December 16, 2025
Mr. Lynn Bauer
Milestone Contractors, L.P.
24358 State Road 23
South Bend, IN 46614
lbauer@milestonelp.com; akrueger@milestonelp.com
RE: Change Order No. 2 (Final)/Project Completion Affidavit
VPA Athletic Court Renovations, Phase II - Project No. 121-033AR2
Dear Mr. Bauer:
At its December 16, 2025 meeting, the Board of Public Works approved the Final
Change Order for this project, be decreased by $95,631.745. The final contract amount
is $1,508,316.58.
In addition, the Project Completion Affidavit for this project was approved in the
amount of $1,508,316.58. Copies of the Change Order and Project Completion Affidavit
are enclosed for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Hillary Horvath
Hillary Horvath, Clerk
Enclosures
HH
December 16, 2025
12/10/2025
December 16, 2025
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 12/10/2025
Name Kyle Ludlow Department Public Works
BPW Date 12/19/2025 Phone Extension 9157
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer Officer Name
BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease. /Encroach
Required Information
Company or Vendor Name Milestone Contractors, L.P.
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name VPA Athletic Court Renovations, Ph II
Project Number 121-033AR2
Funding Source ARP Appropriation
Account No. PR-00015677 PO-0018558
Amount $1,508,316.58
Terms of Contract
Purpose/Description _Project Closeout
For Change Orders Only
Amount of Increase
Decrease
$
($ 95,631.75)
Previous Amount $ 1,603,948.33
Current Percent of Change:
Increase
Decrease
%
(5.96%)
New Amount $ 1,508,316.58
Total Percent of Change:
Increase
Decrease
%
(5.43%)
Time Extension Amount:
New Completion Date: