HomeMy WebLinkAboutChange Order No 3 - South Bend City Hall Renovations Proj No 124-001 - Larson-Danielson
March 10, 2026
Mr. Mark E. Gott
Larson-Danielson Construction Co., Inc.
302 Tyler Street
LaPorte, IN 46350
btl@ldconstruction.com
RE: Change Order No. 3 – South Bend City Hall Renovation – Project No. 124-001
Dear Mr. Gott:
At its March 10, 2026 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $16,280.08, bringing the revised contract
amount to $7,921,618.85.
Enclosed is a copy of the Change Order for your records.
Sincerely,
/s/ Hillary Horvath
Hillary Horvath, Clerk
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:October 10, 2026
PROJECT NO:124-001
PROJECT NAME: South Bend City Hall Renovation
CONTRACT DATE:Nov 25, 2024 CHANGE ORDER NO.3
SUBJECT OF CHANGE ORDER:
See attached memo for owner additions and resulting electrical rework for field orders as well as
time extension related to elevator delays.
The original contract sum $ 7,327,000.00
Net change by previously authorized change orders $ 578,338.77
The contract sum prior to this change order $ 7,905,338.77
By this Change Order, the project amount is Increased
Decreased $ 16,280.08
The new contract sum including this change order $ 7,921,618.85
This Change Order represents a total change of
Total change for entire project 8.12 %
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
RECOMMENDED FOR APPROVAL
CONTRACTOR Construction Manager
CITY OF SOUTH BEND
BOARD OF PUBLIC WORKS
Approved Date: Contractor Signature
Printed Name and Title President
Company name Member
Address Member
City, State, Zip Member
Member
0.22 %
October 10, 2025
Larson-Danielson Const. Co.,Inc.
302 Tyler Street
LaPorte, IN 46350
42 calendar days
August 29, 2025
March 10, 2026
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Hillary Horvath, Clerk
Board of Public Works
FROM: Becca Plantz, PE, Director of Engineering Services
SUBJECT: Award Project No. 124-001
South Bend City Hall Renovation
DATE: March 2, 2026
This final change order for the City Hall remodel increases the contract by $16,280.08 to
cover additional interior signage and miscellaneous electrical adjustments for cubicles,
office technology, vending and weapons detection. The change order also extends the
project completion date from August 29, 2025 to October 10, 2025 is directly tied to
delays caused by the procurement and installation of the new elevator system.
All remaining construction activities after August were dependent on keeping the
first-floor lobby, corridor, and adjacent areas open to support elevator material staging,
installation, and inspection. These constraints prevented completion of finishes, office
spaces, and exterior elements until the elevator work was substantially complete.
Despite these limitations, the project remained on track in all other areas. Punchlist
work for floors 2–6 was completed on July 14, demonstrating that the building was
otherwise progressing toward an August completion. Temporary occupancy was
granted on September 18, allowing City staff to begin moving in before substantial
completion. To support this early move-in, the contractor maintained scaffolding to load
in office furniture, coordinated elevator operator support, and sequenced work to avoid
disrupting City operations.
Remaining work after October 10 was punch list related and dependent on third-party or
owner-provided components, including test and balance delayed by existing mechanical
equipment repairs not included in the remodel contract, replacement locksets required
due to existing hardware compatibility issues, and installation of the Code Blue elevator
controller pending manufacturer backorder.
LaPorte, IN 46350
302 Tyler Street
Ph : 219-362-2127
Change Request
Phone:
Job:56-713 SB,CTYOF-CITY HALL RENOVATIONS
Number:
Date:
57R
9/17/25
To:Rebecca Plantz
SOUTH BEND, CITY OF
227 W. JEFFERSON BLVD
SOUTH BEND, IN 46601
Ph: (574)235-5998
Description:REV Misc Electrical Scope Revisions
Reason: Owner Request
We are pleased to offer the following specifications and pricing to make the following changes:
Per Owner request,furnished all L/M/E/S to complete misc electrical scope revisions: 1) Add/Relocate Cat 6 cables 2) Vending area
extra work
Description Material Subcontract Other PriceLaborEquipment
Owner requested electrical scope revisions $12,950.00$12,950.00
(4) HRS SUPT @ $ 107 / HR $428.00$428.00
$13,378.00Subtotal:
$85.60OH & P Labor 20.00%$428.00
$0.00OH & P Material
$0.00OH & P Equipment
$300.00Subcontractor First 3K 10.00%$3,000.00
$1,459.09Subcontractor After 3K 7.00%$20,844.18
$152.23Bond Markup 1.00%$15,222.69
$15,374.92Total:
If you have any questions, please contact me at (219)575-6135.
Date:
Approved by:Submitted by:Mark Gott
LARSON-DANIELSON CONST. CO INC
Page 1 of 1
LaPorte, IN 46350
302 Tyler Street
Ph : 219-362-2127
Change Request
Phone:
Job:56-713 SB,CTYOF-CITY HALL RENOVATIONS
Number:
Date:
58
10/7/25
To:Rebecca Plantz
SOUTH BEND, CITY OF
227 W. JEFFERSON BLVD
SOUTH BEND, IN 46601
Ph: (574)235-5998
Description:Add'l Interior Signage Pricing
Reason: Owner Request
We are pleased to offer the following specifications and pricing to make the following changes:
(Per Owner Request)Provide all required L/M/E/S to furnish & install additional interior placard signage, as follows: (1)EA 10"w x 8"h
"CITY CLERKS VAULT", (10)EA 7"w x 6"h "ELECTRICAL", & (1)EA "301 COUNCIL CHAMBERS" ADA Signs (Braille).
NOTE:EXTRA SIGNS HAVE APPROX (4-6)WKS AFTER APPROVAL.
Description Material Subcontract Other PriceLaborEquipment
F/I extra interior signage per Owner request $698.00$698.00
(1) HR Supt @ 107/HR $107.00$107.00
$805.00Subtotal:
$21.40OH & P Labor 20.00%$107.00
$0.00OH & P Material
$0.00OH & P Equipment
$69.80Subcontractor First 3K 10.00%$698.00
$0.00Subcontractor After 3K
$8.96Bond Markup 1.00%$896.20
$905.16Total:
If you have any questions, please contact me at (219)575-6135.
Date:
Approved by:Submitted by:Mark Gott
LARSON-DANIELSON CONST. CO INC
Page 1 of 1
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 3/2/2026
Name: Becca Plantz Department of Public Works – Engineering Division
BPW Date: 3/10/2026 Phone Extension:
Required Prior to Submittal to Board
BPW Attorney X Attorney Name
Michael Schmidt
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 3 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Larson Danielson Construction Company
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name South Bend City Hall Renovation
Project Number 124-001
Funding Source Economic Development LIT, TIF, Water & Sewer Capital
Account No. PROJ 362
Amount
Terms of Contract
Purpose/Description Change order 3 to increase the contract amount for additional interior signage
and miscellaneous electrical adjustments as furniture and technology moved
in as well as a completion date extension based around elevator delays.
For Change Orders Only
Amount of Increase
Decrease
$ 16,280.08
($ )
Previous Amount $ 7,905,338.77
Current Percent of Change:
Increase
Decrease
0.22%
( %)
New Amount $ 7,921,618.85
Total Percent of Change:
Increase
Decrease
8.12%
( %)
Time Extension Amount: 42 calendar days
New Completion Date: October 10, 2025