January 27, 2026
Mr. David Merkel
Larson-Danielson Construction Co., Inc.
302 Tyler St.
LaPorte, IN 46350
mcd@ldconstruction.com; btl@ldconstruction.com
RE: Change Order No. 5 – Raclin Murphy Encore Center – Project No. 123-056
Dear Mr. Merkel:
At its January 27, 2026 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $250,703.83, bringing the revised contract
amount to $16,304,225.09 and a completion date of January 23, 2026.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Hillary Horvath
5
$ 15,202,000.00
$ 581,521.26
$ 15,783,521.26
X
#$
$ 16,034,225.09
3.83 %
5.19 %
Contractor Signature CONSTRUCTION MANAGER
CITY OF SOUTH BEND
Address
BOARD OF PUBLIC WORKS
0
City, State, Zip
Printed Name and Title
0
Company Name
0
Member
Member
Member
Approved Date:
President
Member
SUBJECT OF CHANGE ORDER:
123-056
Raclin Murphy Encore Center
8/26/2024
Variety of cost increases and savings as detailed in the attached
documentation.
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO:
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKSPROJECT CHANGE ORDER
DATE:1/27/2025
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is Increased
250,703.83Decreased
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time 9/17/2025
52 Days
RECOMMENDED FOR
Extension of date/time by previous change orders
Date/time extension by this change order 45
New completion date/time 1/23/2025
CONTRACTOR
January 27, 2026
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Hillary Horvath, Clerk Board of Public Works
FROM: Patrick Sherman: Director of Project Management
SUBJECT: Raclin Murphy Encore Center: Change Order #5
DATE: January 22nd, 2026
Greetings, The documents herein detail the costs associated with Change Order #5 for the Raclin Murphy Encore Center project. See the attached This includes a variety of costs associated with the
project including unforeseen issues and some necessary design changes. It also includes the addition of some monumental donor signage for the building. This is to acknowledge the
contributions of generous donors that have contributed more than $15M towards the construction of the Raclin Murphy Encore Center and subsequent parking garage.
The date is also being extended to January 23rd, 2026. There are a number of justified delays due to needing to do re-designs after unforeseen issues both in the building and underground related to utility conflicts.
With this change order, the entire change percentage is now at 5.2%, 1.2% of which is unforeseen, which puts the general change at 4%. These changes are still within the planned
contingency in the project. This change order also includes project savings of $81,964.28, which reflects efforts by the project team to control allowance usage and control costs with value engineering. Total cost controls on the project reduced cost by about 1%.
Thank you and please let me know if you have any questions.
Patrick Sherman
Ph : 219-362-2127
302 Tyler Street
LaPorte, IN 46350
Change Order
Date:
Project:
LARSON-DANIELSON CONST CO. INC.
302 Tyler Street
LaPorte, IN 46350
56-702 SBPUBWKS-RCLN MRPHY ENCORE
Change Order:5
1/16/2026
To Contractor:
Architect's Project: SOUTH BEND, IN 46601
211 N MICHIGAN ST
The Contract is changed as follows:
Change Order 5
21R CCD 8 Floor to Floor Elevation Changes $27,256.00
34 Relocate Plumbing at Portals $2,311.00
39 Credit for Sternburg Light Fixtures $-10,500.00
49B-R CCD 13 Interior Portal Changes (includes Restrooms) & CCD 7 Basement Portal Changes $27,216.00
49AR CCD 13 Portal Changes - Structural $69,491.00
59 CCD 14 Additional Visual Displays $31,912.00
71 Credit for Lighting Controller $-8,100.00
72 Relocate Fire Protection at Portals $1,441.00
73 RFI 223 Exit Signs in EOA $609.00
75A Extend Terrazzo to Colonnade $5,062.00
76 Rework Storm Due to Conflicts $3,954.00
77 Rework Sanitary Due to Conflicts $113.00
78 Delete WC3 $-2,500.00
79 Donor Signage $134,504.11
80 Credit to Remove Acoustic Wall Panels $-10,557.00
81 Change Ceiling Tile Room 104 $1,130.00
84 Banquet Seating Memorabilia Swap $0.00
85 Rework Site Concrete/Bollards Eastside $3,613.00
86 Change Grilles $3,360.00
89 Exit Signs in Equity in Arts $1,799.00
91 Change Out VIP Unistrut Lighting $15,570.00
92 Additional Corner Guards $1,141.00
93 Beer Taps $2,186.00
95 Delete Installation of Picture Frame Trim $-1,540.00
98 Reduce Allowance $-48,767.28
$250,703.83Total:
Ph : 219-362-2127
302 Tyler Street
LaPorte, IN 46350
Change Order
Date:
Project:
LARSON-DANIELSON CONST CO. INC.
302 Tyler Street
LaPorte, IN 46350
56-702 SBPUBWKS-RCLN MRPHY ENCORE
Change Order:5
1/16/2026
To Contractor:
Architect's Project: SOUTH BEND, IN 46601
211 N MICHIGAN ST
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACT AND OWNER.
OWNERARCHITECT
SHIVE-HATTERY
CONTRACTOR
LARSON-DANIELSON CONST CO. INC.
The date of Substantial Completion as of the date of this Change Order therefore is
The Contract Time will be increased by 45 days.
$15,202,000.00
$16,034,225.09
The original Contract Amount was
Net change by previously authorized Change Orders
The Contract Amount prior to this Change Order was
The Contract will be increased by this Change Order in the amount of
The new Contract Amount including this Change Order will be
$581,521.26
$15,783,521.26
$250,703.83
321 SOUTH MAIN STREET,
SOUTH BEND, IN 46601
302 Tyler Street
LaPorte, IN 46350
(Signature)(Signature)
Date DateDate
ByBy By
(Signature)
BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM
Date: 01/22/2026
Name: Patrick Sherman Department of Public Works – Engineering Division
BPW Date: 01/27/2026 Phone Extension: 5601
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Michael Schmidt
Dept. Attorney Attorney Name
Purchasing Mickey Lovy
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA Chg. Order, No. 5 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Larson Danielson Construction
New Vendor Yes If Yes, Approved by Purchasing No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No Project Name Raclin Murphy Encore Center
Project Number 123-056
Funding Source Multiple
Account No. PR/PO # 32487
Amount $250,703.83
Terms of Contract Lump Sum Bid
Special Contract Provisions
Purpose/Description Change order for various items related to the Raclin Murphy Encore Center asdetailed in the attached memo.
For Change Orders Only
Amount of Increase Decrease
$250,703.83
($ )
Previous Amount $ 15,783,521.26 Current Percent of Change: Increase Decrease
3.8%
( %)
New Amount $ 16,034,225.09
Total Percent of Change:
Increase Decrease
5.2%
( %)
Time Extension Amount: 45 Days
New Completion Date: 01/23/2026