HomeMy WebLinkAboutRedevelopment Commission Minutes 01.22.26 - Signed
South Bend
Redevelopment Commission
215 S. Dr. Martin Luther King, Jr. Blvd., Room 301, South Bend, Indiana
Minutes
Regular Meeting
January 22, 2026 – 9:30 a.m.
City Hall Council Chambers 3rd Floor or via:
https://tinyurl.com/RDC2025-2026-Meetings
Meeting Recording Link: https://tinyurl.com/RDC-Meeting-Recordings
The South Bend Redevelopment Commission was called to order at 9:30 a.m.
President Troy Warner presiding.
1. ROLL CALL
Members Present: Troy Warner, President
Dave Relos, Vice President
Eli Wax, Secretary
Gillian Shaw, Commissioner
Ophelia Gooden-Rodgers, Commissioner
Marcus Ellison, Non-Voting Advisor
Legal Counsel: Jenna Throw, City Attorney
Redevelopment Staff: Erik Glavich, Director of Growth and Opportunity, DCI -
Virtual
Lewis Kouassi, Director of Finance, DCI
Joseph Molnar, Asst. Dir. of Growth and Opp., DCI
Erin Michaels, Property Development Manager, DCI
Abigail Magas, City Engineer
Leslie Biek, Assistant City Engineer
Darryl Scott, Chief of Staff
Bianca Jones, Interim Officer of Diversity, Compliance &
Inclusion
Laura Hensley, Board Secretary, DCI
Nicolas Munsen, Assistant City Attorney
Attending: Tim Widerquist, , Widerquist Development, LLC
Karl Widerquist, , Widerquist Development, LLC
Matt Barrett, 110 S. Niles Ave.
Tina Patton, 7070 Sherman Ave.
CITY OF SOUTH BEND REDEVELOPMENT COMMISSION REGULAR MEETING – January 22, 2026
Page | 2
2. Approval of Minutes
A. Approval of Minutes of the Regular Meeting of Thursday, January 8, 2026
Upon a motion by Ophelia Gooden-Rodgers for approval, second by Eli Wax,
the motion carried unanimously; the Commission approved the minutes of
the regular meeting of January 8, 2026.
3. Approval of Claims
A. Claims Allowances January 14, 2026
Upon a motion by Ophelia Gooden-Rodgers for approval second by David
Relos, the motion carried unanimously; the Commission approved the
claims allowances of January 14, 2026.
4. Old Business
A. None
5. New Business
A. River West Development Area
1. Resolution No. 3663 (Establishing the Offering Price, Approving Bid
Specifications, and Approving Notice of Intended Disposition of 1818 W.
Sample St.)
Erin Michaels, Property Development Manager, presented the proposed
disposition of a City-owned parcel at 1818 W. Sample St. The property is
located along West Sample St. near the Ice Box and the Lippert plant.
The RDC acquired the 2.71-acre parcel in 2002. It is zoned Industrial (I).
Historical aerials show it remained vacant until 1972, when it was
converted into a parking lot, which has been its sole use ever since. We
now have interest in redeveloping the site for a more productive
purpose. Disposition is the first required step in that process.
The minimum bid is $71,325, which is the average of two recent
appraisals. Bids are due February 12, 2026, at 9:00 AM and will be
opened publicly at the RDC meeting at 9:30 AM that same day.
President Warner inquired about the disposition process and Ms.
Michaels stated, that State law requires the Redevelopment
Commission to offer any Commission-owned parcel for disposition
before we can begin negotiations. To do that, we present a resolution to
the Commission. If approved, we publish a Notice of Intended
Disposition in the South Bend Tribune for two consecutive Fridays.
During that period, we accept bids from interested parties.
CITY OF SOUTH BEND REDEVELOPMENT COMMISSION REGULAR MEETING – January 22, 2026
Page | 3
All bids must follow the requirements in the disposition packet, which
will be available online and in physical form at City Hall. If we receive any
bids, we will open them publicly at the February 12th RDC meeting and
review them for compliance. If we receive no bids, state law requires a
30-day waiting period. After those 30 days, we may begin negotiations,
and at that point the minimum bid price is no longer fixed at $71,325.
This allows flexibility in negotiating the purchase price and terms.
Tina Patton stated that she noticed in the notes that there has been
interest in redeveloping this property. Her question is: does that interest
involve a bar, a gas station, or any other use that wouldn’t be considered
family-friendly? Joseph Molnar, Assistant Director of Growth and
Opportunity, explained that the interest we’ve received so far has not
involved any of those types of uses. However, one of the reasons we’re
moving this property through the formal disposition process is that we
cannot discuss or negotiate with anyone until that process is complete.
This resolution is the first step. Ultimately, the Commission has full
authority over whether to sell the property, and any interested party
would be required to clearly state their intended use up front.
If someone proposed a gas station or liquor store, staff would be unlikely
to recommend that use. But final approval rests with the Redevelopment
Commission.
Upon a motion by David Relos for approval, seconded by Ophelia
Gooden-Rodgers, the motion carried unanimously; the Commission
approved Resolution No. 3663 as presented on January 22, 2026.
2. Purchase Agreement for 534 Laporte Ave. (Widerquist Development,
LLC)
Erin Michaels, Property Development Manager, explained that this
property went through disposition a few months ago. It is a small former
service station on LaPorte Ave., just north of City Cemetery. The parcel
is approximately 0.11 acres and includes a 250-square-foot structure. It
is zoned Urban Neighborhood Flex. The Board of Public Works acquired
the former pump station in 2017, removed the underground tanks, and
transferred it to the RDC in 2023 to support potential redevelopment.
Widerquist Development is a local developer with more than 30
renovated properties in South Bend, many of them located just down the
street from this site. The photos illustrate the before-and-after
improvements they have completed on other buildings in the area,
highlighting their work on both exterior and interior upgrades.
Purchase Agreement – Key Terms
• Purchase Price: $2,000
CITY OF SOUTH BEND REDEVELOPMENT COMMISSION REGULAR MEETING – January 22, 2026
Page | 4
• Minimum Investment: $20,000
• Planned Use: Renovate the building into an office for their
business
• Due Diligence Period: 60 days
• Closing Deadline: 30 days after due diligence
• Construction Start: Within 12 months of closing
• Construction Completion: Within 24 months of closing
• Certificate of Completion: Required from the RDC once the
project is finished
Tim Widerquist added that he’s been investing in this intersection for
about ten years, and this property has been an ongoing eyesore. Mr.
Widerquist buys and rents residential properties nearby, and its poor
condition makes it harder for him to rent his places across the street.
Cleaning it up and relocating his office would improve the appearance of
his properties and the neighborhood overall.
LaPorte and Walnut are important intersections coming out of
downtown. There’s renewed energy in the area, and he believes this site
can serve as an anchor for cleanliness and continued improvement.
Commissioner Gooden-Rodgers spoke in favor of the project. Secretary
Wax asked what the average appraisals were when the property was put
through disposition and Ms. Michaels stated $5,000. Vice President
Relos asked if utilities would be needed, what hours the office would be
open, and if there was a historic designation on this site. Mr. Widerquist
stated that his plans will be a leasing office with hours of operation by
appointment and that water and electric will be needed at this site. Ms.
Michaels confirmed that there are no historic designations at this
property.
Upon a motion by Gillian Shaw for approval, seconded by Eli Wax, the
motion carried unanimously; the Commission approved the Purchase
Agreement as presented on January 22, 2026.
B. River East Development Area
1. Budget Request (Mishawaka Streetscape)
Leslie Biek, Assistant City Engineer, presented a request for an
additional appropriation to cover project change orders. This project
was bid in February, with limits from Longfellow to Emerson. The West
side, from Longfellow to the overpass, received full streetscape
treatment. East of the railroad tracks to Emerson, we completed a
lighter streetscape focused mainly on utility connections. The project
included a new bike path on the south side of the road, upgraded
utilities, and our standard streetscape elements.
CITY OF SOUTH BEND REDEVELOPMENT COMMISSION REGULAR MEETING – January 22, 2026
Page | 5
The work is substantially complete, but a few remaining items will be
finished once materials arrive or when weather allows in the Spring.
The largest unforeseen cost came from removing old railroad ties left
from the former trolley. We knew the trolley had run through the
corridor and estimated removal needs, but once construction began, we
found the ties conflicted with nearly all work on the south side of the
road—and they were fully encased in concrete. Partial removal wasn’t
feasible and would have cost as much as full removal while also delaying
the project, so we removed the entire section. This item alone accounted
for about $380,000, roughly half of the total change orders.
The financial summary shown here reflects updated funding, including
preliminary engineering dollars from River East and transferred funds
from the Kelly’s Pub project, due to shared site work. We are requesting
an additional $200,000 to complete the project.
Vice President Relos asked, what is left to do in the Spring. Ms. Biek
stated trees will be planted in the Spring rather than the Fall. A small
amount of paver work is still underway. The main delay is the new signal
arm—right now the intersection is operating as a temporary four-way
stop with LED flashers. Once the signal arm arrives, we’ll be able to put
the traffic signal into full operation at Longfellow.
Permanent striping will also be completed in the Spring. As for
sidewalks, we installed new sidewalk on the west side of the tracks, and a
significant amount on the south side east of the tracks where it was
needed for utility work. We also added some on the North side based on
project needs.
Commissioner Shaw asked what we could learn from this mistake and
Ms. Biek explained that Engineering did take some pavement cores, but
they focused on areas where the new utilities were being installed,
which was mostly in the center of the roadway—not where the old
trolley tracks were located. We can definitely take additional cores,
especially near inlets and other locations where we may have conflicts
underground, to get a better understanding of what remains beneath the
surface.
Matt Barrett asked, it appears this work has already been completed, so
he’s wondering what the process is for handling change orders.
Additionally, if the Redevelopment Commission does not approve the
funding, where would the money come from? Ms. Biek responded, since
the work has already been completed and the City has directed its
removal, if the Commission does not approve this request, we will need
CITY OF SOUTH BEND REDEVELOPMENT COMMISSION REGULAR MEETING – January 22, 2026
Page | 6
to identify an alternative funding source to cover the cost. The change
order will follow our standard project procedure and be approved
through the Board of Public Works. Commissioner Wax also spoke in
favor of policy for appropriations.
Upon a motion by David Relos for approval, seconded by Gillian Shaw,
the motion carried unanimously; the Commission approved the Budget
Request as presented on January 22, 2026.
C. Redevelopment General Fund (a.k.a Pokagon-South Bend Fund)
1. Budget Request (2026 Business Assistance Suite)
Bianca Jones, Interim Officer of Diversity, Compliance & Inclusion,
presented an overview of the Small Business Assistance Suite. This
program has been operating for about four and a half years and is
structured as a cohort-based business readiness program designed to
build capacity for local businesses. We don’t provide grants; instead, we
focus on business readiness and improving access to capital. Our
program includes workshops on legal compliance, business operations,
financial management, marketing, and more. Each participant is paired
with a business coach who helps with goal-setting, progress tracking,
and coordinating support services such as legal and accounting
assistance from licensed professionals.
So far in 2025, we’ve supported 77 businesses through coaching and
professional services. Three businesses accessed the City’s revolving
loan fund, and six were connected to resources for MBE/WBE
certification. Overall, we help businesses strengthen their financial and
operational systems, increase their use of professional service providers,
and prepare for funding, contracting, and staffing opportunities.
Key outcomes are that we track the number of businesses completing
the cohort, readiness milestones like financial systems and legal
documentation, and businesses pursuing contract or funding
opportunities. We also measure growth in hiring and engagement with
professional service providers.
Ms. Jones is requesting a $100,000 allocation from the Pokagon South
Bend Fund to sustain and scale the program. This funding will support
cohort-based training, program oversight, and reporting. We plan to
serve at least 40 businesses, with approximately $2,000 invested per
business, and continue strengthening the local pipeline of
contract-ready and capital-ready businesses.
Secretary Wax asked, do you recall last year’s allocation? Ms. Jones
responded that the Small Business Assistance Suite received $85,000 in
CITY OF SOUTH BEND REDEVELOPMENT COMMISSION REGULAR MEETING – January 22, 2026
Page | 7
2025. Regarding the $2,000 per business for direct readiness support:
each participant typically receives about ten hours of coaching, at
roughly $75 per hour. We also cover professional service costs, for
example, setting up financial systems like QuickBooks or Wave, which
we provide at no cost for several months. Participants may also work
with attorneys for contracts, partnership agreements, and similar needs.
The $2,000 reflects the value of these services, not direct cash
assistance.
These services are not provided by City staff. We contract with outside
providers. For the past several years, the program has been
administered by the IMPower Center, which recruits coaches and
professional service providers. We vetted them to ensure they meet
program requirements, and then they are brought on accordingly.
Commissioner Shaw asked for more details on why the program plans to
increase support per business while serving fewer businesses overall.
Ms. Jones replied that, previously, the program worked more like an
à-la-carte model—businesses received one-off services, such as legal
help, but we had limited follow-up and mixed long-term results. By
reducing the number of participants, we can provide deeper, more
consistent support and track outcomes throughout the year.
We also found that many businesses reapplied because the initial
assistance wasn’t enough. Although we’ve had about 800 applications,
the actual number of unique businesses is closer to 500–600, since many
returned seeking additional help.
Commissioner Gooden-Rodgers asked, of the 77 businesses you
mentioned, how are you measuring success? Are these businesses still
operating, and where is this program advertised? If someone wants to
start a small business, how would they know how to get involved?
Ms. Jones explained that our follow-up shows that most of the
businesses we supported last year are still operating. At the end of each
year, we send a questionnaire to check on their progress. Many have
secured new contracts—both private and City-related—and six have
completed MBE/WBE certification. Several have also accessed the
Revolving Loan Fund or expanded their business activity.
Currently, we advertise mainly through Facebook and word of mouth,
and we’re working to strengthen our marketing strategy. Because many
participants are newer businesses, we also coordinate with ecosystem
partners who focus on early-stage startups. For example, programs like
the South Bend Entrepreneurship Adversity Program help
entrepreneurs get registered with the Secretary of State, and once they
complete that program, they qualify for ours.
CITY OF SOUTH BEND REDEVELOPMENT COMMISSION REGULAR MEETING – January 22, 2026
Page | 8
Commissioner Shaw asked the question, how are businesses prioritized
when there are far more applicants than available spots. Ms. Jones
explained that the 800 applications represent four years of submissions,
with about 100 last year. Previously, the program supported anyone
starting a business, but this year it prioritizes businesses that align with
City purchasing needs and can create measurable impact. There is no
race or gender consideration—the program is open to any small, local
business in South Bend. Demographic questions remain on the
application only for historical data purposes.
Joseph Molnar, Assistant Director of Growth and Opportunity, wanted
to clarify, “These funds come specifically from the Pokagon South Bend
Fund, which is tied to the City’s agreement with the Four Winds Casino.
The agreement states that these dollars must support initiatives that
improve educational opportunities and address poverty and
unemployment in the city. These funds are separate from our standard
TIF resources, and I wanted to make that distinction clear for the public.”
Upon a motion by Ophelia Gooden-Rodgers for approval, seconded by
Gillian Shaw, the motion carried unanimously; the Commission approved
the Budget Request as presented on January 22, 2026.
6.Progress Reports
A.Tax Abatement
None
B.Common Council
None
C.Update – Ivy Alley
Joseph Molnar, Assistant Director of Growth and Opportunity, stated that
we will give an update at the February 12, 2026 meeting.
7.Next Commission Meeting
Thursday, February 12, 2026, 9:30 a.m., City Hall Council Chambers 3rd Floor
8.Adjournment
Thursday, January 22, 2026, 10:11 a.m.
______________________________ ______________________________
Eli Wax, Secretary Troy Warner, President