HomeMy WebLinkAboutOpening of Proposals - SRTS Kennedy School Proj No 123-017 - SJCA Inc.RESPONSIBLE OFFICE
SJCA, Inc.
105 E Jefferson Blvd, Suite 216
South Bend, Indiana 46601
317-566-0629
Authorized Negotiator
Sherly George, PE
Executive Vice President and COO
sgeorge@sjcainc.com
Point of Contact
Robin Warner, Director of Construction
Inspection and Project Manager
rwarner@sjcainc.com
PROFESSIONAL SERVICESMay 27, 2025
LETTER OF INTEREST
CITY OF SOUTH BEND
CONSTRUCTION INSPECTION SERVICES FOR SAFE ROUTES
TO SCHOOL AT KENNEDY ACADEMY (DES. 2201237)
Gemma Stanton, ERC/Project Engineer
227 W Jefferson Boulevard
South Bend, IN 46601
EXPERIENCED TEAM & PROJECT MANAGER
Robin Warner will serve as your Project Manager and primary point of contact. Robin has all the credentials and
certifications required by INDOT for Construction Inspection. With extensive experience in federally and locally
funded projects, he is well-equipped to ensure the successful delivery of this Safe Routes To School project for the
City of South Bend.
PRACTICAL & COST-EFFECTIVE APPROACH
SJCA Inc. is known for our quick response time and dedication to a project. Our construction inspection approach
has been highly rated through evaluations and comments. SJCA has visited the project site and formed a strategic
project understanding and approach based on our in-person observations to manage construction services and
keep this project on schedule. Our ability to be proactive before a project begins demonstrates that we are eager
to work with the City of South Bend.
CAPACITY TO DELIVER
Over the past few years, SJCA has increased capacity by growing to approximately 100 employees, with the
commitment of serving our clients with additional resources and capabilities to handle any project challenges. We
have added McCormick Engineering, who we have teamed with on previous construction inspection projects, as
a partner. With well-qualified team members and sufficient capacity, the SJCA team can provide added value to the
project if the contractor desires to accelerate the schedule.
We appreciate the City of South Bend considering SJCA for this project and look forward to a partnership that successfully
delivers it!
Sincerely,
TEAM PREQUALIFICATIONS %
SJCA, Inc.
13.1 Construction Inspection 95%
McCormick Engineering 13.1 Construction Inspection
5% (DBE)
SJCA 95%
McCormick 5%
2SJCA INC | CITY OF SOUTH BEND RFP | CONSTRUCTION INSPECTION | KENNEDY ACADEMY
EXPERIENCED PROJECT MANAGER
ROBIN WARNER
Robin has over 39 years of experience constructing
roads, bridges, drainage systems, airports, and other
civil engineering projects. Beginning his career with
INDOT, Robin has an in-depth understanding of
successfully working with State DOTs and Public Works
Departments. With this experience, Robin believes that
a consulting inspection firm is a steward of the clients’
money and insists that he and his teammates take the
project’s appropriate ownership to get the best value
for the customer’s dollar.
PROJECT MANAGER PROJECT TEAM PROJECT APPROACH PROJECT EXPERIENCE 2
RESIDENT PROJECT REPRESENTATIVE
CAMERON RIEWE
REGISTRATION & TRAINING• Project Supervisor Site Manager Credentials• INDOT Qualified Testing Technician• INDOT Certified Technician• Bridge Construction and Deck Repair• Construction Earthworks• Construction Procedures 1• Construction Procedures 2• Concrete Paving• Hot Mix Asphalt Paving• OSHA 30-hour safety training
INSPECTION PROJECT EXPERIENCE• Marquette Trail, LaPorte County• I-94E over NICTD RR Thin Deck Overlay, LaPorte County• I-94W over NICTD RR Thin Deck Overlay, LaPorte County• Warnke Road over I-94 Deck Overlay, LaPorte County
REGISTRATION & TRAINING• Site Manager Training• Site Manager Certified• INDOT Certified Technician• INDOT Certified Technician Instructor• Indianapolis DPW RPR Training• CPR and First Aid • OSHA 40-hour Certification• Indianapolis Department of Public Works Inspection Client Training
INSPECTION PROJECT EXPERIENCE• Whitewater Basin Trail, Richmond, IN• Lower Fall Creek Trail Phase II, Indianapolis• Multiple Bridge rehabilitation project, I-70 and I-65 inner loop, Indianapolis• Bridge deck overlay, Mann Road over Peyton Lake, Indianapolis• Bridge deck overlay, Mann Road over No Name Creek, Indianapolis• ADA ramp improvements, 53 intersections from 21st Street to
30th street between Kenwood Avenue and North College
Avenue, Indianapolis
Cam is a dedicated professional with a strong
willingness to learn and adapt. He holds a Bachelor
of Science degree in Manufacturing Engineering &
Technology, which has equipped him with a solid
foundation in manufacturing logistics. This background
has fostered a keen sense of organization and an
acute attention to detail, essential qualities for a
construction inspector. Cam excels in calculating pay
quantities swiftly and accurately and has a proactive
approach to notetaking and report generation.
Patrick Booth (SJCA)Sandeep Thapa (SJCA)Becky Booth (SJCA)John Beer (McCormick)
COMMUNICATIONScott Lee PROJECT MANAGERRobin Warner
RESIDENT PROJECT REPRESENTATIVECameron Riewe
CONSTRUCTION INSPECTORS
QA/QC AND TECHNICAL ADVISORGreg Quebe, PS, PE
THE SJCA TEAM HAS AMPLE CAPACITY
SJCA, Inc. was founded in 1998 and
has grown from a single owner firm
specializing in bridge design to a
multi-disciplined firm with four
owners, six office locations, and
approximately 100 employees. Significant
capacity and built-in redundancy
allow us to adjust assignments to
address unforeseen challenges or
accelerated schedules.
McCormick Engineering, LLC is a
South Bend-based certified Indiana
WBE and DBE, and was founded to serve
the public through civil engineering
planning and design. By committing to
understanding the needs of each
project, we are able to define project
success by our ability to meet the
goals and objectives of the client.
PROFESSIONAL
ENGINEERS
FOR THIS PROJECT THE SJCA
TEAM WILL HAVE THESE
RESOURCES AVAILABLE:
RESIDENT PROJECT
REPRESENTATIVES
CONSTRUCTION
INSPECTORS237
PROJECT TEAM
3PROJECT MANAGER PROJECT TEAM PROJECT APPROACH PROJECT EXPERIENCESJCA INC | CITY OF SOUTH BEND RFP | CONSTRUCTION INSPECTION | KENNEDY ACADEMY
PROJECT TEAM
4PROJECT MANAGER PROJECT TEAM PROJECT APPROACH PROJECT EXPERIENCESJCA INC | CITY OF SOUTH BEND RFP | CONSTRUCTION INSPECTION | KENNEDY ACADEMY
PATRICK BOOTH (SJCA)
INDOT Certified Technician
Project Supervisor Site Manager Credentials
INDOT Qualified Testing Technician
SANDEEP THAPA (SJCA)
MS, Civil Engineering, University of Texas at Arlington, Texas
BS, Civil Engineering, Punjab Technical University, India
Construction Manager in Training (CMIT), Texas
JOHN BEER (McCormick)
Indiana Department of Transportation Certified Technician
Indiana Department of Transportation SiteManager User
OSHA 10-Hour Training for Construction Industry
Indiana Certified Residential Appraisers License
Indiana Level II Assessor Certificate
Patrick has four years of experience completing Construction Inspection, RPR,
and Bridge Inspection projects with SJCA. His promotion to Resident Project
Representative in June 2024 reflects his adaptability and readiness to fill any role
necessary to ensure high-quality project outcomes. Patrick is a Navy veteran and
brings precision, attention to detail, and a commitment to excellence to this role.
Sandeep is an engineer with over three years of construction engineering
experience. He has participated in the construction, renovation, and rehabilitation
of buildings, and the construction bridges, sidewalks, and curb ramps. In addition
to his technical skills, Sandeep is known for his collaborative approach, working
closely with contractors and municipal agencies to resolve field issues and
maintain project deadlines.
John is an experienced technician with over 30 years in the construction
industry. His observation experience includes performance of material testing,
monitoring daily construction activities, and preparing Daily Work Reports for
roadway reconstruction, new bridge construction, bridge deck replacement, and
telecommunication fiber installation projects.
PROJECT EXPERIENCE• Resident Project Representative, Bridge 36, Hancock Co.• Inspector, I-65 North Split Reconstruction, Indianapolis,• Assistant RPR, Lower Fall Creek Trail and Pedestrian Bridge, Indianapolis • Inspector, Eagle Creek Airpark, parking, and taxiway rehabilitation, Indianapolis• Inspector, Indianapolis Cultural Trail 2.0
PROJECT EXPERIENCE• Inspector, Lower Fall Creek Trail Phase 2, Indianapolis• Resident Project Representative, City of Warsaw Curb Ramp Improvements
PROJECT EXPERIENCE• Olive Street Reconstruction (2 phases), South Bend• Bendix Drive Reconstruction, South Bend• INDOT On-Call, SR 331 over US 30 Bridge Deck Overlay, Marshall Co.• INDOT On-Call, US 31 Reconstruction, St. Joseph Co.• Coal Line Trail, St. Joseph Co.
BECKY BOOTH (SJCA)
INDOT Certified Technician
Project Supervisor Site Manager Credentials
INDOT Qualified Testing Technician
Becky joined SJCA as a CAD technician and consistently demonstrated
outstanding skills and a genuine enthusiasm for learning new capabilities. With
a move to construction inspection while still occasionally assisting in our CAD
department, she has shown readiness to take on any role and to ensure high-
quality project outcomes.
PROJECT EXPERIENCE• Inspector, Amstutz Road Leo Cedarville, IN, • Inspector, Bridge 250, Randolph Co.• Inspector, INDOT On-Call, I-69 & I-469 bridge deck overlay• Inspector, Bridge 18 Rehabilitation, Blackford Co.• Inspector, Bridge 126 Superstructure Replacement, Henry Co.
5PROJECT MANAGER PROJECT TEAM PROJECT APPROACH PROJECT EXPERIENCE
PROJECT APPROACH
SJCA INC | CITY OF SOUTH BEND RFP | CONSTRUCTION INSPECTION | KENNEDY ACADEMY
SJCA has created a three-pronged approach to achieving a successful Construction Inspection project:
SUCCESSFUL
PROJECT
COORDINATION
SAFETY
QUALITY &
COMPLIANCE
• Contractor
• INDOT
• Utilities
• Public
• Contractor
• Public
• ADA Compliance
• Timely
records
• Standards
• Cost
Control
1
2
3
6PROJECT MANAGER PROJECT TEAM PROJECT APPROACH PROJECT EXPERIENCE
PROJECT APPROACH
SJCA INC | CITY OF SOUTH BEND RFP | CONSTRUCTION INSPECTION | KENNEDY ACADEMY
PROJECT UNDERSTANDING
The value of employing construction inspection is to ensure that the project is
constructed safely according to design, remains compliant with INDOT standards,
encounters minimal public resistance, and requires little involvement from the City
Engineer. A thorough understanding of construction plans and specifications before
and during the project is essential to execute the design properly. If design questions
arise, we can directly consult the designer if preferred. Should any errors be identified
during the project, the City Engineer and Area Engineer will be immediately notified
for prompt resolution. Any changes to the design will require approval from both the
City and Area Engineers.
CHALLENGES
Each project presents unique challenges. This project impacts some neighborhoods
where children will be present. Mail and package delivery, as well as trash collection
and other city services, will be impacted. The
construction inspection team will need to
ensure that unnecessary impacts are not made
to vital services. As the neighborhoods will be
experiencing inconvenience for area residents,
maintenance of traffic will be very important and
could likely change very often. On this type of
project, it should be closely monitored to ensure
safety for the entire period. Additionally, the
project may require clearing the right-of-way
near homes and busy streets. SJCA will ensure
all tree removal is completed in a safe manner,
during the inactive season for the Indiana Bat. We will also ensure that the contractor
remains respectful to adjacent property owners by staying within right-of-way limits.
The items mentioned in this section should be addressed during the preconstruction
conference as well as the biweekly progress meetings. However, the construction
inspection team should work with the contractor daily to ensure that these items
remain at a minimum tolerable level for all involved.
Crosswalks to be restriped.
Obstructions in sidewalk checked
for ADA compliance.
Ramps to be replaced to ADA standards.
Sidewalks to be checked for ADA cross-slope.
Crosswalks to be placed where none exist.
7PROJECT MANAGER PROJECT TEAM PROJECT APPROACH PROJECT EXPERIENCE
PROJECT APPROACH
SJCA INC | CITY OF SOUTH BEND RFP | CONSTRUCTION INSPECTION | KENNEDY ACADEMY
UTILITIES
This project has several utilities that are likely to present issues. Even with pre-project
utility movement, there will likely be utilities that were not moved promptly or are
completely unexpected. Therefore, the inspection team will need to maintain close
contact with the LPA, INDOT, and utility companies to ensure that utility issues are
dealt with in a prompt and safe fashion. Also, it will be necessary to confirm that the
contractor is up to date with having utilities marked at work locations with the proper
frequency. This will help avoid project delays and the disruption of vital utility services.
SAFETY
On-site safety is SJCA’s highest priority. Any unsafe practices observed will be
documented and stopped immediately. If necessary, the City and/or Area Engineer
will be notified. Environmental concerns, such as dust and stormwater leaving the
job site, will also be monitored. At the end of each workday, the site will be checked
for cleanliness and hazards to ensure public safety during off-hours. All personnel to
be assigned to this project are familiar with INDOT’s latest record-keeping program,
current standard specifications, testing frequency requirements, and stormwater
control measures.
Heavy foot traffic can be anticipated and
utility adjustment may be needed near this
recreational water park in the neighborhood.
Removal of tripping hazards.
Replacement of sidewalk and ramps.
Replacement of damaged sidewalk.
Coordination with utilities for new sidewalk.
Ramps and crosswalks to be updated.
8PROJECT MANAGER PROJECT TEAM PROJECT APPROACH PROJECT EXPERIENCE
PROJECT APPROACH
SJCA INC | CITY OF SOUTH BEND RFP | CONSTRUCTION INSPECTION | KENNEDY ACADEMY
COMMUNICATION
Communication protocols will be established in the
preconstruction conference, per INDOT standard specifications.
Daily reports and pay items will be submitted through INDOT-
provided record-keeping software. Bi-weekly progress
meetings will be held with the LPA, INDOT, and the prime contractor to keep
all parties informed and allow for discussion of any concerns. If an issue
arises that requires communication with the Area Engineer, an email will be
sent (copying the City Engineer). Written and photographic records will be
maintained throughout the project and made available as needed, including
at project closeout.
Pre-Construction Review
We will conduct a thorough review of project plans and specifications, ensuring
all necessary permits and traffic control plans are in place and coordinated
with local authorities (e.g., law enforcement, fire protection, EMS, and
school transportation). Coordination with affected utility companies will also
be confirmed.
Site Preparation Inspection
Traffic control installations will be verified, including signage indicating the
approximate date work will begin. All traffic control signs and barricades will be
installed per specifications.
MAINTENANCE OF TRAFFIC & PUBLIC INVOLVEMENT
Maintaining access to local traffic is a priority, and accessibility to properties is
critical for surrounding owners. SJCA personnel are experienced with this type
of issue and will ensure all parties are heard
and their concerns are balanced. Key SJCA
personnel will attend public meetings as
requested. We welcome the City Engineer’s
involvement at every stage of this project,
though we recognize that this will be one of
many projects on the engineer's agenda. We will
provide regular progress reports and be readily
available to address any questions. When
necessary, we will notify the City Engineer of
issues requiring input via phone or email, based
on the engineer's preference.
Quality Assurance and Material Verification
All materials will be monitored, tested, and certified (or otherwise ensured to meet)
the appropriate INDOT and local standards at required frequencies as specified in
contract documents. Testing will be performed at a frequency equal to or greater
than that required by FHWA, INDOT, and local standards. Any deviations or rework
will be documented. We will observe and document each project component using
INDOT’s most recent software, along with any additional documentation required by
the City of South Bend. Only qualified personnel will oversee each project phase.
Any SJCA or subconsultant personnel who are not fully qualified for a particular task
will work under the supervision of fully qualified staff at no additional expense to
the city.
CLOSEOUT
To facilitate a seamless closeout process, the
contractor and inspection team will agree
on production and material quantities daily
throughout construction. Once the contract is
physically complete, the SJCA Project Engineer,
Manager, and Supervisor (PEMS) will provide
the prime contractor with a detailed punch list
of any corrective actions required, if necessary,
and verify completion to the PEMS’s satisfaction
before requesting a pre-final inspection by
INDOT and local authorities. After the pre-final
inspection, the PEMS will conduct a final inspection, ensuring that all punch list
items noted by FHWA, INDOT, and the City Engineer have been resolved. Our team
will work closely with INDOT on final records and material certification to bring the
project to full closure.Placement of stop bars and crosswalks required.
New sidewalks to be placed
where needed
Continuation of sidewalks
where needed
9PROJECT MANAGER PROJECT TEAM PROJECT APPROACH PROJECT EXPERIENCE
PROJECT EXPERIENCE
SJCA INC | CITY OF SOUTH BEND RFP | CONSTRUCTION INSPECTION | KENNEDY ACADEMY
RANDOLPH COUNTY BRIDGE 110
SJCA served as the prime consultant for the
construction inspection of Randolph County Bridge
110. This bridge was unique in that the county desired
to retain the existing substructure. However, due to
the substructure’s age, weight restrictions became
a key concern. To address this, it was necessary to
use lightweight concrete suitable for a bridge deck
application. This challenge required our construction
department to work closely with the design team
to ensure a thorough understanding of lightweight
concrete’s unique characteristics and the special
testing requirements involved. This collaboration was
critical to the project’s success, ensuring the bridge
met both structural integrity and safety standards.
LOWER FALL CREEK TRAIL PHASE II
SJCA served as the prime consultant for the
Construction Inspection of the Lower Fall Creek Trail
Phase II project in Indianapolis. As is often the case with
trail projects, this one presented a number of unique
challenges, particularly with utility coordination and
unforeseen issues that arose during construction. Our
team had to navigate various complexities, including
working closely with utilities and resolving coordination
challenges. Additionally, the project required effective
communication with a diverse set of residents and
property owners adjacent to the trail, each with their
own concerns and personalities.
HANCOCK COUNTY BRIDGE 36
SJCA served as the prime consultant for the
construction inspection of Hancock County Bridge
36, located in eastern Hancock County. This project
involved the demolition of the existing bridge, while
carefully maintaining environmental sensitivity
throughout the process, followed by the construction of
a new three-span slab-top structure. One of the critical
challenges was minimizing the bridge’s closure time, as
the project needed to be completed between the local
agricultural community’s planting and harvest seasons.
Our team successfully managed this timeline, ensuring
minimal disruption to the community while delivering a
quality infrastructure solution.
10PROJECT MANAGER PROJECT TEAM PROJECT APPROACH PROJECT EXPERIENCE
PROJECT EXPERIENCE
SJCA INC | CITY OF SOUTH BEND RFP | CONSTRUCTION INSPECTION | KENNEDY ACADEMY
I-65/I-70 NORTH SPLIT RECONSTRUCTION
SJCA had inspectors on the I-65/I-70 North Split
project in Indianapolis beginning in December 2020.
Our inspectors and engineers were able to add to their
skills and knowledge base on this large-scale project.
They performed inspections for many different types of
construction disciplines. Long hours and the necessity
to move quickly from one construction discipline to
another were challenges that the inspection team met
with confidence.
MARQUETTE MULTI-USE TRAIL
SJCA was the prime consultant for the construction
inspection for the Marquette Multi-Use Trail located
in LaPorte County, Indiana in the town of Michiana
Shores. This project posed significant challenges due
to the extensive tree removal required, all of which had
to be completed within a highly compressed timeline,
requiring our inspection staff to be able to disseminate
between multiple removal items. There were four trees
that the contractor did not necessarily agree with.
However, due to a strong desire to protect our client's
best interest, we were able to work with the design team
and determine that these items were indeed correct in
the contract documents. Therefore, our client was not
required to stand for an extremely large change order.
I-69 FINISH LINE
SJCA provided construction inspection personnel
for the I-69 Finish Line project, which completed the
final connection between Indianapolis and Evansville,
Indiana via Interstate. This significant infrastructure
project allowed our construction staff to enhance their
skills across multiple aspects of construction inspection.
The fast-paced nature of the project required our
team to perform a wide variety of inspection tasks
daily, while simultaneously maintaining meticulous
records and upholding strong public relations. This
experience further strengthened our team’s capability
to deliver high-quality inspection services under
challenging conditions.
Standard RFP Form Ver. 1/2023
6
(Rev. 06/27/18)
Des. #: 2201237
Affirmative Action Certification (AAC) for Disadvantaged Business Enterprises (DBE)
I hereby certify that my company intends to affirmatively seek out and consider Disadvantaged Business Enterprises (DBEs) certified
by the State of Indiana’s DBE Program and the Kentucky Transportation Cabinet (KYTC) DBE Program to participate as part of this
proposal. An Agreement between INDOT and KYTC established reciprocal acceptance of certification of DBE firms in their
respective states under the Unified Certification Program (UCP) pursuant to 49 CFR §26.81(e) and (f).
I acknowledge that this certification is to be made an integral part of this proposal. I understand and agree that the submission of a
blank certification may cause the proposal to be rejected. I certify that I have consulted the following DBE websites to confirm that
the firms listed below are currently certified DBEs:
INDOT: https://entapps.indot.in.gov/DBELocator/
KYTC: https://transportation.ky.gov/Civil-Rights-and-Small-Business-Development/Pages/Certified-DBE-Directory.aspx
I certify that I have contacted the certified DBE’s listed below, and if my company becomes the CONSULTANT, these DBEs have
tentatively agreed to perform the services as indicated. I understand that neither my company nor I will be penalized for DBE
utilization that exceeds the goal. After contract award, any change to the firms listed in this Affirmative Action Certification to be
applied toward the DBE goal must have prior approval by INDOT’s Economic Opportunity Division.
I.DBE Subconsultants to be applied toward DBE goal for the RFP item:
Certified DBE Name Service Planned Estimated Percentage to
be Paid*
%
%
%
%
II.DBE Subconsultants to be utilized beyond the advertised DBE goal for the RFP item:
Certified DBE Name Service Planned Estimated Percentage to
be Paid*
%
%
%
%
Estimated Total Percentage Credited toward DBE Goal:___________
Estimated Percentage of Voluntary DBE Work Anticipated over DBE Goal:__________
Company Name: ____________________________________________________________________
Signature: ___________________________________________ Date: ________________________
∗ It is understood that these individual firm percentages are estimates only and that percentages paid may be greater or less as a result
of negotiation of contract scope of work. My firm will use good faith efforts to meet the overall DBE goal through the use of these
or other certified and approved DBE firms.
McCormick Engineering 13.1 Construction Inspection 5
5%
SJCA Inc.
05/15/2025
100 North Senate Avenue
Room N750
Indianapolis, Indiana 46204
PHONE: (317) 233-4664
FAX: (317) 233-0891
Eric Holcomb, Governor
Michael Smith, Commissioner
McCormick Engineering, LLC
234 North Ironwood Drive
South Bend IN 46615
11/15/2024
Dear Tracy McCormick,
Subject:Declaration of Eligibility
This letter confirms receipt of your annual Declaration of Eligibility (DOE) Affidavit and supporting documentation .The Indiana
Department of Transportation 's Equity Initiative Services (EIS),in compliance with 49 CFR Parts 23 and 26, is pleased to inform
you that your firm's information has been reviewed and approved.
Your firm's DBE/ACDBE Certification will remain valid for another year.
The DBE Directory, located atINDOT: Doing Business with INDOT: DBE Directory , will continue to list your contact information
and will include the NAICS codes, Jurisdiction of Eligibility (JOC) date and description of services performed.
As a DBE/ACDBE, you have the responsibility to comply with all aspects of 49 CFR Parts 23 and 26, which include maintaining
an accurate mailing address, phone number and email addresswith INDOT EIS and promptly following up on all inquiries .
If you have any questions, please feel free to contact us at EISinquiry@indot.in.govatany time.
Derrick Casson
DBE Program Administrator, Equity Initiative Services
Indiana Department of Transportation
cc: file
Sincerely,
NAICS/DBE Codes Assigned:
DBE Code DBE Description NAICS Code DBE Speciality Code
DescriptionNAICS Description
0052.30E Engineering Services 541330 Non- Complex Roadway Design;
Storm & Sanitary Sewer;
Hydrology, Hydraulics adna
Drainage Design
Civil Engineering
Services