HomeMy WebLinkAboutChange Order No 1 (F) & PCA - EV Charger Installations Proj No 124-052 - Barnes Concepts
Regarding the closure of the EV Charger Project 124-052:
Barnes Concepts, LLC represented to the City that it had completed its work related to EV Charger
Project 124-052. As is customary, a final walkthrough was done and a punch list was created. It
was observed that there were many items not up to electrical code or specifications written out in
the project contract. These items were asked to be addressed in a timely manner as the worksites
were not operable. Communication between the contractor and City Team became sporadic and
indecisive. The City allowed time for a specific item to come in that needed repaired as a part of the
punch list. Once that timeframe had passed, communication lacked and coordination did not
happen. Only a few items on the initial punch list were addressed. Barnes Concepts has been
advised by the City’s Legal Department that it is in breach of the contract with the City and that no
further payments will be authorized.
Punch items still remaining:
Veterans Memorial
• Each breaker should be labeled, or panel schedule updated, not with a Sharpie
• Subpanel should be securely mounted.
• The Subpanel should be properly landed with all conductors from Main panel
• Fill in trench between electric panel to first pedestal
Boland
• Each breaker should be a 40 Amp breaker
• Each breaker should be labeled, not with Sharpie
• The Subpanel should be properly landed with all conductors from Main panel
• Subpanel breaker at Main panel needs changed out to match existing
Regards,
Kyle Ludlow
1
$49,325.00
$0.00
$49,325.00
X $
$49,233.75
-0.18 %
-0.18 %
0 days
RECOMMENDED FOR
APPROVAL
Extension of date/time by previous change orders
Date/time extension by this change order 0 daysNew completion date/time 6/30/2025
CONTRACTOR
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time 6/30/2025
By this Change Order, the project amount is Increased
91.25Decreased
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns.
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
124-052
EV Charger Installations
1/21/2025
(Final)
PCR #1-CCB Replacement Installation , PCR #3-Retainage
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKSPROJECT CHANGE ORDER
DATE:4/1/2026
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO:
SUBJECT OF CHANGE ORDER:
Member
Member
Approved Date:
President
Member
Member
Printed Name and Title
Barnes Concepts LLC
Company Name
12562 Maryland St.
Address
BOARD OF PUBLIC WORKS
Crown Point, IN 46307
City, State, Zip
Contractor Signature CONSTRUCTION MANAGER
CITY OF SOUTH BEND
April 14, 2026
FINAL COST
WITNESSETH:
Date:
Printed Name
County of Residence
My Commission ExpiresNotary Signature
WITNESSESS:
Before me, the undersigned Notary Public in and for said country and state, personally appeared
_____________________, and acknowledged his/her signature to the above Project Completion Affidavit on the
________ day of _____________, 202______.
The work under the above contract between the City of South Bend and the undersigned contractor having been
completed, the City of South Bend, its officials and agents are hereby released from all claims and demands whatsoever
arising under or by such contract, and that the contractor performed the work within the scope of the Specifications and
Standards of the City of South Bend which were a part of the above Contract.
Barnes Concepts LLC
Company Address
Crown Point, IN 46307
City, State, Zip
Executed this ________ day of _________________, 202__________.
Company Name
Signature 12562 Maryland St.
Printed Name
CONTRACT SIGNED 1/21/2025
PROJECT Installation of eight public EV charging stations. Four at Boland Park and four at Veterans'
124-052 $49,233.75
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
PROJECT COMPLETION AFFIDAVIT
PROJECT NAME EV Charger Installations
PROJECT NO
Member Attest
SOUTH BEND BOARD OF PUBLIC WORKS
_____________________ _____________________
President Member
_____________________ _____________________
Member Member
_____________________ _____________________
DEPARTMENT OF PUBLIC WORKS APPROVAL
This project is acceptable for final approval and we recommend to the Board of Public Works that it be ordained so.
Construction Manager
If the Contractor is a corporation, the following certificate will be executed. I,
____________________________________, certify that I am Secretary of the Corporation executing this release; that
___________________________________________ who signed this release on behalf of the contractor was then
__________________________________ of said Corporation; that said release was duly signed for and on behalf of
said Corporation by Authority of its governing body, and is within the scope of corporate powers:
Secretary's Signature Corporate Seal
Printed Name
4/1/2026
April 14, 2026
BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM
Date 04/01/2026
Name Kyle Ludlow Department Public Works
BPW Date 04/14/2026 Phone Extension 9157
Review and Approval Required Prior to Submittal to Board Diversity Compliance and Inclusion Officer Officer Name
BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. 1 PCA Chg. Order, No. Traffic Control Resolution Other: Ease. /Encroach
Required Information
Company or Vendor Name Barnes Concepts LLC
New Vendor Yes If Yes, Approved by Purchasing No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name EV Charger Installations
Project Number 124-052
Funding Source PROJ00000576, 408-431000 Account No. PR-00037570 PO-0036708
Amount $49,233.75
Terms of Contract
Purpose/Description _Project Closeout with Deduct Change Order for work not completed.
For Change Orders Only
Amount of Increase Decrease
$
($)91.25 Previous Amount $49,325.00
Current Percent of Change: Increase Decrease
%
(.18%)
New Amount $ 49,233.75
Total Percent of Change: Increase Decrease
%
(.18%)
Time Extension Amount: 0 New Completion Date: