CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
September 10, 2024
Mr. Jacob Kwilasz
Rieth-Riley Construction Co., Inc.
25200 State Road 23
South Bend, Indiana 46614
hgritton@rieth-riley.com
RE: Award Bid – Walker Field Connectivity – Project No. 123-058
Dear Mr. Kwilasz:
At its September 10, 2024 meeting, the Board of Public Works awarded the above
referenced bid to you in the amount of $1,357,388.00. Base Bid Plus Alternate 1 & 2. Enclosed
please find a signed Bid/Proposal form.
Please forward the following documents in one submittal by September 24, 2024 to my
attention for Board of Public Works approval at hhorvath@southbendin.gov:
1) One (1) signed original of the Public Works Contract (enclosed)
2) Labor & Material Payment Bond
3) Performance Bond (125% of Bid Amount)
4) Certificate of Insurance naming the City of South Bend as an additional insured
5) Item #4 for all subcontractors that you use
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/hh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BRIANA N. MICOU
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
September 10, 2024
Mr. Lynn Bauer
Milestone Contractors, L.P.
24358 State Road 23
South Bend, Indiana 46614
akrueger@milestonelp.com
RE: Bid Award – Walker Field Connectivity – Project No. 123-058
Dear Mr. Bauer:
At its September 10, 2024, meeting, the Board of Public Works awarded the above
referenced bid to Rieth-Riley Construction Co., Inc. in the amount of $1,357,388.00.
Thank you for bidding, and we hope you bid with us in the future.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/hh
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk Board of Public Works
FROM: Becca Plantz, PE, Assistant City Engineer
SUBJECT: Award Project No. 123-058
Walker Field Park Connectivity
DATE: August 30, 2024
On August 27, 2024, the Board of Public Works opened and read bids for the above project. I have reviewed them and found them correct.
The bidders are summarized as follows:
Bidder Bid Amount Alternative 1 Alternative 2 Alternative 3 Base + Alt 1 + Alt 2
Rieth-Riley
Construction Co., Inc. $1,232,056.00 $64,340.00 $60,992.00 $78,864.00 $1,357,388.00
Milestone Contractors North, Inc. $1,134,800.00 $119,800.00 $106,400.00 $48,700.00 $1,361,000.00
All bids met or exceeded the MWBE goals. MBE Goal: 2.92% WBE Goal: 5.04%
I recommend award of a contract for the base bid, alternate 1, and alternate 2 for the Walker
Field Park Connectivity project to the lowest responsive / responsible bidder, Rieth-Riley Construction Co., Inc. in the amount of $1,357,388.00.
Sufficient funds have been appropriated from Fund 456 (DFO PROJ 455).
Please call with your questions 5998.
Enc. Bid Tabulation
Pay Item Description Units Quantity Unit Price Total Unit Price Total
MOBILIZATION AND DEMOBILIZATION LS 1 $69,968.48 $69,968.48 $65,000.00 $65,000.00
CLEARING RIGHT-OF-WAY LS 1 $17,301.97 $17,301.97 $45,000.00 $45,000.00
PAVEMENT REMOVAL SYS 1,545 $33.24 $51,355.80 $14.90 $23,020.50
CURB, CONCRETE, REMOVE LFT 1,648 $19.91 $32,811.68 $11.30 $18,622.40
SIDEWALK CONCRETE, REMOVE SYS 311 $45.76 $14,231.36 $30.20 $9,392.20
INLET, REMOVE EACH 5 $889.37 $4,446.85 $930.00 $4,650.00
EXCAVATION, COMMON CYS 785 $57.28 $44,964.80 $37.50 $29,437.50
BORROW CYS 598 $72.48 $43,343.04 $45.00 $26,910.00
STORMWATER EROSION AND SEDIMENT CONTROL LS 1 $12,445.93 $12,445.93 $14,346.15 $14,346.15
SUBGRADE TREATMENT, TYPE II SYS 1,868 $30.83 $57,590.44 $22.00 $41,096.00
STRUCTURE BACKFILL, TYPE 2 CYS 255 $35.61 $9,080.55 $83.50 $21,292.50
COMPACTED AGGREGATE, NO. 53 CYS 84 $138.40 $11,625.60 $169.00 $14,196.00
DENSE GRADED SUBBASE CYS 313 $118.38 $37,052.94 $120.00 $37,560.00
MILLING, ASPHALT, 1 1/2 IN. SYS 2,110 $5.84 $12,322.40 $3.80 $8,018.00
MILLING, APPROACH SYS 237 $10.10 $2,393.70 $11.90 $2,820.30
QC/QA-HMA, 3, 58H, SURFACE, 9.5 mm TON 173 $136.41 $23,598.93 $127.00 $21,971.00
JOINT ADHESIVE, SURFACE LFT 2,136 $0.78 $1,666.08 $0.40 $854.40
LIQUID ASPHALT SEALANT LFT 2,136 $0.30 $640.80 $0.30 $640.80
HMA WEDGE AND LEVEL, TYPE B TON 19 $414.89 $7,882.91 $125.00 $2,375.00
ASPHALT FOR TACK COAT TON 1 $719.17 $719.17 $1,450.00 $1,450.00
SIDEWALK, CONCRETE SYS 1,495 $63.78 $95,351.10 $74.90 $111,975.50
CURB RAMP, CONCRETE SYS 112 $215.49 $24,134.88 $140.00 $15,680.00
DETECTABLE WARNING SURFACES SYS 22 $172.88 $3,803.36 $250.00 $5,500.00
CURB, CONCRETE LFT 605 $37.44 $22,651.20 $57.00 $34,485.00
CURB AND GUTTER, COMBINED LFT 1,421 $30.09 $42,757.89 $49.70 $70,623.70
HMA FOR APPROACHES, TYPE B TON 18 $259.52 $4,671.36 $227.00 $4,086.00
PCCP FOR APPROACHES, 6 IN. SYS 29 $112.71 $3,268.59 $144.00 $4,176.00
SODDING, NURSERY SYS 3,167 $11.93 $37,782.31 $7.40 $23,435.80
FIELD OFFICE, TYPE C MOS 6 $7,918.18 $47,509.08 $750.00 $4,500.00
PIPE, TYPE 2, CIRCULAR, DIAMETER 12 IN. LFT 563 $102.80 $57,876.40 $65.00 $36,595.00
HMA FOR STRUCTURE INSTALLATION, TYPE B TON 86 $174.57 $15,013.02 $129.00 $11,094.00
VIDEO INSPECTION FOR PIPE LFT 563 $4.45 $2,505.35 $2.50 $1,407.50
GEOTEXTILE FOR PIPE TYPE 2B SYS 644 $3.68 $2,369.92 $2.90 $1,867.60
ADJUST WATER VALVE TO GRADE EACH 8 $768.71 $6,149.68 $100.00 $800.00
CASTING, MANHOLE, ADJUST TO GRADE EACH 2 $768.72 $1,537.44 $250.00 $500.00
INLET, TYPE J10 EACH 3 $4,273.18 $12,819.54 $5,000.00 $15,000.00
INLET, TYPE M10 EACH 6 $4,956.62 $29,739.72 $5,700.00 $34,200.00
MANHOLE, TYPE C4 EACH 1 $6,132.11 $6,132.11 $12,200.00 $12,200.00
MAINTAINING TRAFFIC LS 1 $6,296.00 $6,296.00 $6,296.00 $6,296.00
SIGN, SHEET, RELOCATE EACH 1 $210.00 $210.00 $210.00 $210.00
SOLAR POWERED FLASHING BEACON ASSEMBLY EACH 2 $9,600.00 $19,200.00 $9,600.00 $19,200.00
TRANSVERSE MARKING, THERMOPLASTIC, CROSSWALK LINE, WHITE, 24 IN. LFT 250 $15.00 $3,750.00 $8.95 $2,237.50
PAVEMENT MESSAGE MARKING EACH 6 $2,500.00 $15,000.00 $300.00 $1,800.00
LINE, THERMOPLASTIC, SOLID, WHITE, 24 IN. LFT 108 $15.00 $1,620.00 $8.95 $966.60
LINE, THERMOPLASTIC, SOLID, WHITE, 6 IN. LFT 1,457 $2.50 $3,642.50 $1.35 $1,966.95
LINE, THERMOPLASTIC, SOLID, YELLOW, 6 IN. LFT 1,464 $2.50 $3,660.00 $1.35 $1,976.40
TRANSVERSE MARKING, THERMOPLASTIC, CROSSHATCH LINE, WHITE, 12 IN. LFT 450 $10.00 $4,500.00 $4.95 $2,227.50
SPEED TABLE EACH 3 $18,878.83 $56,636.49 $18,000.00 $54,000.00
TREE PROTECTION LFT 984 $6.32 $6,218.88 $9.80 $9,643.20
CONCRETE TRAIL + NODE SYS 334 $143.32 $47,868.88 $116.50 $38,911.00
BENCH EACH 2 $4,122.32 $8,244.64 $3,000.00 $6,000.00
PARK SIGN LS 1 $27,118.25 $27,118.25 $16,979.00 $16,979.00
TRAIL MAP SIGN LS 1 $13,640.61 $13,640.61 $8,953.00 $8,953.00
CONCRTE STAIRS & SIDE WALL LS 1 $61,191.44 $61,191.44 $57,500.00 $57,500.00
STAIR RAILING LFT 49 $515.00 $25,235.00 $515.00 $25,235.00
LIMESTONE BIKE CHANNEL CF 9 $460.00 $4,140.00 $1,420.00 $12,780.00
CONCRETE RETAINING WALL (86 LFT x 2.5' H) LS 1 $34,038.63 $34,038.63 $71,800.00 $71,800.00
STREET TREE (1.5-2") EACH 9 $575.00 $5,175.00 $675.00 $6,075.00
PLANTING SOIL CYS 158 $81.35 $12,853.30 $80.00 $12,640.00
HARDWOOD SHREDDED BARK MULCH CYS 3 $100.00 $300.00 $208.00 $624.00
$1,232,056.00 $1,134,800.00
Rieth-Riley Construction Co.,
Inc.
Base Bid Total
Milestone Contractors, L.P.
Base Bid
City of South Bend
Walker Field Park Connectivity
Bid Tabulation
Bid Opening: 08/27/2024 just after 9:00 am Local Time
Pay Item Description Units Quantity Unit Price Total Unit Price Total
Raised Concrete Intersection - Walnut LS 1 $64,340.00 $64,340.00 $119,800.00 $119,800.00
$64,340.00 $119,800.00
Pay Item Description Units Quantity Unit Price Total Unit Price Total
Raised Concrete Intersection - Webster LS 1 $60,992.00 $60,992.00 $106,400.00 $106,400.00
$60,992.00 $106,400.00
Pay Item Description Units Quantity Unit Price Total Unit Price Total
Tennis Court Removal and Restoration LS 1 $78,864.00 $78,864.00 $48,700.00 $48,700.00
$78,864.00 $48,700.00
$1,232,056.00 $1,134,800.00
$204,196.00 $274,900.00
$1,436,252.00 $1,409,700.00
Certified By: _______________________________
Date: August 30, 2024
Bid Alternate #3 Total
Bid Altnerate #2 Total
Bid Alternate #1 Total
Total Base Bid
Total of Alternates #1-3
Total Base Bid + All Alternates
Rieth-Riley Construction Co.,
Inc.
25200 State Road 23
South Bend, IN 46614
Yes
Yes
Yes
Yes
Yes
DBE/MBE GOALS
BID FOR PUBLIC WORK - FORM 96
BID BOND (5% OF TOTAL BID AMOUNT)
BIDDER CHECKLIST
ADDENDUM ACKNOWLEDGEMENT
574-288-8321
Jacob K. Kwilasz
CONTRACTOR CONTACT INFORMATION
Bid Alternate #3
Yes
Bid Alternate #1
Yes
574-288-4811
Yes
Yes
Yes
Bid Alternate #2
Lynn J. Bauer
South Bend, IN 46614
Milestone Contractors, L.P.
24358 SR 23
September 10, 2024
BOARD OF PUBLIC WORKS CITY OF SOUTH BEND, INDIANA
PUBLIC WORKS CONTRACT
This Agreement is made and entered into this 10th Day of September 2024, by and between Rieth-Riley Construction Co., Inc., (the “Contractor”), and the Board of Public Works (the "Board”).
The Contractor covenants and agrees to make the following improvement, as fully set out in the
Request for Quotations, Standard Specifications, Special Provisions, Plans, and Bid Proposals, all of which are set forth as a part of this Contract, for:
PROJECT NO. 123-058
DESCRIPTION: WALKER FIELD CONNECTIVITY
COMPLETION DATE: SEE SPECIFICATIONS AMOUNT: $1,357,388.00 FUNDING: PR-00034877
The unit prices for this improvement were those prices as received and accepted by the Board on
the 10th Day of September 2024.
The Contractor further agrees to notify the assigned Engineer when this improvement is completed. This notification shall be in the form of a Project Completion Affidavit, signed by the
Contractor. Upon final acceptance of the improvement by the Engineer, the Contractor’s final
estimate will be presented to the Board for final Payment with one (1) copy of the Project Completion Affidavit and one (1) copy of a Waiver of Lien.
Each of the Parties, by signing below, represents and warrants to the other Party that he/she/it has
the authority to bind the named person or entity to this Agreement.
BOARD OF PUBLIC WORKS REITH-RILEY CONSTRUCTION CO., INC.
President Member Printed Name
Member Member Signature
Member Attest: Clerk
September 10, 2024
BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM
Date 08/30/2024
Name Becca Plantz Department Public Works
BPW Date 09/10/2024 Phone Extension 5998
Review and Approval Required Prior to Submittal to Board
Diversity Compliance
and Inclusion Officer Officer Name
BPW Attorney Attorney Name Michael Schmidt
Dept. Attorney Attorney Name
Purchasing Mickey Lovy
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA
Chg. Order, No. Traffic Control Resolution Other: Ease./Encroach
Required Information
Company or Vendor Name Rieth-Riley Construction Co., Inc.
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE WBE Completed E-Verify Form Attached Yes No Project Name Walker Field Park Connectivity
Project Number 123-058
Funding Source PROJ-455
Account No. 456-10-101-121-444000
Amount $1,357,388.00
Terms of Contract Unit prices and lump sums
Purpose/Description A traffic calming and pedestrian connectivity project on Ewing Avenue by
Walker Field and Rum Village Parks.
For Change Orders Only
Amount of Increase Decrease
$
($ ) Previous Amount $
Current Percent of Change:
Increase
Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount: New Completion Date: