HomeMy WebLinkAboutChange Order No 1 - WWTP Compressor Building Masonry Impr. Proj No. 121-046 - Slatile Roofing
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BRIANA N. MICOU
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
July 23, 2024
Mr. Gerald Longerot
Slatile Roofing & Sheet Metal Co., Inc.
1703 S. Ironwood Dr.
South Bend, IN 46613
gerald.longerot@slatile.com; debra.carothers@slatile.com
RE: Change Order No. 1 (Final) – Wastewater Treatment Plant Compressor Building
Masonry Improvements – Project No. 121-046
Dear Mr. Longerot:
At its July 23, 2024 meeting, the Board of Public Works approved the above referenced
Change Order be increased by $95,170, bringing the revised contract amount to $550,770 with
a new completion date of June 30, 2024.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENVIRONMENTAL SERVICES
TO: Members of the Board of Public Works
Michael Schmidt, Assistant City Attorney Public Works
Theresa Heffner, Clerk of the Board of Public Works
FROM: Jacob M. Klosinski, P.E., Assistant City Engineer
SUBJECT: Agenda Request – Change Order No. 1
121-046 WWTP Compressor Building Masonry Improvements
(PROJ00000289 / PR-00018587 / PO-0020775)
DATE: July 19, 2024 (Updated, Explanation of Change Orders above 20% limit)
The Division of Engineering and Division of Wastewater request the Board of Public Works approve
a change order for Project No. 121-046 WWTP Compressor Building Masonry Improvements for
additional work required during construction to address unforeseen conditions and conditions that
could not be identified during design. These conditions included clogged bathroom drain piping,
replacement of steel lintels that were deteriorated due to rust jacking and delamination, fabrication
of a steel plate jamb due to open masonry at a door frame to accommodate installation,
tuckpointing two glass block window sections that had excessively deteriorated joints, and the
replacement of additional brick blocks that were cracked or split that were beyond the original scope
of the project.
Change Order No. 1 consists of the following additions:
PCO#1: Plumbing / Drain Modifications $13,510.00
PCO#2: Lintel Replacement (unit price item) $ 3,800.00
PCO#3: Glass Block Seal and Tuckpoint $ 5,960.00
PCO#4: 2,300 Additional Brick Replacement (unit price item) $80,500.00
PCO#5: North Building Steel Plate Frame for Door $ 1,400.00
TOTAL Change Order No. 1 $105,170.00
Use of $10,000 Owner directed allowance from Base Bid ($10,000.00)
TOTAL Change in Contract Price $ 95,170.00
Original Contract Price: $455,600.00
Change Order No. 1: $ 95,170.00 net increase
New Contract Price with Change Order No. 1: $550,770.00
In addition, the contract completion date is adjusted to June 30, 2024, due to door and door
hardware manufacturer and supplier delays. All work for the project is complete.
Explanation of Exceedance of Change Orders above 20%:
The subject change orders exceeded the 20% change order threshold by $4,050.00 (approximately
0.9%). All change orders required for this project were necessary to complete the project scope of
work to secure the building envelope and address unforeseen conditions that were encountered
during the construction phase that could not have been reasonably foreseen during the design
phase of the project.
PCO#1: Plumbing / Drain Modifications
During construction, the contractor encountered plugged drainpipes that were deteriorated with
interior section loss and leaking and corroded pipe joints that were only visible after the removal of
toilets in the process of installing new toilets. Upon review of the project engineer and architect, it
was determined that the drain issues needed to be addressed immediately to avoid further
deterioration or leaking of municipal sewage into the basement of the Compressor Building.
PCO#2: Lintel Replacement
The condition of steel lintels (steel angle / steel beam above windows and doorways) are often
covered by masonry block infill and or limestone and the level of rusting jacking and corrosion due
to water entering behind the block masonry is not always visible to the architect or engineer during
visual inspection. During construction, limestone lintels were removed, and one lintel was replaced.
Unit pricing was provided with Bid Pricing so that there was a defined cost for each lintel
replacement. Lintels support masonry above windows and doors, and lintel replacement was
necessary to maintain adequate load transfer to the block and foundation below. In the lintel
replacement had been neglected and left in place, mortar joints would have continued to crack
around the window openings and further corrosion would result in rust jacking or “lifting” of the block
around the opening.
PCO#3 Glass Block Seal and Tuckpointing
During a heavy rain event, water was observed seeping through the glass blocks at one of the
Mezzanine Windows and seeping out the brick at the bottom of the glass block openings. After
engineer and architect visual inspection of the second-floor glass block window, it was determined
that the mortar joints between the glass blocks were heavily deteriorated and, in some instances,
had completed eroded away with non-bonded, open joints and fractures. To avoid further water
penetration or damage, the glass block joints needed to be tuckpointed with a softer, more flexible
silicone mortar joint rather than a cementitious mortar joint. This was necessary to help seal the
building envelope of the Mezzanine / Second Floor from water infiltration.
PCO#4 2,300 Additional Brick Replacement
At the time of scoping, the amount of brick replacement in the base bid was 1,000 units. During
construction, additional bricks were determined by the project engineer and architect to be cracked
or broken and required replacement. In some cases, sections of brick had to be removed and rebuilt
resulting in an additional 2,300 bricks that were replaced during the project. The square footage of
walls that were impacted by microcracking and broken bricks were much higher than originally
expected. With the contractor mobilized and scaffolding in place, neglecting the broken brick
replacement work would have resulted in additional costs. With unit pricing available, project
engineer and architect determined that it was in the best interest of the City to address the brick
replacement work through the Unit Pricing provided for the project. It is worth noting that unit pricing
received for additional brick replacement work was the same between the contractors that provided
bids for the project.
PCO#5: North Building Steel Plate Frame for Door
During the removal of an older steel double-leaf door for the Storage Room Addition at the
Compressor Building, the brick was uncovered to be hollow beyond the door jamb. As a result, the
jamb fasteners for the new door did not have a solid block for the jamb fasteners to anchor the door
jamb frame. The project engineer and architect determined that a fabricated steel jamb plate would
be the least expensive alternative to provide a solid connection point for the door jamb frame.
The result of the combined change orders exceeded the 20% change order threshold by $4,050.00.
Engineering determined that this overage was a reasonable amount given the scope of work
required to secure the building envelope and address unforeseen conditions.
Had Engineering opted to re-bid or re-quote this work, the additional staff hours, design contract
fees, time lost, and construction cost to re-mobilize a contractor on-site to complete the work would
have exceeded the additional costs required to complete the change order work under this contract.
Funding for this project was provided through Sewage Works Capital – Wastewater Capital,
Account 642-06-605-514-442005. For questions regarding the subject Agenda Request,
contact Jacob M. Klosinski (Ext. 9496) at the Division of Engineering.
Jacob M. Klosinski 07-12-2024
July 23, 2024
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date: 07-15-2024
Name: Jacob M. Klosinski Department of Public Works – Engineering Division
BPW Date: 07-23-2024 Phone Extension: 9496
Required Prior to Submittal to Board
BPW Attorney X Attorney Name Michael Schmidt
Dept. Attorney Attorney Name Michael Schmidt
Purchasing Mickey Lovy / Ron O'Connor
Check the Appropriate Item Type –Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 001 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Slatile Roofing and Sheet Metal Co., Inc. (V-00001513)
)New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name WWTP Compressor Building Masonry Improvements
Project Number 121-046 / PROJ00000289 / PR-00018587 / PO-0020775
Funding Source Sewage Works – Wastewater Capital
Account No. 642-06-605-514-442005 Sewage Works Capital
Amount See below
Terms of Contract Base Bid + Unit Prices
Special Contract Provisions
Purpose/Description Engineering recommends the Board of Public Works approve Change Order
No. 1. Work included plumbing drain improvements, lintels, glass block tuck
pointing, masonry brick replacements, and door jamb plate fabrication due to
unforeseen conditions and engineer’s assessment of necessary repairs. This
request includes the use of the $10,000 owner directed allowance and
approval of the balance of funds for the change order.
For Change Orders Only
Amount of
Increase
Decrease
$ 95,170.00
($ )
Previous Amount $ 0.00
Current Percent of Change:
Increase
Decrease
20.9%
(%)
New Amount $ 550,770.00
Total Percent of Change:
Increase
Decrease
20.9%
(%)
Time Extension Amount: Date adjusted to 06-30-2024 (Manufacturer delay: doors and hardware)
New Completion Date: 06-30-2024