HomeMy WebLinkAboutReject Bid & Re-Advertise - South Well Field WTP Improvements - Bid Package 2 Div A Proj No 117-059A - R Yoder
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BREANA N. MICOU
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
May 8, 2025
Mr. Jason Yoder
R. Yoder Construction, Inc.
27453 CR 150
Nappanee, IN 46550
shelly@ryoderconstruction.com
RE: Rejection of Bids – South Well Field Water Treatment Plant and Distribution System
Improvements – Bid Package 2 – Division A – Project No. 117-059A
Dear Mr. Yoder:
At its May 8, 2025 meeting, the Board of Public Works approved the rejection of all bids
for the above referenced project, due to incomplete bid received.
This project will be advertised at a later date. Thank you for bidding, and we hope you
bid with us in the future.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/hh
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIV. OF ENGINEERING & DIV. OF WATER
TO: Members of the Board of Public Works
Michael Schmidt, Assistant City Attorney Public Works
Theresa Heffner, Clerk of the Board of Public Works
FROM: Jacob M. Klosinski, P.E., Assistant City Engineer
SUBJECT: Agenda Req. – Reject Bid Package #2 Division A Bid (Non-responsive)
Agenda Req. – Request to Re-Advertise Bid Package #2 Division A
South Well Field, Water Treatment Plant, and Distribution System
Improvements – Bid Package 2 Division A
Project No. 117-059A / DFO PROJ00000082
DATE: May 1, 2025
The Board of Public Works received public bids for the subject project at its Regular Meeting on
April 22, 2025. The Department of Public Works, Division of Engineering and Division of Water
Works reviewed the bids for Project No. 117-059A South Well Field, Water Treatment Plant,
and Distribution System Improvements – Bid Package 2, Division A.
The four bids Ranked as follows:
BIDDER BASE BID
DIVISION A
R. Yoder Construction (Nappanee, IN)Incomplete Bid
C&E Excavating (Elkhart, IN)No Bid
HRP Construction, Inc. (South Bend, IN) No Bid
Selge Construction Co., Inc. (Niles, MI) No Bid
Bid Opening Notes:
R.Yoder Construction’s Bid Package 2 receipt was acknowledged at the Board Meeting. No
pricing information was clearly provided during the Bid Opening except on an M/WBE Form that
listed a bid price amount of $5,159,605.00. Upon the Division of Engineering’s review of the Bid
Package 2 documents and contacting by R. Yoder Construction via telephone, it was
determined that R. Yoder Construction’s Bid Package 2 was incomplete and non-responsive.
R.Yoder confirmed via telephone that they did not included the correct pricing or attachments
for Bid Package #2 Division A and noted that the bid price included on the M/WBE form was
intended for Bid Package #1.
Recommendations:
Reject Bid(s) for Bid Package 2 Division A and
Approval to Re-Advertise Bid Package 2 Division A
The Department of Public Works, Division of Engineering, and Division of Water Works
reviewed the pricing for Bid Package 1, Bid Package 2 Division A and Bid Package 2
Division B.
Upon assessment, Public Works recommends the Board of Public Works reject the lone bid
for Bid Package #2 Division A.
Bid Package 1 and Bid Package 2 Division B remain under consideration since four of the
contractors that bid on either Bid Package 1 or Bid Package 2 Division B submitted
complete bids. The direction of the project is dependent on review of a complete bidder
submission and price for Bid Package 2 Division A.
The Division of Engineering and Division of Water Works are prepared to re-bid Bid
Package 2 Division A with the following Bid Schedule:
May 9, 2025: First Re-advertisement
May 16, 2025: Second Re-advertisement
May 20, 2025: Pre-Bid Meeting
June 10, 2025: Bid Opening at Board of Public Works Meeting.
We recommend the Board of Public Works consideration to take action to reject the Bid
Package 2 Division A bid(s) at the May 8, 2025, Board of Public Works Agenda Review
Session and approve the request to re-advertise Bid Package 2 Division A with the above
bidding schedule.
For questions regarding the subject Agenda Request or project scope of work, contact
Jacob M. Klosinski (Ext. 9496) at the Division of Engineering.
May 8, 2025
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 05-01-2025
Name: Jacob M. Klosinski Department of Public Works – Engineering Division
BPW Date: 05-08-2025 *Agenda Session* Phone Extension: Ext. 9496
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Michael Schmidt
Dept. Attorney Attorney Name Michael Schmidt
Purchasing Mickey Lovy / Ron O'Connor
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name
South Well Field, Water Treatment Plant, and Distribution System
Improvements – Bid Package #2 Division A
Project Number 117-059A / DFO PROJ00000082
Funding Source Southside TIF and Water Capital Fund
Account No. PR/PO #
Amount
Terms of Contract
Special Contract Provisions
Purpose/Description The Division of Engineering & Division of Water recommends the Board of
Board of Public Works reject the lone non-responsive quote for Bid Package
#2 Division A. Please note that Bid Package #1 and Bid Package #2 Division
B are still under consideration. We are requesting action at the May 8, 2025
Agenda Session to re-advertise Bid Package #2 Division A. See Memo.
For Change Orders Only
Amount of Increase
Decrease
$
($ )
Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: