September 10, 2024
Ms. Jessica Clark
Lochmueller Group, Inc.
112 West Jefferson Blvd., Suite 500
South Bend, Indiana 46601
jclark@lockgroup.com
RE: Amendment No. 1 to Professional Service Agreement
Dear Ms. Clark:
At its September 10, 2024 meeting, the Board of Public Works approved the above
referenced amendment for design of Coal Line Trail Phase 3 to include additional survey work
in the amount of $11,626.00.
Enclosed please find the original of the amendment for your signature. Please sign and
return the original amendment to hhorvath@southbendin.gov. Please retain a copy for your
records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/hh
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
TO: Board of Public Works
FROM: Gemma Stanton, Project Engineer
SUBJECT: PSA Amendment 1
DATE: 8/30/2024
Attached is a request to amend the PSA for the design of Coal Line Trail Phase 3 with Lochmueller
Group. This amendment is needed to complete a Location Route Control Survey and topographic
survey at intersections along College Street for raised intersection design. The additional cost is
$11,626.00. This increase is eligible for 80% reimbursement from INDOT and we are working to
secure funds from MACOG to cover $9,300.80 with a contribution of $2,325.20. Sufficient funds for
the full amount of the amendment have been appropriated from TIF-River West.
I request the Board of Public Works approve Amendment 1. Thank you for your consideration. Please
call with your questions.
CITY OF SOUTH BEND PAGE 1 OF 3 123-3013-00H
X:\CORPORATE\PRIVATE\ACCOUNTING DATA\CONTRACTS\SOUTH BEND\123-3013-00H COAL LINE TRAIL PHASE 3\SOUTH BEND\AM 1\2024-08-29 AM 1 CITY.DOCX
AMENDMENT NO. 1
THIS AMENDMENT NO. 1 IS MADE AND ENTERED INTO THIS _____ DAY OF ___________, 2024
BY AND BETWEEN CITY OF SOUTH BEND, HEREINAFTER REFERRED TO AS “LPA” AND
LOCHMUELLER GROUP, INC., HEREINAFTER REFERRED TO AS “CONSULTANT”.
WITNESSETH
WHEREAS, LPA and CONSULTANT did on November 28, 2024 enter into a Contract to provide
services for Coal Line Trail, Phase 3, Engineering services and design of a multi-use path and urban
design features., and
WHEREAS, additional surveying is required, and
WHEREAS, LPA desires the CONSULTANT to provide the services, and
WHEREAS, the CONSULTANT has expressed an interest in providing the additional required
services, and
WHEREAS, in order for the CONSULTANT to provide the additional services, it is necessary to
amend the original agreement, and
NOW, THEREFORE, it is agreed by and between both parties that the original Contract be
amended as follows:
I. Section IV Compensation on page 1 or 17 is hereby deleted in its entirety and hereby
replaced in its entirety with the following:
SECTION IV COMPENSATION. The LPA shall pay the CONSULTANT for the Services performed
under this Contract as set forth in Appendix “D” which is herein attached to and made an
integral part of this Contract. The maximum amount payable under this Contract shall not
exceed $361,336.00.
II. Items 1.9 and 1.10 of Appendix “A” are added as follows:
1.9 Perform Location Control Route Survey (LCRS) generally along the centerline of
College Street.
1.10 Perform pick up survey at the side streets on the west side of College Street,
approximately 80' x 50' locations outside of previously surveyed area to provide
data for raised intersection design.
III. Item 1.0 Amount of Payment of Appendix “D” is hereby deleted in its entirety and
hereby replaced in its entirety with the following:
1.0 AMOUNT OF PAYMENT
1.1 The CONSULTANT shall receive compensation for providing such professional
services under Appendix “A” of this Contract in the amount of a total fee not-to-
CITY OF SOUTH BEND PAGE 2 OF 3 123-3013-00H
X:\CORPORATE\PRIVATE\ACCOUNTING DATA\CONTRACTS\SOUTH BEND\123-3013-00H COAL LINE TRAIL PHASE 3\SOUTH BEND\AM 1\2024-08-29 AM 1 CITY.DOCX
exceed Three Hundred Sixty-One Thousand Three Hundred Thirty-Six Dollars
($361,336.00), unless an amendment to this Contract is executed by the parties
that increases the maximum amount payable.
1.2 The CONSULTANT shall be paid for the work performed under Item 1.0, 2.0, 3.0,
4.0, 5.0, 6.0, 7.0, 8.0, and 9.0 of Appendix “A” of this Contract on a lump sum basis,
in accordance with the following lump sum fee schedule:
1.2.1. Topographic Survey Data Collection ........................................... $38,136.00
1.2.2. Urban Trail Design and Plans .................................................... $127,200.00
1.2.3. Decorative Lighting Design ......................................................... $21,600.00
1.2.4. Traffic Signal Design .................................................................... $10,400.00
1.2.5. Project Management .................................................................. $20,000.00
1.2.6. Environmental Documentation .................................................. $65,700.00
1.2.7. Permitting ..................................................................................... $8,900.00
1.2.8. Utility Coordination ..................................................................... $26,400.00
1.3 The CONSULTANT shall be paid for the work performed under Items 10.0 and 12.0
of Appendix “A” of this Contract on an hourly rate basis based on the rates set
forth in Exhibit “1” , attached hereto and incorporated herein by reference and in
accordance with the following not to exceed fee schedule:
1.3.1. Public Involvement ..................................................................... $13,200.00
1.3.2. Construction Phase Services ....................................................... $12,200.00
1.4 The CONSULTANT shall receive payment for Title Search Services performed under
Item 11.0 of Appendix “A” of this Contract based on the specific cost per unit
multiplied by the actual units of work performed in accordance with the following
schedule:
1.4.1. Title Reports (32 parcels @ $550 each) ...................................... $17,600.00
Except as herein modified, changed, and amended, all terms and conditions of the original
Contract dated November 28, 2023 shall continue in full force and effect.
This Amendment No. 1 increases the total fee not-to-exceed of $349,710.00 by $11,626.00 to a
new total fee not-to-exceed amount of $361,336.00.
CITY OF SOUTH BEND PAGE 3 OF 3 123-3013-00H
X:\CORPORATE\PRIVATE\ACCOUNTING DATA\CONTRACTS\SOUTH BEND\123-3013-00H COAL LINE TRAIL PHASE 3\SOUTH BEND\AM 1\2024-08-29 AM 1 CITY.DOCX
IN WITNESS WHEREOF, the parties have hereunto executed this Amendment No. 1 effective the
day and year first above written.
LOCHMUELLER GROUP, INC.
_________________________________
Jessica J. Clark, PE
Regional Leader – Northern Indiana
September 10, 2024
BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM
Date: 8/30/2024
Name: Gemma Stanton Department of Public Works – Engineering Division
BPW Date: September 10th, 2024 Phone Extension: 9083
Required Prior to Submittal to Board
BPW Attorney Attorney Name Michael Schmidt
Dept. Attorney Attorney Name
Purchasing
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA Chg. Order, No. Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Lochmueller Group
New Vendor Yes If Yes, Approved by Purchasing No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No Project Name Coal Line Trail Phase 3
Project Number 123-007 (INDOT DES #2201235)
Funding Source TIF-River West
Account No. 324-431002
Amount $11,626.00
Terms of Contract Lump sum
Purpose/Description Amendment to PSA for design of Coal Line Trail Phase 3 to include additional survey work. Eligible for 80% reimbursement of the PSA amount from INDOT.
For Change Orders Only
Amount of Increase Decrease
$
($ ) Previous Amount $
Current Percent of Change:
Increase Decrease
%
( %)
New Amount $
Total Percent of Change:
Increase
Decrease
%
( %)
Time Extension Amount:
New Completion Date: