October 8, 2024
Mr. Joseph Gozelski
The MRD Group, Inc.
4777 W. Lincoln Ave.
West Milwaukee, WI 53219
gozelski@themrdgroup.net
RE: Change Order No. 1 – South Bend Medical Foundation Demolition – Project No. 123-
076
Dear Mr. Gozelski:
At its October 8, 2024 meeting, the Board of Public Works approved the above
referenced Change Order be increased by $39,562.50, bringing the revised contract amount to
$1,802,562.50 with an additional thirty (30) days and with a new completion date of January 19,
2025.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/hh
October 8, 2024
Page 1 of 1
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk Board of Public Works
FROM: Zach Hurst, PE, Sr. Project Engineer
SUBJECT: Change Order No. 1 - Project No. 123-076
Demolition of South Bend Medical Foundation
DATE: 09/30/2024 During the course of decommissioning the South Bend Medical Foundation to be prepared for demolition, additional costs were incurred for asbestos removal and universal waste disposal. The contract includes a $100,000 allowance for these specific items, but that limit was exceeded. The cost breakdown is as follows:
• Additional Asbestos Removal (unforeseen): $38,940.00 o This includes wall mastic that was hidden during the original asbestos survey and uncovered once wall coverings were removed.
• Additional Asbestos Removal (unforeseen): $13,172.50 o This includes transite panels that were hidden during the original asbestos survey and uncovered after removing exterior siding.
• Universal Waste Removal (anticipated cost): $74,250.00
o This includes removal of all universal waste found in the building: computers, batteries, monitors, fluorescent lights, mercury-containing equipment.
• Waste Oil / Sludge Removal (anticipated cost): $13,200.00 o This includes removal of all waste oil and sludge found in diesel tanks on the site.
• Total of all added costs: $139,562.50
• Apply existing $100k allowance: ($100,000)
• This change order: $39,562.50
BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM
Date 09/30/2024
Name Zach Hurst Department DPW
BPW Date 10/08/2024 Phone Extension 3057
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer Officer Name
BPW Attorney Attorney Name
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 1 Traffic Control Resolution Other: Ease./Encroach
Required Information
Company or Vendor Name The MRD Group
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE WBE Completed E-Verify Form Attached Yes No Project Name Demolition of South Bend Medical Foundation (531 N. Main St.)
Project Number 123-076
Funding Source River West DA TIF
Account No. PO-00031911
Amount This change: $39,562.50; Revised Amt.: $1,802,562.50
Terms of Contract Lump Sum
Purpose/Description Change Order No. 1 addresses unforeseen asbestos removal and universal
waste disposal.
For Change Orders Only
Amount of Increase Decrease
$ 39,562.50
($ ) Previous Amount $ 1,763,000
Current Percent of Change:
Increase
Decrease
2.2%
( %)
New Amount $ 1,802,562.50
Total Percent of Change:
Increase
Decrease
2.2%
( %)
Time Extension Amount: 30 days New Completion Date: 1/19/2025