HomeMy WebLinkAboutChange Order No.1 & Final - High St Sidewalk Improvements Proj No 123-012 - Milestone Contractors LP1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/235-9251
FAx 574/235-9171
CITY OF SOUTH BEND TAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
February 25, 2025
Mr. Kevin Cleek
Milestone Contractors, L.P.
24358 State Road 23
South Bend, IN 46614
kcleek(a,milestonelp. com
RE: Change Order No. 1 (Final) — High Street Sidewalk Improvements — Project No. 123-
012
Dear Mr. Cleek:
At its February 25, 2025 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $2,480.11, bringing the revised contract amount to
$219,810.11.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/hh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BREANA N. MIcou
sours a
CITY OF SOUTH BEND, INDIANA°�
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER x 1865 X
DATE: 10/26/2024
PROJECT NO: 123-012
PROJECT NAME: High St Sidewalk Improvements
CONTRACT DATE: 5/9/2024
CHANGE ORDER NO: 1 (Final)
SUBJECT OF CHANGE ORDER: PCR #1-Second church approach and curb turnouts
All items completed substantially as planned.
See attached Comparison of Estimate for overruns and underruns.
The original contract sum $ 217,330.00
Net change by previously authorized change orders $ 0.00
The contract sum prior to this change order $ 217,330.00
By this Change Order, the project amount is X❑ Increased
❑ Decreased $ 2,480.11
The new contract sum including this change order $ 219,810.11
This Change Order represents a total change of 1.14 %
Total change for entire project 1.14 %
Original contracted completion date/time
Extension of date/time by previous change orders
Date/time extension by this change order
New completion date/time
CONTRACTOR
Aors Z- ria_�
Contractor Signature
Kevin L. Cleek
Printed Name and Title
Milestone Contractors, L.P.
Company Name
24358 SR 23
Address
South Bend, IN
City, State, Zip
10/26/2024
0 days
0 days
10/26/2024
RECOMMENDED FOR APPROVAL
CONSTRUCTION MANAGER
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
1laa
Elizabeth A. Maradik, President
Gary A. Gilot, Member
Murray L. Miller, Member
�
Joseph R. Molnar, Vice President
Breana Micou, Member
Attest: Theresa M. Heffner, Clerk
Date: February 25, 2025
City of South Bend Project No. 123-012 Change Order #1 10/26/2024
HIGH ST SIDEWALK IMPROVEMENTS
Line Item
Qty
Unit
Price
Total
Notes
Second Church Approach
1
EA
$9,681.50
$9,681.50
SECOND APPROACH FOR CHURCH WAS MISSED ON ORIGINAL BUDGET
CURB TURNOUTS
1
EA
$2,335.08
$2,335.08
CURB TURNOUTS WERE MISSED ON ORIGINAL BUDGET ADDED TO CURB AND GUTTER.
FOUR TURNOUTS AT $765/EA
CONCRETE UNDER -RUNS
1
LS
-$2,283.30
-$2,283.30
UNDER ON SIDEWALK AND ADA RAMP
AGGREGATE UNDER -RUNS
1
LS
-$901.09
-$901.09
UNDER ON 53s
LANDSCAPING UNDER -RUNS
1
LS
-$3,504.50
-$3,504.50
UNDER ON SOD
EXCAVATION UNDER -RUNS
1 1
LS
-$2,547.58
-$2,547.58
1 UNDER FOR NOT NEEDING TO TEAR UP ROADWAY FOR ADA PATH
INLET PROTECTION UNDER -RUNS
1 1
LS
-$300.00
-$300.00
1 ONLY NEEDED TO PROTECT TWO INLETS INSTEAD OF THREE
CO Total = $2,480.11
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 2/18/2025
Name: Leslie Biek, Assistant City Engineer Department of Public Works — Engineering Division
BPW Date: 2/25/2025 Phone Extension: 9323
Required Prior to Submittal to Board
Diversity Compliance ® Officer Name
and Inclusion Officer
BPW Attorney ® Attorney Name
Dept. Attorney ® Attorney Name
Purchasing ❑
Check the Appropriate Item Type — Required. for All Submissions
❑ Professional Services Agreement ❑ Contract ❑ Proposal
❑ Open Market Contract ❑ Amendment/Addendum ❑ Special Purchase, QPA
❑ Bid Opening ❑ Bid Award ❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening ❑ Quote Award ❑ Reject Bids/Quotes
❑ Proposal Opening ❑ C/O & PCA No. ❑ PCA
® Chg. Order, No. ❑ Traffic Control ❑ Resolution
n Other: ❑ Ease./Encroach
Company or Vendor Name
New Vendor
MBE/WBE Contractor
Project Name
Project Number
Funding Source
Account No.
Amount
Terms of Contract
Special Contract Provisions
Purpose/Description
Information
❑ Yes[:] If Yes, Approved by Purchasing
❑ No
❑ WBE Completed E-Verify Form Attached Yes
❑ No
High Street Sidewalk Improvements
123-012; PROJ 410
South Side Redevelopment Area TIF
PO # 32149
For Change Orders Only
Amount of ® Increase $ 2,480.11
❑ Decrease ($ )
Previous Amount $ 217,330.00
Increase 1.14%
Current Percent of Change
New Amount
Decrease ( %)
$ 219,810.11
Increase 1.14%
Total Percent of Change: Decrease
Time Extension Amount:
New Completion Date: