HomeMy WebLinkAboutOpening of Proposals - SRTS Kennedy School Proj No 123-017 - DLZ IndianaMay 27, 2025
KENNEDY ACADEMY CONSTRUCTION INSPECTION
SAFE ROUTES TO SCHOOL»
CITY OF SOUTH BEND
Project Manager
Brad Dailey, PE » Division Manager
574.532.7017 » bdailey@dlz.com
Authorized Negotiator
Andrew C. Lemberis, PE » Vice President
574.514.3713 » alemberis@dlz.com
Responsible Office
DLZ Indiana, LLC
2211 East Jefferson Boulevard » South Bend, IN 46615
574.236.4400 » www.dlz.com
1City of South Bend » Safe Routes to School » Construction Inspection
There is no greater importance than protecting the safety of our children. All too often the news reports of tragedy caused
by distracted driving or other careless acts. We value the importance of the Safe Routes to School (SRTS) program and
appreciate the opportunity to submit our Letter of Interest. Our dedication to working with the City of South Bend, combined
with our knowledge of the INDOT-LPA process, make DLZ the ideal partner to assist you in delivering this project. Let us take
this opportunity to share with you our qualifications and experience, and most importantly how we can help you!
A Highly Qualified Team You Know and Trust » We have assembled a local team with experience and dedication
perfectly suited to helping you deliver this project. Our proposed Project Engineer (Steve Menis) and Project Manager
(Brad Dailey, PE) have over 50 combined years of experience in the construction industry, and together have delivered over
15 SRTS, sidewalk, and trail projects across Northern Indiana. Our team has the knowledge and experience to not only
deliver this type of project, but also to efficiently handle issues in the field and thereby minimize disruptions to your staff.
A Team Dedicated to Growing and Improving the City of South Bend » DLZ has been working with the City since 1916.
With over 100 employees working in our South Bend Office, our local presence has produced many infrastructure projects
that have changed the landscape, provided economic development and improved the quality of life of the City residents. Our
team is local and has the ability to respond to any need 24 hours a day, 365 days a year. We want to continue this investment
and partnership well into the future.
The City of South Bend has put forth considerable effort in prioritizing this project for its residents. As the designer of this
project DLZ offers the unique combination of inherent knowledge of the area and this project, as well as the construction
experience of managing similar projects in similar settings. Having a direct connection between our design and
construction teams will allow for streamlined communication to help resolve issues in the most efficient manner. We
truly appreciate the opportunity to express our interest to work alongside the City on this project and for your consideration
of our team to express our interest in working with the City on this project and your consideration of our team.
SAFE ROUTES TO SCHOOL
KENNEDY ACADEMY
CITY OF SOUTH BEND » CONSTRUCTION INSPECTION SERVICES
Your VisionOur Commitment
This project illustrates your commitment to improving safety for students who walk to school.
We would be excited to partner with you to make this project a success.
Improving pedestrian routes near Kennedy Academy
2City of South Bend » Safe Routes to School » Construction Inspection
IDENTIFICATION & QUALIFICATIONS
DLZ Indiana, LLC
DLZ Indiana, LLC (DLZ) is a State certified minority-owned business enterprise (MBE) headquartered in South Bend, Indiana.
DLZ’s other Indiana offices are located in Indianapolis, Fort Wayne, Munster, and Burns Harbor. Our South Bend office is less
than 5 miles from the project site. Our ability to quickly access the project from our South Bend office will further enhance our
services to the City.
We focus on meeting and exceeding our clients’ expectations and are known for our expertise, integrity, and contributions to
the people and communities we serve. A family- and minority-owned, full-service firm, DLZ’s multidisciplinary, collaborative
approach to professional services allows us to build and lead successful project teams providing solutions that save money,
improve operations, and solve problems. Our vision is simple: Create successful partnerships with our clients that facilitate
trust, commitment, and communication.
We have been lucky to work with the City of South Bend for more than a century. We have completed the inspection of
sidewalks, ADA ramps, and trail projects for you and dozens of communities throughout Indiana. We want to be a part of your
vision to create accessible routes for students and parents to Kennedy Academy. We will support your mission through our
work on this project.
CONSTRUCTION
SERVICES
DLZ is a recognized leader in the construction inspection
field with one of the largest INDOT pre-qualified
construction inspection (13.1) teams in the State. Through
our work experience over the years with local governments
and INDOT, our DLZ team has developed excellent
relationships and a great understanding of the needs
of each type of organization and specifically INDOT-LPA
projects. The INDOT Area Engineers and Project Engineers
know and have worked directly with many of the DLZ team
members. These overall capabilities, our established
working relationships, and our ability to work
efficiently, demonstrates our high level of commitment
and qualifications to perform the required services on
this contract.
DLZ Indiana, LLC » 95% » 13.1
McCormick Engineering, LLC (DBE) » 5% » 13.1
TEAM PARTICIPATION
McCormick Engineering, LLC
McCormick is a local consulting firm providing professional
services for both the public and private sector for more than
35 years. McCormick Engineering, LLC (McCormick) is an
Indiana Certified WBE/DBE firm. McCormick has provided
engineering services to the public sector since 2008.
PROJECT TEAM
Principal In Charge/Quality Manager
ANDREW C. LEMBERIS, PE
Technical Resource ANTHONY GLENN, PE
Project Engineer
STEVE MENIS
Project Manager
BRAD DAILEY, PE
Inspectors (as required)
AUDREY STOOKSBURY, EI (DLZ)JOHN BEER (MCCORMICK)
INDOT LaPorte District
STEVE HAUERSPERGER (AREA ENGINEER)
CITY OF SOUTH BEND
BRAD DAILEY, PE
Project Manager
»27 Years Experience
»BS Civil Engineering,
Tri-State University
As a father of 6 children, the safety of our children is personal priority. Steve has 25 years of experience
performing construction supervision, administration, inspection, testing and final records documentation
for various construction projects. Steve’s proactive communication skills and organizational skills make
him an ideal candidate to lead this project that involves multiple intersections and the need to coordinate
with both schools. He has worked on several trail, sidewalk and SRTS projects, and he understand the importance of
constructing to ADA standards.
Relevant Experience
»INDOT Contract R-39513, SRTS at Monroe Primary/
Studebaker Elementary in South Bend, St. Joseph
County, IN
»INDOT Contract R-35693 North Liberty SRTS, North
Liberty, IN
»INDOT Contract R-34699 Safe Routes to School in
Mishawaka, St. Joseph County
»INDOT Contract R-39089, Stellar Trail, Trail and
Boardwalk Construction in North Liberty, St. Joseph
County
»INDOT Contract R-37347 Tamarack Trail in North
Liberty, St. Joseph County
STEVE MENIS Project Engineer
»25 Years Experience »BS Civil Engineering, Valparaiso University
City of South Bend » Safe Routes to School » Construction Inspection
Brad has 27 years experience in the construction industry. His
construction experience includes all types of road, bridge, traffic and
building projects. As the Division Manager for DLZ’s Construction
operations, Brad is a hands-on leader and is responsible for quality
control, scheduling, and financial management of field services
professional services contracts. His responsibilities also include
administrative management of the division and project coordination of
its professional staff.
Relevant Experience
»INDOT Contract R-34602 Pennsy-Greenway Trail Phase 2 and 3,
Schererville, IN
»INDOT Contract R-39012 Northview School SRTS, Valparaiso, IN
»INDOT Contract R-35693 North Liberty SRTS, North Liberty, IN
»INDOT Contract R-38150 US 30 Multi-Use Trail Phase 2A,
Valparaiso, IN
»INDOT Contract R-37323 ADA Sidewalk Ramp Improvements,
South Whitley, IN
»INDOT Contract R-37372 Calumet Avenue Multi-Use Trail,
Valparaiso, IN
»INDOT Contract R-36481 Safe Routes to School Project, Twin
Branch Elementary, Mishawaka, IN
»INDOT Contract R-36482 Safe Routes to School Project, Beiger
Elementary, Mishawaka, IN
»Pennsy Greenway Trail, Phase IV, Schererville, IN
»INDOT Contract R-39513, SRTS at Monroe Primary/Studebaker
Elementary in South Bend, St. Joseph County, IN
»INDOT Contract R-39089, Stellar Trail, Trail and Boardwalk
Construction in North Liberty, St. Joseph County, IN
»INDOT Contract R-37347 Tamarack Trail in North Liberty, St. Joseph
County, IN
»INDOT Contract R-37346, Wrenwood Multi-Use Trail in North
Liberty, St. Joseph County, IN
»INDOT Contract R-38061, LaSalle Trail, Phase III in St. Joseph
County, IN
3
Project Engineer’s Approach
»Keep the City informed throughout the project
»Make sure ample resources are available for successful
completion of the project
»Coordinate and monitor the contractor’s budget and
schedule
»Be direct liaison between DLZ Team and the City and
other stakeholders, as needed
»Be committed full time throughout the duration of this
contract
4City of South Bend » Safe Routes to School » Construction Inspection
Since joining DLZ, Audrey has performed construction inspection on a variety of INDOT and Local Public Agency
projects. She has experience in the observation and documentation of various aspects of road construction including
asphalt pavement, concrete curb, sidewalk, as well as water main and storm sewer installation.
Relevant Experience
»INDOT Contract R-44096, Plymouth Greenway Trail Phase
III, Plymouth, IN
»INDOT Contract R-42712, Road Rehabilitation on US 24
from 0.32 miles West of US 421 to 0.63 miles East of US
421, White County, IN
»INDOT Contract B-42171, Bridge Widening on Cedar Street
over St. Joseph River, Mishawaka, IN
»NICTD West Lake Corridor, Lake County, IN. Civil Inspector,
CM. The project includes an 8-mile expansion of the
existing South Shore Line and includes track, elevated
structures, bridges, retaining walls, and pedestrian
tunnels.
»I-94 Concrete Pavement Restoration, Porter County, IN.
Civil Engineer I, Highway Dept. The project includes
concrete pavement restoration for approximately 5 miles
of I-94 with additional replacement of ten guardrails and
restriping of pavement markings.
»US 31 Bridge Rehabilitation, Miami County, IN. Civil
Engineer I, Highway Dept. The project includes a rigid
deck overlay and railing replacement on US 31 over Old
US 24 & Norfolk Southern Railway, as well as replacement
of existing guardrails.
»Culvert Cleaning within INDOT LaPorte District, Lake,
Newton, Jasper, White, and St. Joseph County, IN. Civil
Engineer I, Highway Dept. The project includes cleaning
culverts within various state routes, including SR 114, SR
16, SR 55, US 20, US 231, and US 41.
John is an experienced technician with 30 years in the construction industry. Observation experience includes performance of material
testing, monitoring daily construction activities and preparing Daily Work Reports for roadway reconstruction, bridge deck replacement
and telecommunication fiber installation projects.
Relevant Experience
»INDOT On-Call, SR 331 over US 30 Bridge Deck Overlay,
Marshall County
»INDOT On-Call, US 24 Bridge Bundle, Fulton County
»INDOT On-Call, US 31 Reconstruction, St. Joseph County
»INDOT On-call, SR 49 Bridge Bundle, Porter County
»INDOT On-call, I-69 Bridge over Robinson Creek
Reconstruction, Fort Wayne
»Coal Line Trail, St. Joseph County
»Olive Street Reconstruction (2 phases), South Bend
»Indiana Toll Road Concessions, ITS Phase II,
Lake, Elkhart, LaGrange & Steuben County
»Handley Elementary Safe Routes to School, LaPorte
»Bendix Drive Reconstruction, South Bend
»Maplecrest Road Widening, Fort Wayne
»Kercher Road Reconstruction, Goshen
»LaPorte Street Footbridge Rehabilitation, Plymouth
»Mishawaka Bridge over Yellow Creek, Elkhart
AUDREY STOOKSBURY, EI DLZ Inspector
JOHN BEER McCormick Inspector
»2 Years Experience
»33 Years Experience
»BS Civil Engineering, Purdue University
»Indiana Department of Transportation Certified Technician
KEY STAFF We all Hold the Keys to Safety
Safety is a core value at DLZ. As such, we are lucky
to have a full-time dedicated safety professional,
Phil Yrjanson, that works with our Indiana team.
Phil’s responsibility is to visit project sites and work
with our teams on injury and accident prevention.
He also leads our monthly targeted field safety
training. In recent months he or our staff have
noted several deficient items in the field and shared
those lessons learned with the entire staff in order
to raise awareness. Some examples include:
• Alerted a contractor that their workers were
performing hot welding while standing on a gas line
attached to a bridge.
• Noted several instances of inconsistent use of
PPE and emphasizing to wear the same PPE as
the worker performing the task or move to a safe
location outside the work zone.
• Alerted contractor to loose handrail that had an
insufficient nail pattern.
New ramps planned at Bertrand and Fremont
City of South Bend » Safe Routes to School » Construction Inspection
PROJECT APPROACH
Coordinating traffic flow necessary on local streets,
alleys and drives
PROJECT UNDERSTANDING
We have completed a recent site visit of the proposed project
location and also reviewed the most recent set of design
plans. In addition to the construction of 20 curb ramps
at various intersections near Kennedy Academy, this Safe
Routes to School project will also replace approximately 900
feet of deteriorated or substandard sidewalk.
Existing alley approaches and residential driveways will be
reconstructed within the project limits to further provide
safe walking access throughout the corridor. A total of
29 residential drives and 21 alley approaches will be
reconstructed. Careful coordination with residents will be
necessary as access is temporarily impeded during the
course of construction.
5
LEGEND
Project Limits
Sidewalk, Ramp and
Drive Replacement
Linco
l
n
w
a
y
W
e
s
t
Goodland AvenueBertrand Street
Longley AvenueN. Johnson StreetN. Olive Street
Fremont Street
6City of South Bend » Safe Routes to School » Construction Inspection
MAINTENANCE OF TRAFFIC
Challenge
In many locations sidewalk and ramps will be replaced on both sides of the street. Pedestrian detour routes will be changed frequently to
accommodate ongoing construction as work often progresses one block at a time.
Solution
DLZ will request and review the contractor’s schedule early to verify construction is sequenced in accordance with the project plans and
Contract Information Book. Our team will closely monitor pedestrian detours to confirm they are set up correctly, maintained during
construction, and efficiently moved to the next location.
Pedestrian traffic will be routed to one side while the opposite side is under construction
SITE CONSIDERATIONS &
CHALLENGES
After a recent site visit, we have a thorough understanding of the
requirements of this project and the City’s expectations. With
a targeted November 2025 letting date, DLZ anticipates that
construction activities will begin in the Spring of 2026 and should
be complete prior to school beginning in August.
Our experience on similar projects tells us that the “best laid plans
often go awry.” Even with the most thorough project planning and
scrutinized design, unknown conditions can arise and must be
addressed. Identifying these risks early, being prepared to act,
and having a direct link to design resources will allow us to quickly
identify, evaluate, and implement and necessary field changes.
SCHOOL DROP-OFF AND PICK-UP
Challenge
Construction near schools will always present challenges due to
construction conditions and the curiosity of kids. Closely following
the Maintenance of Traffic plans, providing clearly defined
pedestrian detours, and maintaining a safe construction area will
be important to the overall safety of everyone.
Solution
Though direct impacts to Kennedy Academy will be minor during
construction, walking along the Goodland Avenue, Bertrand Street,
Freemont Street and N. Johnson Street corridors will impact
children walking to Kennedy Academy. Steve Menis will meet with
school officials at Kennedy Academy to discuss areas that will be
under construction and allow the school to address safety and
staying away from the work areas with the students.
Safe walking routes will be maintained for
Kennedy Academy
CITY OF SOUTH BEND
PROJECT ENGINEER
Steve Menis
Schedule and facilitate
meetings for all stakeholders,
including progress meetings.
Clearly communicate through
meeting minutes/summaries
and time-critical action items.
Return phone calls and
emails the same business
day or within 24 hours.
Establish and confirm
expectations and goals early
in the planning/design process.
COMMUNICATION PLAN
7City of South Bend » Safe Routes to School » Construction Inspection
Existing electric pole at the southeast corner of
Bertand and Fremont
FIELD ADJUSTMENTS WITHIN
RIGHT-OF-WAY CONSTRAINTS
Challenge
The plans detail the proposed construction at multiple intersections
along Goodland Avenue, Fremont Street, Bertrand Street, Longley
Avenue, and N. Johnson Street. Based on existing locations of fire
hydrants, power poles, storm drains, trees, etc., further details for
the relocation or protection of facilities may be required. Minor field
adjustments to sidewalk/ramps is often required to avoid unnecessarily
removing trees that are in conflict.
Solution
Our team is experienced in the inspection of new sidewalk and
trail systems, particularly in urban areas, that retrofit existing or are
built adjacent to constrained elevations or permanent features. We
understand that field changes are inevitable. We will work closely with
the contractor, and our design group, to verify that any needed changes
meet the intent of the plans, meet ADA regulations, and are evaluated
with full consideration of any added costs.INDOT LAPORTE DISTRICT
Steve Hauersperger
COMMUNICATION WITH
STAKEHOLDERS
Challenge
Construction of the SRTS project will affect Kennedy Academy
and numerous adjacent property owners. School officials,
parents, and adjacent property owners are concerned about
issues such as immediate access, how they will reach their home
or business, etc. Communicating logistical details daily and to all
parties can quickly become a complex effort.
Solution
DLZ knows that the City is our most important stakeholder and
we will coordinate with other stakeholders based on a plan that
is approved by the City. But our overall goal is to be your least
concern and work directly with the contractor and stakeholders
to communicate the important messages seamlessly. Steve will
leverage his strong communication and organizational skills to
work with the contractor and develop a database of affected
owners and communicate as required via emails, door-to-door
notifications and/or small group meetings.
8City of South Bend » Safe Routes to School » Construction Inspection
Project Management Approach
We believe that it’s not just what we do, it’s how we do
it. That’s why we proactively manage our relationships
with clients. As a rule, clients don’t simply want to be
notified when the job is done—they want to be kept up
to speed. So we listen, we communicate, and we deliver.
For us, the ultimate reward is a happy client. We believe
every job is different, and that we owe it to you to never
make assumptions. Sure, we have plenty of experience,
but we realize your needs are unique—so we won’t
take anything for granted. We believe working hard for
our clients is its own reward. That’s why we’re proud
to stand behind the projects we work on. Besides, the
majority of our business is from repeat customers. That’s
a testament not only to the quality of our work, but also
to the quality of our client service.
Steve
Menis
Brad
Dailey
WHY CHOOSE DLZ
AND OUR TEAM?
The Best Project
Manager and Engineer
to get your job done! Quality
Using best practices and guidance from the City, we
will develop standards for the bidirectional flow of
information between the construction and design
teams. It’s critical on a project with a significant
footprint, that standard processes and procedures be
followed by all team members to confirm the integrity
of the construction.
Communication
There are various audiences and types of
communication on a project like this. The highest
priority communications are those related to the
safety of the public and workforce on site. A detailed
communication plan for the project will be developed
for both inter and intra project communications,
including a robust plan for needs related to public
outreach.
Safety and Work Site Management
Safety of the worker and public are of utmost
importance. For this project, eliminating pedestrian
and worker interactions that could create unsafe
conditions will be critical. The team will scrutinize
the staging and proposed work plan, and address
deficiencies. We will communicate with the City to
inform you of changes to site access in order to notify
the public and monitor safety and mobility.
Schedule
DLZ will work tirelessly with the contractor to keep
the project on schedule, but we will not sacrifice the
quality of construction to maintain schedule.
Team Compliance with ADA Experience
DLZ has experience with the successful construction
of various projects that accommodate ADA compliant
facilities. Small tweaks to sidewalk, and ramp cross-
slopes can push grades out of compliance. We have
proven inspection techniques to help reduce these
risks.
Teamwork
The DLZ Team will function as an extension of your
staff, all working toward the common goal of a
successful project.
Cost Control
The DLZ Team will be constantly vigilant for cost
saving opportunities on the project. This can be
accomplished through various avenues including value
added opportunities, change order management,
identifying potential issues prior to causing a delay,
and managing inspection staffing levels.
9City of South Bend » Safe Routes to School » Construction Inspection
Monroe Primary/Studebaker
Elementary SRTS » South Bend,
Indiana
DLZ provided project management, construction inspection,
and administration services to replace over 4,500
square yards of concrete sidewalk and curb ramps at
approximately 100 intersections in the City of South Bend.
This project included replacing selected sections of
sidewalk and curb ramps within the general areas of
Monroe Primary Center and Studebaker Elementary School.
Significant field coordination was necessary to adjust
the concrete removal limits to maximize the sidewalk
replacement and control the project quantities. Grades
and elevations of the newly constructed elements were
monitored to confirm they met current ADA standards.
Nearly 5,800 linear feet of curb was replaced throughout
this project to allow for proper construction of the new curb
ramps.
Stellar Trail » North Liberty, Indiana
Construction engineering services were provided for the construction of a new 4,600-foot asphalt trail that connects Tamarack
Trail to School Trail. A 400-foot boardwalk was constructed along an existing wetland area just east of North Liberty School.
The boardwalk consisted of helical piles, concrete end bents, and treated lumber. Construction of the project also included
subgrade treatment, compacted aggregate, and seeding. Coordination for the project included maintenance of traffic, staging of
construction, construction schedule, and material testing.
EXPERIENCE
Wrenwood Trail » North Liberty, Indiana
DLZ provided construction engineering services for the construction of a
new asphalt trail from North Liberty School to the Potato Creek Crossing
Subdivision. A new 70’-2” Pre-Engineered Steel Truss Bridge was
constructed over Potato Creek. The bridge consisted of steel piling, concrete
end bents and reinforced concrete bridge approaches. Construction of
the project also included subgrade treatment, compacted aggregate, curb
ramp, and landscaping. Coordination for the project included maintenance of
traffic, staging of construction, construction schedule, and material testing.
LaSalle Trail, Phase III » St. Joseph County, Indiana
DLZ provided construction engineering services for the extension of the LaSalle Trail shared use path from Auten Road to the
Indiana/Michigan State Line. Work included construction of ADA compliant infrastructure with trail being 10 feet wide and hard-
surfaced concrete pavement with 2-foot shoulders. The length of the path is 5,700 feet.
The path follows the alignment on the existing former railroad bed and aligns with the trail from the previous phase, LaSalle Trail
Phase II. Coordination was required to align the path from the south side of State Line Road to the north side with the existing
IN-MI River Valley Trail.
City of South Bend » Safe Routes to School » Construction Inspection 10
11City of South Bend » Safe Routes to School » Construction Inspection
R-34699 Safe Routes to School
Project » Mishawaka, Indiana
INDOT Contract R-34699, was a Safe Routes to School
project in Mishawaka, Indiana. Curb ramps and sidewalks
along various streets near Battell Elementary School were
upgraded per current ADA requirements. Several streets
within the project limits had very steep grades, which
required additional construction engineering and field
adjustments to be made. Besides coordinating with local
residents and businesses, additional coordination was
performed so the project would not interfere with school.
Tamarack Trail » North Liberty, Indiana
DLZ provided construction administration services to construct a new 4,600-foot asphalt trail from Quinn Road to Wabash
Avenue. The trail connects the North Liberty Community Center to the North Liberty Youth League Ballpark along the
abandoned railroad corridor (formerly Indiana, Illinois, and Iowa Railroad). Approximately 2,200 feet of woods were cleared
as part of the project. Construction of the project also included subgrade treatment, compacted aggregate, and seeding.
Coordination for the project included maintenance of traffic, staging of construction, construction schedule, and material
testing.
(Rev. 06/27/2018)
Request for Proposal Number:
RFP Item Description:
Affirmative Action Certification (AAC) for Disadvantaged Business Enterprises (DBE)
I hereby certify that my company intends to affirmatively seek out and consider Disadvantaged Business Enterprises (DBEs)
certified by the State of Indiana’s DBE Program and the Kentucky Transportation Cabinet (KYTC) DBE Program to participate as
part of this proposal. An Agreement between INDOT and KYTC established reciprocal acceptance of certification of DBE firms in
their respective states under the Unified Certification Program (UCP) pursuant to 49 CFR §26.81(e) and (f).
I acknowledge that this certification is to be made an integral part of this proposal. I understand and agree that the submission
of a blank certification may cause the proposal to be rejected. I certify that I have consulted the following DBE websites to
confirm that the firms listed below are currently certified DBEs:
INDOT: https://entapps.indot.in.gov/DBELocator/
KYTC: https://transportation.ky.gov/Civil-Rights-and-Small-Business-Development/Pages/Certified-DBE-Directory.aspx
I certify that I have contacted the certified DBEs listed below, and if my company becomes the CONSULTANT, these DBEs have
tentatively agreed to perform the services as indicated. I understand that neither my company nor I will be penalized for DBE
utilization that exceeds the goal. After contract award, any change to the firms listed in this Affirmative Action Certification to
be applied toward the DBE goal must have prior approval by INDOT’s Economic Opportunity Division.
I.DBE Subconsultants to be applied toward DBE goal for the RFP item:
Certified DBE Name Service Planned Estimated Percentage to be
Paid*
%
%
%
%
II.DBE Subconsultants to be utilized beyond the advertised DBE goal for the RFP item:
Certified DBE Name Service Planned Estimated Percentage to be
Paid*
%
%
%
%
Estimated Total Percentage Credited toward DBE Goal:
Estimated Percentage of Voluntary DBE Work Anticipated over DBE Goal:
Company Name:
Signature: Date:
*It is understood that these individual firm percentages are estimates only and that percentages paid may be greater or less as a result of
negotiation of the contract scope of work. My company will use good faith efforts to meet the overall DBE goal through the use of these
or other certified and approved DBE firms.