September 23, 2025
Mr. Dalton Pafford
Byrne & Jones Construction
13940 St. Charles Rock Road
Sant Louis. Missouri 63044
dpafford@byrneandjones.com
RE: Change Order No. 1 – VPA Leeper Park Tennis Courts – Project No. 124-022
Dear Mr. Pafford:
At its September 23, 2025 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $14,950, bringing the revised contract amount
to $1,771,121.07.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Hillary Horvath
Hillary Horvath, Clerk
Enclosures
HH
Byrne & Jones Construction
13940 St. Charles Rock Road
Saint Louis, Missouri 63044
Phone: (314) 567-7997 Fax: (314) 567-1828
www.byrneandjones.com
Project Name:Change Order Number:1
Customer:City of South Bend Date:
Contract Number:S19575-DJP Project Number: S19475-DJP
Owner Rep.:Lidya Abreha Project Manager:Dalton Pafford
PT Court Testing
Addition of third party testing on the PT pours 14,950.00$
CHANGE ORDER #1 14,950.00$
B&J CO NUMBER DATE DESCRIPTION CALENDAR DAYS REJECTED OPEN APPROVED
1 PT Court Testing $14,950.00
`
Change Order - Totals $0.00 $0.00 $14,950.00
Original Contract Amount:$1,756,171.07
Approved Change Orders: $14,950.00
Total Contract Amount (Inc. CO's): $1,771,121.07
Open Change Orders: $0.00
Potential Contract Amount (Inc. Approved CO's & Open CO's): $1,771,121.07
Total Approved (ADDED/DELETED) Calendar Days:
Signature: Date: Signature: Date:
Change Order Summary
NOTES:
9/12/25
Byrne & Jones Change Order
VPA Leeper Park Tennis Courts
September 12, 2025
CHANGE ORDER #1
CHANGE ORDERS
September 23, 2025
Subsurface Investigation and Foundation Engineering
Construction Materials Testing and Inspection
Environmental Services
Alt & Witzig Engineering, Inc.
1418 86th Place • Merrillville, Indiana 46410
Geotechnical (574) 276-4151• Testing (219) 314-9028
W & A
Offices:
Cincinnati • Columbus, Ohio
Indianapolis • Evansville • Terre Haute • Fort Wayne • Lafayette •
Merrillville, Indiana
August 12, 2025
Byrne & Jones
Attention: Mr. Dalton Pafford
Re: Construction Materials Testing
& Inspection Services
Leeper Park
South Bend, Indiana
Proposal No. 25MV021
Dear Mr. Pafford:
Pursuant to your request, Alt & Witzig Engineering, Inc., would like to furnish you with the
applicable unit rates for the construction materials testing and inspection services and cost
estimate required for the above referenced project.
It is proposed that our fee for the performance of any inspection or testing services be
determined on a unit charge basis in accordance with the enclosed Schedule of Services and Fees
for Construction Quality Control.
Thank you for the opportunity to offer our services. We look forward to working with you on this
project.
Sincerely,
ALT & WITZIG ENGINEERING, INC.
Andrew Beneturski
Enclosure: Cost Estimate
Fee Schedule
Materials Testing & Construction Quality Control
Leeper Park
Alt & Witzig Proposal # 25MV021
August 12, 2025
Page 2 of 3
Leeper Park - Cost Estimate
Service Service Detail Unit Cost/ Unit Cost
Senior Engineering Technician 1 Full Days 3
6 hrs on site, travel
8 968.00 $ 7,744.00
Half Days
2 hrs on site, travel
4 516.00 $ 2,064.00
Concrete Specimens 2 4x8 48 22.00 $ 1,160.00
Cylinder Pickup Trip 4 359.00 $ 1,434.00
Management Time Hour 8 145.00 $ 1,160.00
Estimated Total
$
13,458.00
1. Services include reinforcing steel inspections, post tension cable installation and stressing inspections, concrete
testing, masonry testing/inspections. Multiple services can be performed during a single site visit.
2. One set of (6) compression test specimens cast for each day’s pour of each concrete mixture, plus one set for each
additional 100 CY.
3. (1) half day and (2) full days for each pour, (1/2) day PT pre pour inspection, (1) concrete testing, (1) PT stressing.
• Testing will be charged on a time and materials basis as scheduled by the contractor. If
the actual number of trips exceeds the above noted estimate additional fees will be
accrued.
Fee Schedule
Materials Testing & Construction Quality Control
Leeper Park
Alt & Witzig Proposal # 25MV021
August 12, 2025
Page 3 of 3
Construction Materials Testing and Inspection
Professional Services Unit Price Unit
Senior Engineering Technician
Regular Time
Overtime
$ 105.00
$ 147.00
Hour
Hour
Project Manager $ 145.00 Hour
Project Engineer, P.E. $ 165.00 Hour
Mileage $ 0.80 Mile
Equipment Unit Price Unit
Nuclear Density Gauge, ASTM D2922, ASTM D 2950 $ 65.00 Day
Housel Penetrometer, Dynamic Cone Penetrometer $ 65.00 Day
Laboratory Testing Services Unit Price Unit
Standard Moisture-Density Relationship, ASTM D 698 $ 190.00 Test
Modified Moisture-Density Relationship, ASTM D 1557 $ 190.00 Test
Cylinder Compressive Strength, ASTM C 39 $ 22.00 Test
NOTE: This is only a partial list of services offered by Alt & Witzig Engineering, Inc. Fees for other services are
available upon request. Field services are charged with a four (4) hour on-site minimum, excluding cylinder pick-
ups. A one-day notice is preferred for scheduling field services. The regular time rates apply to work performed
within eight (8) hours, during a normal workday. A normal day is from 7:00 a.m. - 6:00 p.m. excluding Saturdays,
Sundays, and holidays. These charges have been established as guidelines and their applicability to a specific
project should be confirmed with Alt & Witzig Engineering, Inc.
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 09/15/2025
Name: Lidya Abreha Department of Public Works – Engineering Division
BPW Date: 09/23/2025 Phone Extension: 5961
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Michael Schmidt
Dept. Attorney Attorney Name
Purchasing Mickey Lovy
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. 1 PCA
Chg. Order, No. 1 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Byrne & Jones Construction.
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name VPA Leeper Park Tennis Courts
Project Number 124-022 (PROJ00000529)
Funding Source Parks & Recreation
Account No. 287-443001
Amount
Terms of Contract
Special Contract Provisions
Purpose/Description Addition of third party testing on the PT pours.
For Change Orders Only
Amount of Increase
Decrease
$14,950.00
($ )
Previous Amount $ 1,756.171.07
Current Percent of Change:
Increase
Decrease
0.87%
( %)
New Amount $ 1,771,121.07
Total Percent of Change:
Increase
Decrease
0.87%
( %)
Time Extension Amount: N/A
New Completion Date: N/A