HomeMy WebLinkAboutChange Order No. 2 - Cleveland Rd & Ameritech Dr. Improvements Proj No 122-049 - Milestone Contractors ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BREANA N. MICOU 1316 COUNTY-CITY BUILDING 227 W. JEFFERSON BOULEVARD SOUTH BEND, INDIANA 46601-1830 PHONE 574/ 235-9251 FAX 574/ 235-9171 CITY OF SOUTH BEND JAMES MUELLER, MAYOR BOARD OF PUBLIC WORKS December 10, 2024 Mr. Kevin Cleek Milestone Contractors North, Inc, 24358 State Road 23 South Bend, IN 46614 kcleek@milestonelp.com RE: Change Order No. 2 – Cleveland Rd. & Ameritech Dr. Intersection Improvements – Project No. 122-049 Dear Mr. Cleek: At its December 10, 2024 meeting, the Board of Public Works approved the above referenced Change Order be increased by $31,488.59, bringing the revised contract amount to $1,463,270.49. Enclosed is a copy of the Change Order for your records. If you have any further questions, please call this office at (574) 235-9251. Sincerely, /s/ Theresa Heffner Theresa Heffner, Clerk Enclosures TH/hh INTER-OFFICE MEMORANDUM DEPARTMENT OF PUBLIC WORKS DIVISION OF ENGINEERING TO: Theresa Heffner, Clerk Board of Public Works FROM: Scott Kreeger, Senior Project Engineer SUBJECT: Change Order #2 - Project No. 122-049 Cleveland Road & Ameritech Drive Intersection Improvements DATE: December 2, 2024 Change Order #2 includes the restoration and widening of Dylan and Brick Rd curb edge to accommodate the increased truck traffic. Please see attachments for more details. CITY OF SOUTH BEND, INDIANA DEPARTMENT OF PUBLIC WORKS PROJECT CHANGE ORDER DATE: PROJECT NO: PROJECT NAME: CONTRACT DATE: CHANGE ORDER NO: SUBJECT OF CHANGE ORDER: CONTRACTOR RECOMMENDED FOR APPROVAL CONSTRUCTION MANAGER CITY OF SOUTH BEND BOARD OF PUBLIC WORKS 11/18/2024 122-049 Cleveland Road & Ameritech Drive Intersection Improvements 11/1/2023 2 PCR #5-Overruns and Underruns PCR #6-Remaining CO Items The original contract sum $ 1,281,000.00 Net change by previously authorized change orders $ 150,781.90 The contract sum prior to this change order $ 1,431,781.90 By this Change Order, the project amount is X Increased 31,488.59Decreased $ The new contract sum including this change order $ 1,463,270.49 This Change Order represents a total change of 2.20 % Total change for entire project 14.23 % Original contracted completion date/time 7/26/2024 Extension of date/time by previous change orders 0 days Date/time extension by this change order 0 days New completion date/time 7/26/2024 Contractor Signature Printed Name and Title Approved Date: Milestone Contractors North, INC. Company Name 24358 SR 23 Address South Bend, IN 46614 City, State, Zip Elizabeth A. Maradik, President Joseph R. Molnar, Vice President Gary A. Gilot, Member Murray L. Miller, Member Kevin Cleek Project Manager December 10, 2024 112-049 Change Order #2 Date Description QTY Unit Total SUBTOTAL $45,655.94 Final Underruns $ (14,167.35) FINAL CO TOTAL $31,488.59 Associated File 7/24/2024 HMA Patching Shoulder (Brick and Ameritech) 30.66 SYD $115.00 Added HMA shoulder repair at Brick and Ameritech.pdf 7/24/2024 Communication Lid Replacement Communication lid replacement.pdf 10/23/2024 Mobilization (Airmarking, Brick Rd)1 EA $2,864.50 $2,864.50 Added line striping on Brick and Dylan (Airmarking)10/23/2024 Solid Yellow (Airmarking, Brick Rd)900 lft $0.58 $522.00 10/23/2024 Solid White (Airmarking, Brick Rd)1170 lft $0.58 $678.60 10/23/2024 Stop Bar (Airmarking, Brick Rd)30 lft $8.63 $258.90 10/23/2024 Restocking Fee for trench drain Restocking Fee for Trench Drain.pdf 8/26/2024 Mobilization (NEW)1 EA $2,800.00 $2,800.00 Dylan PRICE FOR RE INSTALL WIDENING.pdf 8/26/2024 #4 Excavation, Common 37 CYS $46.30 $1,713.10 8/26/2024 #9 HMA Surface, PG70-22P, 9.5 mm, Type C 10.0 TON $320.00 $3,200.00 8/26/2024 #11 HMA Base, PG 64-22, 25.0mm, Type C 40.5 TON $144.00 $5,832.00 8/26/2024 #23 Curb, Concrete 135 LFT $98.00 $13,230.00 8/26/2024 #25 Topsoil 6.7 CYS $470.00 $3,149.00 8/26/2024 #53 Curb Remove 98 LFT $50.00 $4,900.00 10/18/2024 NEW Seed Mobilization $450.00 $450.00 10/18/2024 NEW Mulched Seeding 60 SYS $7.25 $435.00 $3,525.90 1 EA $1,108.24 $1,108.24 1 EA $988.70 $988.70 1 EA BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date 11/26/2024 Name Scott Kreeger Department Public Works BPW Date 12/10/2024 Phone Extension 9245 Required Prior to Submittal to Board BPW Attorney Attorney Name Michael Schmidt Dept. Attorney Attorney Name Purchasing Mickey Lovy Check the Appropriate Item Type – Required for All Submissions Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA Chg. Order, No. 2 Traffic Control Resolution Other: Ease./Encroach Required Information Company or Vendor Name Milestone Contractors North, Inc. New Vendor Yes If Yes, Approved by Purchasing No MBE/WBE Contractor MBE WBE Completed E-Verify Form Attached Yes No Project Name Cleveland Rd and Ameritech Dr Intersection Improvements Project Number 122-049 Funding Source Local Roads/Bridge Account No. 265-06-600-506-436008 Amount $31,488.59 Terms of Contract Purpose/Description Change Order #2 – Additional should restoration at Dylan & Brick For Change Orders Only Amount of Increase Decrease $ 31,488.59 ($ ) Previous Amount $ 1,431,781.90 Current Percent of Change: Increase Decrease 2.2% ( %) New Amount $ 1,463,270.49 Total Percent of Change: Increase Decrease 14.23% ( %) Time Extension Amount: New Completion Date: