-0029777
Funding Source Water Works, Infrastructure Mains
Account No. 622-06-604-620-442007
Amount $90,378.77
Terms of Contract
Special Contract Provisions
Purpose/Description The Division of Engineering and recommends the approval of Change Order
No. 2 for the subject project. Change Order No. 2 includes the adjustment of
final quantities and additional scope of work (paving, roadway preparation,
water main appurtenances, hydrants).
For Change Orders Only
Amount of Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: