HomeMy WebLinkAboutAward Bid - Wall and Greenlawn Proj No 124-023B - Selge Construction
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BREANA N. MICOU
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
May 27, 2025
Mr. Robert P. Kuhns
Selge Construction Co., Inc.
2833 South 11th Street
Niles, MI 49120
bkuhns@selgeconstruction.com
RE: Award Bid – Wall St. Improvements – Project No. 124-023B
Dear Mr. Kuhns:
At its May 27, 2025 meeting, the Board of Public Works awarded the above referenced
bid to you in the amount of $2,592,256.25; Base Bid Plus Alternate. Enclosed please find a
signed Bid/Proposal form.
Please forward the following documents in one submittal by June 10, 2025 to my
attention for Board of Public Works approval at hhorvath@southbendin.gov:
1)One (1) signed original of the Public Works Contract (enclosed)
2)Labor & Material Payment Bond
3)Performance Bond (125% of Bid Amount)
4)Certificate of Insurance naming the City of South Bend as an additional insured
5)Item #4 for all subcontractors that you use
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/hh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BREANA N. MICOU
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
May 27, 2025
Mr. Dustin P. Hilary
Milestone Contractors, L.P.
24358 State Road 23
South Bend, IN 46614
epiliopow@milestonelp.com; akrueger@milestonelp.com
RE: Bid Award – Wall St. Improvements – Project No. 123-023B
Dear Mr. Hilary:
At its May 27, 2025, meeting, the Board of Public Works awarded the above referenced
bid to Selge Construction Co., Inc. in the amount of $2,592,256.25; Base Bid Plus Alternate.
Thank you for bidding, and we hope you bid with us in the future.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/hh
May 27, 2025
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BREANA N. MICOU
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
Mr. Ruben Alvarado
Rieth-Riley Construction Co., Inc.
25200 State Road 23
South Bend, IN 46614
gvanparys@rieth-riley.com
RE: Bid Award – Wall St. Improvements – Project No. 124-023B
Dear Mr. Alvarado:
At its May 27, 2025, meeting, the Board of Public Works awarded the above referenced
bid to Selge Construction Co., Inc. in the amount of $2,592,256.25; Base Bid Plus Alternate.
Thank you for bidding, and we hope you bid with us in the future.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/hh
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk
Board of Public Works
FROM: Leslie Biek, Assistant City Engineer
SUBJECT: Award Project No. 124-023B
Wall St and Greenlawn Ave Improvements
DATE: 5/19/2027
On May 13, 2025, the Board of Public Works opened and read three (3) bids for the above
referenced project, which consisted of a base bid and one alternate.
The bid results are as follows:
Bidder Base Bid Alternate A Base Bid +
Alternate
Engineer’s Estimate 2,773,170.00 33,640.00 2,806,810.00
Selge Construction 2,559,630.45 32,625.80* 2,592,256.25*
Rieth-Riley Construction 3,132,760.77 45,773.25 3,178,534.02
Milestone Contractors North, L.P. 2,993,000.00 51,000.00 2,984,000.00
*There was a calculation error that resulted in an increase of $0.55 to the Alternate A bid amount.
It is requested the Board of Public Works and Utilities award the base bid plus alternate to the
lowest responsive and responsible bidder, Selge Construction Co., Inc. in the amount of
$2,592,256.25.
Sufficient funds have been appropriated from River East TIF
Thank you for your consideration of this request.
Enc. Bid Tabulation
May 27, 2025
BOARD OF PUBLIC WORKS
CITY OF SOUTH BEND, INDIANA
PUBLIC WORKS CONTRACT
This Agreement is made and entered into this 27th Day of May, 2025, by and between Selge
Construction Co., Inc., (the “Contractor”), and the Board of Public Works (the "Board”).
The Contractor covenants and agrees to make the following improvement, as fully set out in the
Request for Quotations, Standard Specifications, Special Provisions, Plans, and Bid Proposals, all
of which are set forth as a part of this Contract, for:
PROJECT NO. PR-124-023B
DESCRIPTION: WALL ST. IMPROVEMENTS
COMPLETION DATE: SEE SPECIFICATIONS
AMOUNT: $2,592,256.25; BASE BID PLUS ALTERNATE
FUNDING: PR-00039963
The unit prices for this improvement were those prices as received and accepted by the Board on
the 27th Day of May, 2025.
The Contractor further agrees to notify the assigned Engineer when this improvement is
completed. This notification shall be in the form of a Project Completion Affidavit, signed by the
Contractor. Upon final acceptance of the improvement by the Engineer, the Contractor’s final
estimate will be presented to the Board for final Payment with one (1) copy of the Project
Completion Affidavit and one (1) copy of a Waiver of Lien.
Each of the Parties, by signing below, represents and warrants to the other Party that he/she/it has
the authority to bind the named person or entity to this Agreement.
BOARD OF PUBLIC WORKS SELGE CONSTRUCTION CO.,
INC.
President Member Printed Name
Member Member Signature
Member Attest: Clerk
May 27, 2025
Wall Street and Greenlawn Avenue ImprovementsCity Project No. 124-023BCity of South BendBid TabulationBase BidEngineer's Estimate Selge Construction Rieth-Riley Construction Milestone ContractorsItem Description Unit Quantity Unit Price Amount Unit Price Amount Unit Price Amount Unit Price AmountNo.1. Construction Engineering 1 LS $40,980.00 $40,980.00 $25,000.00 $25,000.00 $18,500.00 $18,500.00 $13,200.00 $13,200.00 2. Mobilization/Demobilization 1 LS $130,100.00 $130,100.00 $70,450.00 $70,450.00 $105,132.59 $105,132.59 $97,600.00 $97,600.00 3. CPM Schedule 1 LS $1,500.00 $1,500.00 $1,500.00 $1,500.00 $563.32 $563.32 $1,200.00 $1,200.00 4. CPM Monthly Update 5 MO $500.00 $2,500.00 $250.00 $1,250.00 $350.00 $1,750.00 $1.00 $5.00 5. Maintenance of Traffic 1 LS $35,000.00 $35,000.00 $39,500.00 $39,500.00 $32,275.16 $32,275.16 $47,277.05 $47,277.05 6. Erosion Control 1 LS $15,000.00 $15,000.00 $12,500.00 $12,500.00 $15,846.12 $15,846.12 $4,500.00 $4,500.00 7. Clearing Right of Way 1 LS $45,000.00 $45,000.00 $84,700.00 $84,700.00 $18,101.96 $18,101.96 $70,300.00 $70,300.00 8. Common Excavation 9,010 CYD $22.00 $198,220.00 $36.65 $330,216.50 $30.85 $277,958.50 $40.00 $360,400.00 9. Borrow 4,195 CYD $50.00 $209,750.00 $0.01 $41.95 $73.59 $308,710.05 $0.01 $41.95 10. Tree, 6", Remove 8 EA $600.00 $4,800.00 $200.00 $1,600.00 $200.00 $1,600.00 $200.00 $1,600.00 11. Tree, 10", Remove 8 EA $1,200.00 $9,600.00 $500.00 $4,000.00 $500.00 $4,000.00 $500.00 $4,000.00 12. Tree, 18", Remove 9 EA $2,500.00 $22,500.00 $1,400.00 $12,600.00 $1,400.00 $12,600.00 $1,400.00 $12,600.00 13. Tree, 30", Remove 2 EA $5,000.00 $10,000.00 $2,000.00 $4,000.00 $2,000.00 $4,000.00 $2,000.00 $4,000.00 14. Sign, Remove 32 EA $150.00 $4,800.00 $100.00 $3,200.00 $141.94 $4,542.08 $100.00 $3,200.00 15. Sign, Relocate 2 EA $200.00 $400.00 $325.00 $650.00 $614.38 $1,228.76 $150.00 $300.00 16. Pipe, Remove 50 LFT $25.00 $1,250.00 $52.00 $2,600.00 $62.26 $3,113.00 $44.00 $2,200.00 17. Structures, Remove 3 EA $1,000.00 $3,000.00 $750.00 $2,250.00 $778.30 $2,334.90 $960.00 $2,880.00 18. Fire Hydrant, Remove 1 EA $1,500.00 $1,500.00 $1,300.00 $1,300.00 $1,556.61 $1,556.61 $3,100.00 $3,100.00 19. Concrete Curb, Remove 3,145 LFT $15.00 $47,175.00 $5.50 $17,297.50 $17.49 $55,006.05 $9.00 $28,305.00 20. Concrete Approaches and Sidewalk, Remove 320 SYD $20.00 $6,400.00 $10.50 $3,360.00 $42.84 $13,708.80 $22.00 $7,040.00 21. Concrete Pavement, Remove 75 SYD $20.00 $1,500.00 $10.50 $787.50 $100.36 $7,527.00 $25.00 $1,875.00 22. Brick, Remove 25 SYD $20.00 $500.00 $10.00 $250.00 $124.53 $3,113.25 $25.00 $625.00 23. Milling, Varible Depth 460 SYD $6.00 $2,760.00 $9.00 $4,140.00 $24.09 $11,081.40 $23.00 $10,580.00 24. OMITTED25. Compacted Aggregate, No. 53 2,940 TON $45.00 $132,300.00 $46.75 $137,445.00 $41.89 $123,156.60 $29.00 $85,260.00 26. HMA Surface 650 TON $120.00 $78,000.00 $116.25 $75,562.50 $116.22 $75,543.00 $139.00 $90,350.00 27. HMA Intermediate 1,010 TON $110.00 $111,100.00 $103.25 $104,282.50 $103.22 $104,252.20 $109.00 $110,090.00 28. HMA Base 1,495 TON $95.00 $142,025.00 $88.00 $131,560.00 $87.93 $131,455.35 $89.00 $133,055.00 29. Joint Adhesive 3,220 LFT $2.00 $6,440.00 $2.70 $8,694.00 $2.66 $8,565.20 $0.10 $322.00 30. PCCP, 8" 350 SYD $100.00 $35,000.00 $95.00 $33,250.00 $119.44 $41,804.00 $160.00 $56,000.00 31. PCCP, Colored, 8" 110 SYD $200.00 $22,000.00 $145.00 $15,950.00 $172.78 $19,005.80 $169.00 $18,590.00 32. PCCP, Colored, 6" 25 SYD $150.00 $3,750.00 $140.00 $3,500.00 $346.57 $8,664.25 $375.00 $9,375.00 33. PCCP for Approaches, 6" 80 SYD $140.00 $11,200.00 $95.00 $7,600.00 $103.31 $8,264.80 $87.00 $6,960.00 34. PCCP for Approaches, 8" 155 SYD $150.00 $23,250.00 $103.00 $15,965.00 $112.75 $17,476.25 $100.00 $15,500.00 35. D-1 Contraction Joint 105 LFT $25.00 $2,625.00 $28.00 $2,940.00 $32.56 $3,418.80 $42.00 $4,410.00 36. Concrete Curb 1,265 LFT $40.00 $50,600.00 $54.50 $68,942.50 $39.34 $49,765.10 $45.00 $56,925.00 37. OMITTED38. Concrete Curb and Gutter, Type B 2,325 LFT $40.00 $93,000.00 $39.50 $91,837.50 $30.86 $71,749.50 $45.00 $104,625.00 39. Concrete Curb and Gutter, Depressed 300 LFT $35.00 $10,500.00 $28.00 $8,400.00 $52.58 $15,774.00 $51.00 $15,300.00 40. Concrete Sidewalk, 4" 1,700 SYD $70.00 $119,000.00 $54.25 $92,225.00 $57.81 $98,277.00 $77.00 $130,900.00 41. Concrete Curb Ramp 250 SYD $225.00 $56,250.00 $170.00 $42,500.00 $179.54 $44,885.00 $150.00 $37,500.00 42. Concrete Curb Ramp, Colored 140 SYD $250.00 $35,000.00 $140.00 $19,600.00 $250.71 $35,099.40 $150.00 $21,000.00 43. Detectable Warning Surface 50 SYD $150.00 $7,500.00 $280.00 $14,000.00 $59.49 $2,974.50 $259.00 $12,950.00 44. Mulched Seeding, Type "U" 8,400 SYD $3.00 $25,200.00 $1.30 $10,920.00 $1.30 $10,920.00 $6.00 $50,400.00 45. Sodding 3,000 SYD $5.00 $15,000.00 $8.00 $24,000.00 $9.86 $29,580.00 $26.00 $78,000.00 46. Street Tree 27 EA $600.00 $16,200.00 $695.00 $18,765.00 $695.00 $18,765.00 $695.00 $18,765.00 47. Storm Sewer Manhole, 48" 16 EA $5,000.00 $80,000.00 $5,200.00 $83,200.00 $6,072.25 $97,156.00 $5,500.00 $88,000.00 48. Storm Sewer Catch Basin 7 EA $3,000.00 $21,000.00 $4,100.00 $28,700.00 $3,370.60 $23,594.20 $5,140.00 $35,980.00 49. OMITTED50. OMITTED51. Storm Sewer Pipe, 12" 1,193 LFT $60.00 $71,580.00 $109.25 $130,335.25 $60.35 $71,997.55 $49.00 $58,457.00 52. Storm Sewer Pipe, Water Main Grade, 12" 44 LFT $90.00 $3,960.00 $136.00 $5,984.00 $84.59 $3,721.96 $90.00 $3,960.00 53. Storm Sewer Pipe, 18" 583 LFT $70.00 $40,810.00 $109.00 $63,547.00 $83.17 $48,488.11 $60.00 $34,980.00 54. Storm Sewer Pipe, Water Main Grade, 18" 75 LFT $100.00 $7,500.00 $141.00 $10,575.00 $107.26 $8,044.50 $108.00 $8,100.00 55. OMITTED56. OMITTED57. Underground Storm Sewer System 1 LS $675,000.00 $675,000.00 $540,000.00 $540,000.00 $907,558.19 $907,558.19 $817,700.00 $817,700.00 58. Fire Hydrant, Assembly 1 EA $6,000.00 $6,000.00 $19,250.00 $19,250.00 $9,548.46 $9,548.46 $16,100.00 $16,100.00 59. Water Main, 4" 30 LFT $60.00 $1,800.00 $205.00 $6,150.00 $182.77 $5,483.10 $190.00 $5,700.00 60. Bend, 45 Degree, 4" 4 EA $600.00 $2,400.00 $565.00 $2,260.00 $1,121.98 $4,487.92 $850.00 $3,400.00 61. OMITTED62. Adjust Casting to Grade 8 EA $500.00 $4,000.00 $700.00 $5,600.00 $616.49 $4,931.92 $1,330.00 $10,640.00 1 of 2
63. Sheet Sign, 0.080 in. 128 SFT $25.00 $3,200.00 $24.00 $3,072.00 $24.00 $3,072.00 $24.00 $3,072.00 64. Sheet Sign, 0.125 in. 15 SFT $25.00 $375.00 $29.00 $435.00 $29.00 $435.00 $29.00 $435.00 65. Sign Post, Square, Type 2, Reinforced Anchor Base 325 LFT $25.00 $8,125.00 $20.00 $6,500.00 $20.00 $6,500.00 $20.00 $6,500.00 66. Solar Powered Flashing Pedestrian Crossing Signage Assembly 2 EA $10,000.00 $20,000.00 $12,000.00 $24,000.00 $12,000.00 $24,000.00 $12,000.00 $24,000.00 67. Lighted Bollard 8 EA $900.00 $7,200.00 $5,000.00 $40,000.00 $5,000.00 $40,000.00 $5,000.00 $40,000.00 68. Line, Thermoplastic, Solid, White, 4" 1,875 LFT $2.00 $3,750.00 $1.10 $2,062.50 $5.00 $9,375.00 $5.00 $9,375.00 69. Line, Thermoplastic, Solid, White, 4", Grooved 880 LFT $2.00 $1,760.00 $2.10 $1,848.00 $6.00 $5,280.00 $6.00 $5,280.00 70. Line, Thermoplastic, Solid, Yellow, 4", Grooved 205 LFt $2.00 $410.00 $2.10 $430.50 $6.00 $1,230.00 $6.00 $1,230.00 71. Line, Thermoplastic, Solid, Blue, 4" 160 LFT $2.00 $320.00 $10.20 $1,632.00 $7.00 $1,120.00 $7.00 $1,120.00 72. Line, Thermoplastic, Solid, White, 6" 440 LFT $2.00 $880.00 $1.95 $858.00 $8.00 $3,520.00 $8.00 $3,520.00 73. Transverse Line, Thermoplastic, White, 24", Stop Bar 75 LFT $15.00 $1,125.00 $9.25 $693.75 $17.00 $1,275.00 $17.00 $1,275.00 74. Transverse Line, Thermoplastic, White, 24", Crosswalk 380 LFT $15.00 $5,700.00 $9.25 $3,515.00 $17.00 $6,460.00 $17.00 $6,460.00 75. Pavement Message Marking, Multicomponent, Tabled Intersection 6 EA $850.00 $5,100.00 $425.00 $2,550.00 $1,000.00 $6,000.00 $1,000.00 $6,000.00 76. Pavement Message Marking, Multicomponent, Handicap Space 2 EA $500.00 $1,000.00 $150.00 $300.00 $750.00 $1,500.00 $750.00 $1,500.00 77. Temporary Fence 1 LS $10,000.00 $10,000.00 $25,000.00 $25,000.00 $14,336.56 $14,336.56 $7,110.00 $7,110.00 Total$2,773,170.00 $2,559,630.45 $3,132,760.77 $2,933,000.00 Add Alternate A - Raised IntersectionEngineer's Estimate Selge Construction Rieth-Riley Construction Milestone ContractorsItem Description Unit Quantity Unit Price Amount Unit Price Amount Unit Price Amount Unit Price AmountNo.A1. Construction Engineering 1 LS $1,200.00 $1,200.00 $2,500.00 $2,500.00 $2,500.00 $2,500.00 $2,336.00 $2,336.00A2. OMITTEDA3. HMA Surface (Deduct) (35) TON $120.00 ($4,200.00) $116.25 ($4,068.75) $116.22 ($4,067.70) $139.00 ($4,865.00)A4. HMA Intermediate (Deduct) (55) TON $110.00 ($6,050.00) $103.24 ($5,678.20)* $103.22 ($5,677.10) $109.00 ($5,995.00)A5. HMA Base (Deduct) (130) TON $95.00 ($12,350.00) $88.00 ($11,440.00) $87.93 ($11,430.90) $89.00 ($11,570.00)A6. Joint Adhesive (Deduct) (310) LFT $2.00 ($620.00) $2.70 ($837.00) $2.66 ($824.60) $0.10 ($31.00)A7. PCCP, 8" 295 SYD $100.00 $29,500.00 $100.50 $29,647.50$137.19 $40,471.05 $160.00 $47,200.00A8. PCCP, Colored, 8" 95 SYD $200.00 $19,000.00 $145.00 $13,775.00 $192.24 $18,262.80 $169.00 $16,055.00A9. D-1 Contraction Joint 230 LFT $25.00 $5,750.00 $28.00$6,440.00 $13.81 $3,176.30 $42.00 $9,660.00A10. Concrete Curb 210 LFT $45.00 $9,450.00 $54.50 $11,445.00 $55.40 $11,634.00 $45.00 $9,450.00A11. Concrete Curb and Gutter, Type B (Deduct) (210) LFT $35.00 ($7,350.00) $39.50 ($8,295.00) $30.86 ($6,480.60) $45.00 ($9,450.00)A12. Line, Thermoplastic, Solid, White, 6" (Deduct) (195) LFT $2.00 ($390.00) $1.95 ($380.25) $8.00 ($1,560.00)$8.00 ($1,560.00)A13. Transverse Line, Thermoplastic, White, 24", Crosswalk (Deduct) (190) LFT $15.00 ($2,850.00) $9.25 ($1,757.50) $17.00 ($3,230.00) $17.00 ($3,230.00)A14. Pavement Message Marking, Multicomponent, Tabled Intersection 3 EA $850.00 $2,550.00 $425.00 $1,275.00 $1,000.00 $3,000.00 $1,000.00 $3,000.00Total$33,640.00 $32,625.80* $45,773.25 $51,000.00Acknowledge Addendum No. 1Yes Yes YesAcknowledge Addendum No. 2Yes Yes YesBid Tab SummaryEngineer's Estimate Selge Construction Rieth-Riley Construction Milestone Contractors$2,773,170.00 $2,559,630.45 $3,132,760.77 $2,933,000.00$2,806,810.00 S2,592,256.25* $3,178,534.02 $2,984,000.00*Corrected by EngineerI hereby certify that the above truly and accurately represents bids received for this project on May 13, 2025May 15, 2025Chad Knip, P.E.Abonmarche Consultants, Inc.Base Bid + Add Alt A (Base + Raised Intersection)Base Bid2 of 2
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 5/19/2025
Name Leslie Biek Department DPW
BPW Date 5/27/2025 Phone Extension 9323
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer Officer Name
BPW Attorney Attorney Name Michael Schmidt
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Selge Construction
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Wall St and Greenlawn Ave Improvements
Project Number 124-023B
Funding Source River East TIF
Account No. PR-39963
Amount $2,592,256.25
Terms of Contract
Purpose/Description Award Bid + Alternate for work on Wall St from Greenlawn to Ironwood.
For Change Orders Only
Amount of Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: