Loading...
HomeMy WebLinkAboutChange Order No 1 - Riverfront West Urban Neighborhood Proj No 121-067 - C&E Excavating April 14, 2026 Mr. Bryan Slott C&E Excavating, Inc. 53767 County Road 9 Elkhart, IN 46514 bslott@candeexcavating.com RE: Change Order No. 1 – Riverfront West Urban Neighborhood Development – Project No. 121-067 Dear Mr. Slott: At its April 14, 2026 meeting, the Board of Public Works approved the above referenced Change Order be increased by $522,000, bringing the revised contract amount to $6,501,535 with a new completion date of November 30, 2027. Please forward the following documents in one submittal by April 28, 2026 to my attention for Board of Public Works approval at hhorvath@southbendin.gov : Enclosed is a copy of the Change Order for your records. Sincerely, /s/ Hillary Horvath Hillary Horvath, Clerk 1 $5,979,535.00 $0.00 $5,979,535.00 x $ $6,501,535.00 8.73 % 8.73 % Member Member Member Company Name President Address Member City, State, Zip CITY OF SOUTH BEND Printed Name and Title BOARD OF PUBLIC WORKS Approved Date: Contractor Signature CONSTRUCTION MANAGER Date/time extension by this change order 30 New completion date/time 11/30/2027 CONTRACTOR RECOMMENDED FOR APPROVAL Extension of date/time by previous change orders The original contract sum Net change by previously authorized change orders The contract sum prior to this change order By this Change Order, the project amount is Increased 522,000.00DecreasedThe new contract sum including this change order This Change Order represents a total change of Total change for entire project Original contracted completion date/time 10/31/2027 PROJECT NO:121-067 PROJECT NAME:Riverfront West Urban Neighborhood Infrastructure Improvements CONTRACT DATE:9/18/2025 CHANGE ORDER NO: SUBJECT OF CHANGE Multiple Changes to Address Utility Delays and Necessary Revisions CITY OF SOUTH BEND, INDIANA DEPARTMENT OF PUBLIC WORKS PROJECT CHANGE ORDER DATE:4/14/2026 April 14, 2026 Page 1 of 1 INTER-OFFICE MEMORANDUM DEPARTMENT OF PUBLIC WORKS DIVISION OF ENGINEERING TO: Hillary Horvath, Clerk Board of Public Works FROM: Charlotte Brach, Assistant City Engineer SUBJECT: Change Order No. 1 - Project No. 121-067 Riverfront West Urban Neighborhood Infrastructure Improvements DATE: April 14, 2026 On September 18, 2025, the Board of Public Works entered into an agreement with C&E Excavating, Inc. to perform necessary infrastructure improvements to the Riverfront West Urban Neighborhood area. The City is now requesting that the Board of Public Works approve the following requested changes to the contract: Revised completion date for Milestones 1 & 2 shall now be February 1, 2027. Previous completion dates were December 31, 2025 and October 31, 2026. The additional time is necessary due to utility relocation delays. Milestones 3 & 4 shall remain the same. Milestone 5 shall now be November 30, 2027. In addition to the additional time, the City requests approval for the following changes in scope: 1. $34,000 related to additional watermain and sanitary line work. 2. $158,000 related to plan revisions to work around utility conflicts, including additional excavation, equipment and labor necessary to complete a portion of the work before utilities are permanently relocated. 3. $330,000 related to utility relocation delays and necessary expenses to ensure minimum impact of such delays on Milestones 1 & 2. BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date: 4/6/2026 Name: Charlotte Brach Department of Public Works – Engineering Division BPW Date: 4/14/2026 Phone Extension: 9246 Required Prior to Submittal to Board BPW Attorney X Attorney Name Dept. Attorney Attorney Name Purchasing Check the Appropriate Item Type – Required for All Submissions Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA Chg. Order, No. 1 Traffic Control Resolution Other: Ease./Encroach Required Information Company or Vendor Name C&E Excavating, Inc. New Vendor Yes If Yes, Approved by Purchasing No MBE/WBE Contractor MBE WBE Completed E-Verify Form Attached Yes No Project Name 121-067 Riverfront West Urban Neighborhood Development Project Number PROJ605 Funding Source Riverfront West Development Area TIF/Water Capital/Wastewater Capital Account No. PO # 40183 Amount $522,000.00 Terms of Contract Base Bid and Alternate Special Contract Provisions N/A Purpose/Description Change Order No. 1 for the Riverfront West Urban Neighborhood Development Project for multiple changes to address utility delays and necessary revisions. See attached memo. For Change Orders Only Amount of Increase Decrease $ 522,000.00 ($ ) Previous Amount $ 5,979,535.00 Current Percent of Change: Increase Decrease 8.73% ( %) New Amount $ 6,501,535.00 Total Percent of Change: Increase Decrease 8.73% ( %) Time Extension Amount: 30 calendar days New Completion Date: 11/30/2027