May 13, 2025
Mr. Garrett VanParys
Rieth-Riley Construction Company
25200 State Road 23
South Bend, IN 46614
gvanparys@rieth-riley.com
RE: Change Order No. 1 – YSB and SB Thrive Subdivision Improvements – Project No.
123-011
Dear Mr. VanParys:
At its May 13, 2025 meeting, the Board of Public Works approved the above referenced
Change Order be increased by $120,499.45, bringing the revised contract amount to
$3,446,871.04.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/hh
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Members of the Board of Public Works
Michael Schmidt, Assistant City Attorney Public Works
Theresa Heffner, Clerk of the Board of Public Works
FROM: Jacob M. Klosinski, P.E., Assistant City Engineer
SUBJECT: Agenda Request –Change Order No. 1
123-011 YSB / SB Thrive Subdivision Improvements
(PROJ00000465 / PR-00026650 / PO-0029777)
DATE: April 25, 2025
The Division of Engineering recommends the Board of Public Works approval of Change Order No.
1 for Project No. 123-011 YSB and SB Thrive Subdivision Improvements. Change Order No. 1
addresses the addition of sidewalk with funding that was approved by the Redevelopment
Commission in 2024.
Change Order No. 1 Summary
Additional Sidewalk Construction $117,499.45
Additional Survey and Construction Staking (subcontractor Bertsch Frank) $ 3,000.00
Total Change Order No. 1 $120,499.45
Note: City Engineering directed this change request at the request of the Redevelopment
Commission and approved funding from the Redevelopment Commission.
Original Contract Amount: $3,326,371.59
Previous Change Orders: $ 0.00
Current Change Order No. 1: $ 120,499.45
Percentage Increase by Change Order No. 1: 3.62%
New Project Total: $3,446,871.04
Additional Time: 0 Days
New Completion Date: 07/31/2024
Time adjustments to the contract will be addressed in an upcoming change order that reflects the
final adjustments necessary for tree planting and the remaining right-of-way restoration work. The
next change order will also address final quantities for overruns and underruns for unit price items.
Funding for this project was provided through Fund101 General Fund, Fund 408 Economic
Development Income Tax, Fund 433 Redevelopment Commission General Fund ARP015. For
questions regarding the subject Agenda Request, contact Jacob M. Klosinski (Ext. 9496) at the
Division of Engineering.
May 13, 2025
South Bend
Redevelopment Commission
227 West Jefferson Boulevard, Room 1308, South Bend, Indiana
Redevelopment Commission Agenda Item I. Pres/ V-Pres
DATE: September 12, 2024
FROM: Charlotte Brach, P.E.
SUBJECT: Budget Request —YSB and South Bend Thrive
Sidewalk
ATTEST. J 6,"je:, cretary
r1
Date:
Lv APPROVED Not Approved
SOUTH BEND REDEVELOPMENT COMMISSION
Funding Source* (circle) River West; River East; South Side; Douglas Road; West Was
Funds are subject to the City Controller's determination of availability; if funds are unavailable, as solely determined by
authorization of the expenditure of such funds shall be void and of no effect.
Riv. East Res.
er, then the
PURPOSE OF RE UEST: Budget request for $120,000 out of the Pokagon Fund for sidewalk throughout the Youth
Services Bureau and South Bend Thrive subdivision.
SPECIFICS: The City is constructing the public infrastructure for the YSB and South Bend Thrive Subdivision,
including storm sewer, sanitary sewer, water main, streets, curbs, curb ramps, lighting, and trees. This request
will cover the public sidewalk for the subdivision.
EXCELLENCE I ACCOUNTABILITY i INNOVATION I INCLUSION I EMPOWERMENT
1400S County -City Building 227 W. Jefferson Bvld. South Bend. Indiana 46601' p 574.235.9371 vnvw.southbend! n.gov
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 04-25-2025
Name: Jacob M. Klosinski Department of Public Works – Engineering Division
BPW Date: 05-13-2025 Phone Extension: Ext. 9494
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Michael Schmidt
Dept. Attorney Attorney Name Michael Schmidt
Purchasing Mickey Lovy
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 1 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Rieth-Riley Construction Company (V-00001411)
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name YSB and SB Thrive Subdivision Improvements
Project Number 123-011 (PROJ00000465)
Funding Source
Account No. PO-0029777
Amount See Below
Terms of Contract Unit Prices
Special Contract Provisions
Purpose/Description The Division of Engineering requests the Board of Public Works approval of
Change Order No. 1 for the subject project. Refer to Inter-Office
Memorandum and attachments for change order details for additional scope
and quantity adjustments for overruns and underruns.
For Change Orders Only
Amount of Increase
Decrease
$ 120,499.45
($ )
Previous Amount $ 3,326,371.59
Current Percent of Change:
Increase
Decrease
3.62%
( %)
New Amount $ 3,446,871.04
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount: 0 Days