HomeMy WebLinkAboutChange Order No. 1 - PW Service Center Roofing Proj No R124-032B - Slatile Roofing1316 COUNTY -CITY BUILDING 227 W. JEFFERSON BOULEVARD SOUTH BEND, INDIANA 46601-1830 PHONE 574/235-9251 FAx 574/235-9171 CITY OF SOUTH BEND JAMES MUELLER, MAYOR BOARD OF PUBLIC WORKS May 13, 2025 Mr. Kenneth W. Hoy Jr. Slatile Roofing and Sheet Metal Co., Inc. 1703 South Ironwood Dr. South Bend, IN 46613 Ken.hoykslatile.com RE: Change Order No. 1 — PW Service Center Roofing Replacement — Project No. R124- 032B Dear Mr. Hoy: At its May 13, 2025 meeting, the Board of Public Works approved the above referenced Change Order be increased by $52,220.70, bringing the revised contract amount to $951,032.70. Enclosed is a copy of the Change Order for your records. If you have any further questions, please call this office at (574) 235-9251. Sincerely, /s/ Theresa Heffner Theresa Heffner, Clerk Enclosures TH/hh ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BREANA N. MIcou INTER -OFFICE MEMORANDUM V � DEPARTMENT OF PUBLIC WORKS r8a DIVISION OF ENGINEERING TO: Theresa Heffner, Clerk Board of Public Works FROM: Lidya Abreha, Project Engineer SUBJECT: Change Order #1 - Project No. R124-032B PW Service Center Re -roofing DATE: May 5t", 2025 The purpose of this change order is to address the replacement of the air conditioning systems for AC-1 and AC-4, as well as furnaces associated with AC-4 which will be installed on the roof. Please see attached documents for more details. Page 1 of 1 CITY OF SOUTH BEND, INDIANA DEPARTMENT OF PUBLIC WORKS PROJECT CHANGE ORDER DATE: PROJECT NO: PROJECT NAME: CONTRACT DATE: CHANGE ORDER NO: SUBJECT OF CHANGE ORDER: 5/2/2024 R124-032B PW Center Re -Roofing 1/14/2025 1 Replacement of the air conditioning systems for AC-1 and AC-4, as well as furnaces associated with AC-4 The original contract sum $ 898,812.00 Net change by previously authorized change orders $ 0.00 The contract sum prior to this change order $ 898,812.00 By this Change Order, the project amount is QX Increased The new contract sum including this change order This Change Order represents a total change of Total change for entire project Original contracted completion date/time Extension of date/time by previous change orders Date/time extension by this change order New completion date/time CONTRACTOR w Contractor Signature ❑ Decreased $ 52,220.70 $ 951,032.70 5.8 % 5.8 % 06/20/2025 0 days 0 days 06/20/2025 RECOMMENDED FOR APPROVAL CO RUCTION MANAGER CITY OF SOUTH BEND Printed Name and Title CITY OF SOUTH BEND, INDIANA BOARD OF PUBLIC WORKS Slatile Roofing and Sheet Metal Co., INC Company Name Elizabeth A. Maradik, President 1703 South Ironwood Addresses a South Bend, IN 46613 City, State, Zip Gary A. Gilot, Member Murray L. Miller, Member ,�- 7T� Joseph R. Molnar, Vice President Breana Micou, Member /Xe Attest: Theresa M. Heffner, Clerk Date: May 13, 2025 Phone:5742337485 Fax: 5742337531 info®slati leroofing. com www.slatileroofing.com ROOFING AND RESTORATION, INC. 1703 South Ironwood • South Bend, IN 46613 05/02/2025 ATTN: Lydia Abreha RE: Quote for Project at 731 South Lafayette Blvd. The total project cost is $52,220.70, which includes the base quote of $49,734.00 plus a 5% fee of $2,486.70. Thank you for the opportunity to provide a quote for this project. Please do not hesitate to reach out if you have any questions or require further clarification. Ken Hoy Jr. Project manager ken.hoy@slatile.com Established 1924 ROOFING — MASONARY RESTORATION — SHEET METAL et VIKUL vaired, �WPYI%Afjte? n� Plarmbing • Heating • Air Conditioning • Boilers Commercial • Residential • hiditstrial April 30, 2025 Slatile Roofing & Sheet Metal Co. Attn: Ken Hoy 1703 S. Ironwood Dr. South Bend, IN 46613 Re: A/C System Replacements Dear Mr. Hoy: We are pleased to quote you on the work associated with the replacement of the air conditioning systems for AC-1 and AC-4, as well as the furnaces associated with AC-4, on the site of the City of South Bend Traffic & Lighting Building at 731 South Lafayette Boulevard in South Bend, Indiana. To provide clarity to our quotation, all items are laid out in a start -to -finish work sequence. We propose to perform the following: • Disconnect and remove the existing Carrier twinned vertical cased coils from furnace systems AHU-1 and AHU-4 and discard off -site. o All utilities will be taken back to a point suitable for reconnection. • Disconnect and remove the existing humidifiers and discard off -site. o All utilities associated with the humidifiers will be demolished and removed. The water lines will be permanently capped to prevent future leaks. • Disconnect and remove the twinned furnaces for system AHU-4 and discard off -site. • Modify the existing return air base for AHU-4 as required to accommodate the new furnaces. • Furnish and install two (2) Carrier 96% efficient, 60k BTU furnaces for system AHU-4 and set on the original return air plenum base. o Carrier Furnace M#: 59SC6A060M17-16 • Furnish and install two (2) Carrier twinned, cased vertical coils with thermal expansion valves (TXV's) and set on top of the new and existing furnaces. o Carrier Coil M#: CAVTCOIL408A00 • Furnish and install two (2) Carrier 7.5 Ton, 460V/30, single circuit condensers with two -stage compressors and set on the wood supports on the roof. o New wood supports furnished and installed by Slatile. We will add additional wood supports on top of these to support our new units as needed. o New units are to be hoisted to the roof by Slatile when they are setting the other existing units. • Furnish and install all applicable sheet metal as required to build new supply air transition pieces to connect between the new cased coils and the existing supply air ductwork. • Furnish and install 1%" thick x %# density foil faced fiberglass ductwrap on the new supply ductwork transition pieces and tie-in to the existing duct insulation. • Furnish and install 2" Schedule 40 PVC pipe with DWV pattern solvent welded fittings to connect the new furnaces to the existing furnace 2" intake and exhaust pipes. • Furnish and install Schedule 40 carbon steel pipe and fittings to connect the new furnaces to the existing furnaces. • Furnish and install Schedule 40 PVC pipe with pressure pattern solvent welded fittings to connect the new furnaces and cased coils to the existing condensate piping system. ,10E VqUI�r 1011 South Michigan Street • South Bend, IN 46601 Phone: (574) 289-6351 • Fax: (574) 289-3755 OQ ® www.ejwhiteinc.net Licensed— Bonded— Insured IN License #CP81021273 • Furnish and install all required line voltage to connect the new furnaces to the existing electrical circuits. • Furnish and install all required line voltage to connect the new condensers to the existing electrical whips/circuits. • Furnish and install one (1) Carrier low voltage twinning kit (#AGATWNDTE0IA) to join the operation of the two furnaces, matching the operation and sequencing of the existing systems. • Reconnect all applicable low voltage wiring to the new furnaces and condensers. o Existing thermostats will be reused. • Pressure test the existing refrigerant piping with Nitrogen to a minimum of 350 PSI for atleast 24 hours to ensure no leaks are present. o Our pricing is based on reusing the existing refrigerant piping. The piping will be pressure tested and checked to ensure no leaks are present. o We have verified with Carrier that the existing refrigerant piping sizes will work for the new equipment. • Flush the existing refrigerant piping with Nu-Calgon RX11 refrigerant line flush and Nitrogen to ensure all impurities including debris, oils, moisture and other non-condensables have been removed from the system. • Furnish and install Type "L" OXY/ACR nitogenized (cleaned and capped) copper with cleaned and bagged fittings to reconnect the existing refrigerant piping to the new coils and condensers. o Includes a new filter drier for each condensing unit. o All fittings will be brazed with 15% silver brazing alloy. • Furnish and install %" thick Armaflex rubber insulation on all new interior refrigeration suction piping. o Insulation work performed by Valley Insulating Co. of Mishawaka. • Furnish and install %" thick Armaflex rubber insulation on all new and existing exterior refrigerant suction piping associated with these two condensing units. o Insulation work performed by Valley Insulating Co. of Mishawaka. o Does not include reinsulating the exterior refrigerant suction piping associated with the other, existing condensing units. The insulation on these lines is rotten and has fallen off. The lack of insulation greatly reduces the efficiency of the refrigeration systems. We would suggest that while the insulator is on site, they provide a price for your consideration to reinsulate these other existing lines. • Pressure test the completed refrigerant system to a minimum of 350 PSI to ensure no leaks are present. • Triple evacuate each system to a final standing vacuum of 250 microns or less to ensure a clean, tight system with no debris, moisture or other non-condensables. • Charge each system with new, virgin, R-410A refrigerant in accordance with the manufacturer's specifications and charging instructions. • Provide documented start-up of the new furnace and A/C systems in accordance with the manufacturer's requirements. • Includes clean-up and demobilization for our scope of work. • Includes all applicable permits with the City of South Bend Building Department for our scope of work. • Includes a full one (1) year labor and material warranty on all Edward J. White, Inc. furnished and installed material and equipment associated with this project. o The new condensing units are furnished with a one (1) year parts and five (5) year compressor parts warranty. The new furnaces are furnished with a one (1) year parts and twenty (20) year heat exchanger parts warranty. We will perform the work as described above for the sum of Forty -Nine Thousand Seven Hundred Thirty -Four and 00/100 Dollars ($49,734.00). Does not include sales tax or work associated with other HVAC systems on site. All material is currently in stock and available in approximately 1 week from date of order. Our proposal must be accepted within 14 days of this quotation, otherwise, our pricing is null and void! We are backlogged for summer and need to complete this work prior to June 1(or as close to that as possible) to make this work with our schedule. We could start this work right away (within a few days of award). Please contact our office with any questions. Respectfully submitted; Edward J. White, Inc. Jeffrey M. Bucher, Jr. Vice -President BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date 05/05/2025 Department Public Name Lidva Abreha BPW Date 05/13/2025 Phone Extension 5961 Required Prior to Submittal to Board BPW Attorney ® Attorney Name Michael Schmidt Dept. Attorney ❑ Attorney Name Purchasing ❑ Mickey Lovy Check the Appropriate Item Type — Required. for All Submissions ❑ Professional Services Agreement ❑ Contract ❑ Proposal ❑ Open Market Contract ❑ Amendment/Addendum ❑ Special Purchase, QPA ❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet ❑ Quote Opening ❑ Quote Award ❑ Reject Bids/Quotes ❑ Proposal Opening ❑ C/O & PCA No. ❑ PCA ® Chg. Order, No. 1 ❑ Traffic Control ❑ Resolution n Other: n Ease./Encroach Company or Vendor Name New Vendor MBE/WBE Contractor Project Name Project Number Funding Source Account No. Amount Terms of Contract Purpose/Description Information Yes U If Yes, Approved by Purchasing No El MBE ❑ WBE Completed E-Verify Form Attached ❑❑ Nos PW Service Center Roofing Replacement (task 2) R124-032B Motor Vehicle High & Sewage Works Capital 202-503-443001 & 642-509-443001 Lump Sum For Change Orders Only Amount of ® Increase $ 52,220.70 ❑ Decrease ($ ) Previous Amount $ 898,812.00 Increase Current Percent of Change: Decrease New Amount $ 951,032.70 Increase Total Percent of Change: Decrease Time Extension Amount: New Completion Date: 5.8% 5.8%