May 13, 2025
Mr. Matthew D. Cain
HRP Construction Inc.
5777 Cleveland Rd./PO BOX 226
South Bend, IN 46628
mattc (ae,hrpconstruction. com
RE: Change Order No. 1 (Final)/Project Completion Affidavit
Wastewater Treatment Plant Yard Piping Improvements Contract A - Project No. 123-
031 A
Dear Mr. Cain:
At its May 13, 2025 meeting, the Board of Public Works approved the Final Change
Order for this project, be increased by $21,746 with an additional thirty-two (32) days. The final
contract amount is $500,746 with a completion date of August 15, 2024.
In addition, the Project Completion Affidavit for this project was approved in the amount
of $500,746. Copies of the Change Order and Project Completion Affidavit are enclosed for your
records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/hh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BREANA N. MIcou
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENVIRONMENTAL SERVICES
TO: Members of the Board of Public Works
Michael Schmidt, Assistant City Attorney Public Works
Theresa Heffner, Clerk of the Board of Public Works
FROM: Jacob M. Klosinski, P.E., Assistant City Engineer
SUBJECT: Agenda Request —Change Order No. 1 & Project Completion Affidavit
121-046 WWTP Compressor Building Masonry Improvements
(PROJ00000435 / PR-00030459 / PO-0030075)
DATE: April 29, 2025
The Division of Engineering and Division of Wastewater recommend the Board of Public Works
approval of Change Order No. 1 (FINAL), the Project Completion Affidavit, and closeout documents
for Project No. 123-031A WWTP Yard Piping Improvements.
Change Order No. 1 Summary
Additional Hydro Excavation to Expose Existing Utilities (Unforeseen Condition):
• Multiple subcontractors provided hydro excavation services to expose existing utilities in a
congested area between tanks. Many of the utility locations were unknown due to
inaccurate record drawings. Any of the utilities identified that were no longer in use were
removed during the excavation and hydro excavation work instead of adding additional
costs to protect or restore abandoned facilities.
• Cost Increase: $35,000.00
3-inch Reuse Water Line Repair:
• A 3-inch reuse water main ruptured during construction that required pavement removal,
excavation, repair and pavement restoration. This was completed by the contractor since
they were on -site and readily available to assist with the repair.
• Cost Increase $24,000.00
Adjustment in Quantities
• 6" WAS and Sludge Pipe Remove, reduced quantity by 167 LFT, Deduct $8,350.00
• 8" Sludge Pipe, Remove, reduced quantity by 2 LFT, Deduct $120.00
• 6" Ductile Iron Pipe, reduced quantity by 170 LFT, Deduct $28,220.00
• 8" Ductile Iron Pipe, reduced quantity by 5 LFT, Deduct $1,300.00
• 6" Ductile Iron 90 Deg Horizontal Bend, reduced quantity by 2 EACH, Deduct $11,000.00
• 8" Ductile Iron Transition Coupling, added quantity 1 EACH, Increase $9,000.00
• 5' Sidewalk, Concrete, 4 IN, reduced quantity by 32 LFT, Deduct $1,664.00
• Mulched Seeding and Sodding, increased quantity by 176 SYS, Increase $4,400.00
• Net Cost Adjustment for Unit Quantities, Cost Reduction:-$37,254.00
Change Order No. 1 Net Adjustment
• Cost Increase: $21,746.00
Total Change Order No. 1 Amount: $21,746.00
Original Contract Amount:
Previous Change Orders:
Current Change Order No. 1:
Percentage Increase by Change Order No
New Project Total:
Additional Time:
New Completion Date:
Attached are the following documents:
• Change Order No. 1
• Project Completion Affidavit
$479,000.00
$ 0.00
$ 21,746.00
4.54%
$500,746.00
32 Days
8/15/2024
• Maintenance Bond (10%, 3-Year), Amount $50,075.00
• Consent of Surety to Final Payment
• Pay Application — Final
• Final Waiver of Lien
Funding for this project was provided through Sewage Works Capital — Wastewater Capital,
Account 642-06-605-514-442005. For questions regarding the subject Agenda Request,
contact Jacob M. Klosinski (Ext. 9496) at the Division of Engineering.
DATE:
PROJECT NO:
PROJECT NAME:
CONTRACT DATE:
CHANGE ORDER NO.
CITY OF SOUTH BEND
DEPARTMENT OF PUBLIC WORKS =-
PROJECT CHANGE ORDER18;
04-29-2025
123-031A (DFO PROJ00000435)
South Well Wastewater Treatment Plant Yard Piping
Improvements - Contract A
03-12-2024
SUBJECT OF CHANGE ORDER: Additional Scope Items due to unforeseen conditions, Add'I
Hydro Excavation and 3-inch Reuse Water Pipe Repair, Site
Restoration
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns.
The original contract sum
Net change by previously authorized change orders
The contract sum prior to this change order
By this Change Order, the project amount is
The new contract sum including this change order
This Change Order represents a total change of
Total change for entire project
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
CONTRA OR
aa&kl JJ
Contractor Signature ma ew Cain, President
Matthew D. Cain, President
Printed Name and Title
HRP Construction, Inc.
Company name
5777 Cleveland Road / PO Box 266
Address
South Bend, IN 46628
City, State, Zip
$
479,000.00
$
0.00
$
479,000.00
® Increased
❑ Decreased $
$
21,746.00
500,746.00 J3
4.54 %
4.54 %
07/14/2024
0 Days
32 Days
8/15/2024 Im
RECOMMENDED FOR APPROVAL
Construction Manager
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
to�(4
Elizabeth A. Maradik, President
Gary A. Gilot, Member
4 7��
Murray L. Miller, Member
Joseph R. Molnar, Vice President
Breana Micou, Member
Attest: Theresa M. Heffner, Clerk
Date: May 13, 2025
�O45p13T11 g �
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
PROJECT COMPLETION AFFIDAVIT
1865
II 11 -
PROJECT NAME Wastewater Treatment Plant Yard Piping Improvements - Contract A
PROJECT NO. 123-031 A FINAL COST 500,746.00
CONTRACT 03-12-2024 MAINTENANCE AGREEMENT ENDS 08/15/2027
SIGNED
PROJECT
DESCRIPTION
Demolition Work, Installation of Sludge Piping, and Site Restoration at the
Wastewater Treatment Plant
WITNESSETH:
The work under the above contract between the City of South Bend and the undersigned contractor having
been completed, the City of South Bend, its officials and agents are hereby released from all claims and
demands whatsoever arising under or by such contract, and that the contractor performed the work within the
scope of the Specifications and Standards of the City of South Bend which were a part of the above Contract.
Executed this 29th day of April , 20 25
Signature
Nancy Knapik, Vice President
Printed Name
HRP Construction, Inc.
Company Name
5777 Cleveland Road
PO Box 266
Company Address
South Bend, IN 46628
City/State/Zip
WITNESSES
Before me, the undersigned Notary Public in and for said country and state, personally
appeared Nancy Knapik , and acknowledged his/her signature to the above Project Completion
Af ldavit on the 29th day of April , 20 25
(// C L Vargmft
`'" tJoiy9c, Stale of kdorla
tary Signature My Commission Expire sir 06L
Cynthia L. Vanheste , „ My
Printed Name County of Residence i
If the Contractor is a corporation, the following certificate will be executed.
I, Nancy Knapik , certify that I am Secretary of the Corporation executing this release; that
Nancy Knapik who signed this release on behalf of the contractor was then
Secretary of said Corporation; that said release was duly signed for and on behalf of said
Corporation by Authority of its governing body, and is within the scope of corporate powers:
Secretary's ignature
Nancy Knapik, Secretary
Printed Name
Corporate Seal
DEPARTMENT OF PUBLIC WORKS APPROVAL
This project is acceptable for final approval and we recommend to the Board of Public Works that it be
ordained so.
Date:
Construction Manager
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
Elizabeth A. Maradik, President
119
�GfsAG
Gary A. Gilot, Member
jYLwy � 7'i2o�4,
Murray L. Miller, Member
Joseph R. Molnar, Vice President
Breana Micou, Member
Attest: Theresa M. Heffner, Clerk
Date: May 13, 2025
State of Indiana, County of St. Joseph SS:
Nancy Knapik being duly sworn that he/she is the Vice President
(Name of Officer) (Title)
of HRP Construction Inc. — having contracted with City of South Bend
(Contractor) (Owner)
Demolition work, installation of sludge piping, and site restoration at the
to furnish certain materials and/or labor as follows; Wastewater Treatment Plant
(Deseripdon)
for a project known as Wastewater Treatement Plant Yard Piping Improvements, Contract A, Project 123-031A
(Name of Project)
located at 3113 Riverside Drive, South Bend, IN
and owned by City of South Bend
(Owner)
and does hereby further state on the behalf of the aforementioned subcontractor/supplier;
(PARTIAL WAIVER) that there is due from the Contractor the aura of
Dollars
❑ receipt of which is hereby aclatowledged; or
❑ the payment of which lies been promised as the sole consideration for this Affidavit and Final Waiver of Lien which is given
solely with respect to said amount, and which waiver shall be effective only upon receipt of payment thereof by the
undersigned;
(FINAL WA1VEJt) that the final balance due from the contractor is the sum of
Twenty Five Thousand Thirty Seven Dollars and Thirty Cents ($ 25,037.30)
❑ recelpt of which is hereby acknowledged; or
® the payment of which has been promised as the sole consideration for this Affidavlt and Final Waiver of Lien which shall
become effective onlyuponreeeipt of such payment,
THEREFORE, the undersigned waives and releases unto the Owner of said premises, any and all liens or claims whatsoever
on the above -described property and improvements thereon an account of labor or material or both, furnished b the undersigned
thereto, subject to limitations or conditions expressed herein, if any; and further certified that no other party has any claim or right to a
Jim on account of any work performed or material furnished to the undersigned for said project, and within the scope of this Affidavit
and Waiver of Lien.
HRP Construction Inc.
BY
(Fim) (uthoriz�io .Representative)
STATE OF INDIANA ) Nancy Knapik, Vice President
SS:
5T. JOSEPH COUNTY )
Before me, the undersigned, a Notary Public, In and for said County and State, personally appeared Nancy Knapik
and acknowledged the execution of the foregoing Affidavit and Waiver of Lien.
IN WITNESS WHEREOF, I have hereunto subscribed my name and affixed my o eial seal on the 29th day of
April 20 25
N Public Signature
My Commission Expires: March 6, 2032
Residing in St. Joseph County, Indiana
Cynthia L. Vanheste
Notary Public Name
�Z�f 3t uA.KZ A CyLanheste
�G�hdla�
Jo8l"W"�3
t 66�
MAINTENANCE BOND
KNOW ALL MEN BY THESE PRESENTS:
Bond No. MNT9477204
That HRP Construction Inc. PO Box 266 5777 Cleveland Rd, South Bend, IN 46624-0266
as Principal, hereinafter call Contractor, and Fidelity and Deposit Company of Maryland
Chicago, IL 60606 , as Surety, hereinafter call Surety; are held and firmly bound unto
City of South Bend Board of Public Works -, as Obliges, hereinafter called Owner, in the penal sum of
$50,074.60 R, for the payment whereof Contractor and Surety bind themselves, their heirs, executors,
administrators, successors, and assigns, jointly and severally, firmly by these presents.
WHEREAS, Contractor has by written agreement, dated March 14, 2024 1
entered into a contract with owner for Project No. 123-031 -A, Wastewater Treatment Plant Degrit Building Yard Piping Replacement $
in accordance with the General Conditions, the Drawings and Specifications, which contract is by reference incorporated herein,
and made a part hereof, and is referred to as the Contract.
NOW, THEREFORE, the condition of this obligation is such that, if Contractor shall remedy any defects due to faulty materials or
workmanship, and pay for any damage to other work resulting therefrom, which shall appear within a period of jt�3 year(s)
from the date of substantial completion of the work provided for in the Contract, then this obligation to be void; otherwise to
remain in full force and effect.
Bond Shall be Effective from August 15, 2024 to August 15, 2027.
PROVIDED, HOWEVER, that Owner shall give Contractor and Surety notice of observed defects with reasonable promptness.
SIGNED and sealed this 30th day of April .2025
HRP Construction Inc.
Pri
(Seal)
Matthew D. Cain', President
Fidelity and Deposit Company of Maryland 'NOA111C11
tk
Z<ZF,
w
0
Z Mz cio
1 S
Jep r L. Kas24ia, ktorrt,8'�y-in-Fact vo,
ZURICH AMERICAN INSURANCE COMPANY
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY
FIDELITY AND DEPOSIT COMPANY OF MARYLAND
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS: That the ZURICH AMERICAN INSURANCE COMPANY, a corporation of the State of New
York, the COLONIAL AMERICAN CASUALTY AND SURETY COMPANY, a corporation of the State of Illinois, and the FIDELITY
AND DEPOSIT COMPANY OF MARYLAND a corporation of the State of Illinois (herein collectively called the "Companies"), by
Robert D. Murray, Vice President, in pursuance of authority granted by Article V, Section 8, of the By -Laws of said Companies, which
are set forth on the reverse side hereof and are hereby certified to be in full force and effect on the date hereof, do hereby nominate,
constitute, and appoint William J. CERNEY, III, Nicole L. BICKNELL, Jennifer L. KASZNIA, Pamela S. HIGGINBOTHAM,
Megan E. RIESENBERG, Faith D. HUNT, Mark E. WOBBE, Barbara E. PEARSON, and Theresa M. BURNS, of South Bend,
Indiana, Sandra L. JUNK, and Jordan M. SCHEIBER, of Fort Wayne, Indiana and Wesley L. MANTOOTH, and Lisa M.
THOMAS, of Indianapolis, Indiana, its true and lawful agent and Attorney -in -Fact, to make, execute, seal and deliver, for, and on
its behalf as surety, and as its act and deed: any and all bonds and undertakings, and the execution of such bonds or undertakings in
pursuance of these presents, shall be as binding upon said Companies, as fully and amply, to all intents and purposes, as if they had been duly
executed and acknowledged by the regularly elected officers of the ZURICH AMERICAN INSURANCE COMPANY at its office in New
York, New York., the regularly elected officers of the COLONIAL AMERICAN CASUALTY AND SURETY COMPANY at its
office in Owings Mills, Maryland., and the regularly elected officers of the FIDELITY AND DEPOSIT COMPANY OF
MARYLAND at its office in Owings Mills, Maryland., in their own proper persons.
The said Vice President does hereby certify that the extract set forth on the reverse side hereof is a true copy of Article V, Section 8,
of the By -Laws of said Companies, and is now in force.
IN WITNESS WHEREOF, the said Vice -President has hereunto subscribed his/her names and affixed the Corporate Seals of the
said ZURICH AMERICAN INSURANCE COMPANY, COLONIAL AMERICAN CASUALTY AND
SURETY COMPANY, and FIDELITY AND DEPOSIT COMPANY OF MARYLAND, this 17th day of September, A.D. 2021.
Yitii+t \ , ilft ftt„
r Gosr,„''asua4gam
p '''+.xtt
\",Yfltttiitttft
���'�PO�^+;,�dc
;•^Oc�r^pQp'•`ti.`E�.� bt`,,
`F+'•56
Coal C%�.ti
�c�i0 A x
s rr; t+?x
is
�I seal.
rgga;,tQJ�: : Ti` 43 ,�.•�
^�U47..r''�k�a `
•5
,'4tttttl+.HUf..... ff���tft
a
''"ry
aaaa`a```
�eyi,�i t41t\a
+ ftili It\ftfaa�a
+
By Robert D. lllturay
Vice President
By: Dawn E. Brown
Secretary
State of Maryland
County of Baltimore
ATTEST:
ZURICH AMERICAN INSURANCE COMPANY
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY
FIDELITY AND DEPOSIT COMPANY OF MARYLAND
On this 17th day of September, A.D. 2021, before the subscriber, a Notary Public of the State of Maryland, duly commissioned and qualified,
Robert D. Murray, Vice President and Dawn E. Brown, Secretary of the Companies, to me personally known to be the individuals and officers described
in and who executed the preceding instrument, and acknowledged the execution of same, and being by me duly sworn, deposeth and saith, that he/she is
the said officer of the Company aforesaid, and that the seals affixed to the preceding instrument are the Corporate Seals of said Companies, and that the said
Corporate Seals and the signature as such officer were duly affixed and subscribed to the said instrument by the authority and direction of the said Corporations.
IN TESTIMONY WHEREOF, I have hereunto set my hand and affixed my Official Seal the day and year first above written.
'etc y�R•1t3�ftf �f'
t•Rt,t tstc\
Constance A. Dunn, Notary Public
My Commission Expires: July 9, 2023
EXTRACT FROM BY-LAWS OF THE COMPANIES
"Article V, Section 8, Attorneys -in -Fact. The Chief Executive Officer, the President, or any Executive Vice President or Vice President
may, by written instrument under the attested corporate seal, appoint attomeys-in-fact with authority to execute bonds, policies,
recognizances, stipulations, undertakings, or other like instruments on behalf of the Company, and may authorize any officer or any such
attorney -in -fact to affix the corporate seal thereto; and may with or without cause modify of revoke any such appointment or authority at any
time."
CERTIFICATE
I, the undersigned, Vice President of the ZURICH AMERICAN INSURANCE COMPANY, the COLONIAL AMERICAN
CASUALTY AND SURETY COMPANY, and the FIDELITY AND DEPOSIT COMPANY OF MARYLAND, do hereby certify that the
foregoing Power of Attorney is still in full force and effect on the date of this certificate; and I do further certify that Article V, Section 8, of
the By -Laws of the Companies is still in force.
This Power of Attorney and Certificate may be signed by facsimile under and by authority of the following resolution of the Board of
Directors of the ZURICH AMERICAN INSURANCE COMPANY at a meeting duly called and held on the 15th day of December 1998.
RESOLVED: "That the signature of the President or a Vice President and the attesting signature of a Secretary or an Assistant Secretary
and the Seal of the Company may be affixed by facsimile on any Power of Attorney... Any such Power or any certificate thereof bearing such
facsimile signature and seal shall be valid and binding on the Company."
This Power of Attorney and Certificate may be signed by facsimile under and by authority of the following resolution of the Board of
Directors of the COLONIAL AMERICAN CASUALTY AND SURETY COMPANY at a meeting duly called and held on the 5th day of
May, 1994, and the following resolution of the Board of Directors of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND at a
meeting duly called and held on the 1 Oth day of May, 1990.
RESOLVED: "That the facsimile or mechanically reproduced seal of the company and facsimile or mechanically reproduced signature
of any Vice -President, Secretary, or Assistant Secretary of the Company, whether made heretofore or hereafter, wherever appearing upon a
certified copy of any power of attorney issued by the Company, shall be valid and binding upon the Company with the same force and effect
as though manually affixed.
IN TESTIMONY WHEREOF, I have hereunto subscribed my name and affixed the corporate seals of the said Companies,
this 30th day of April , 2025 .
CFO cut40- ,rr # i 40M
Brian M. Hodges, Vice President
TO REPORT A CLAIM WITH REGARD TO A SURETY BOND, PLEASE SUBMIT A COMPLETE DESCRIPTION
OF THE CLAIM INCLUDING THE PRINCIPAL ON THE BOND, THE BOND NUMBER, AND YOUR CONTACT
INFORMATION TO:
Zurich Surety Claims
1299 Zurich Way
Schaumburg, IL 60196-1056
wtyv.reportsfclaims@zurichna.com
800-626-4577
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 04-29-2025
Name: Jacob M. Klosinski Department of Public Works — Engineering Division
BPW Date: 05-13-2025 Phone Extension: Ext. 9494
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Michael Schmidt
Dept. Attorney ® Attorney Name Michael Schmidt
Purchasing
® Mickey Low
Check the Appropriate Item Type — Required. for All Submissions
❑ Professional Services Agreement ❑ Contract ❑ Proposal
❑ Open Market Contract ❑ Amendment/Addendum ❑ Special Purchase, QPA
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award ❑ Reject Bids/Quotes
❑ Proposal Opening ® C/O & PCA No. 1 ❑ PCA
❑ Chg. Order, No. ❑ Traffic Control ❑ Resolution
❑ Other: ❑ Ease./Encroach
Company or Vendor Name
New Vendor
MBE/WBE Contractor
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Special Contract Provisions
Purpose/Description
Amount of
El
Previous Amount
Information
HRP Construction, Inc. (V-00000775
❑ Yes[] If Yes, Approved by Purchasing
® No
❑ WBE Completed E-Verify Form Attached ❑❑ Nos
Wastewater Treatment Plant Yard Piping Improvements — Contract A
123-031A (PROJ00000435 / PO-0030075)
642-06-605-514-442005
PO-0030075
See Below
Sum
The Division of Engineering and Division of Wastewater requests the Board
of Public Works approval of Change Order No. 1 and the project completion
affidavit for the subject project. All work is complete. Refer to Inter -Office
Memorandum and attachments for chan e order and completion affidavit.
For Change Orders Only
Increase $ 21,746.00
Decrease ($ )
$ 479,000.00
Increase 4.54%
Current Percent of Change:
Decrease ( %)
New Amount
$ 500,746.00
Increase 4.54%
Total Percent of Change:
Decrease ( %)
Time Extension Amount:
32 Days
New Completion Date:
08/15/2024