HomeMy WebLinkAboutChange Order No 1 - Cleveland Rd & Ameritech Dr Intersection Improv. Proj No. 122-049 - Milestone
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BRIANA N. MICOU
1316 COUNTY-CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/ 235-9251
FAX 574/ 235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
July 23, 2024
Mr. Kevin L. Cleek
Milestone Contractors North, Inc
24358 SR 23
South Bend, IN 46614
akrueger@milestonelp.com
RE: Change Order No. 1 – Cleveland Road & Ameritech Dr. Intersection Improvements
Project No. 122-049
Dear Mr. Cleek:
At its July 23, 2024 meeting, the Board of Public Works approved the above referenced
Change Order be increased by $150,781.90, bringing the revised contract amount to
$1,431,781.90.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
CITY OF SOUTH BEND, INDIANA
DEPARTMENT OF PUBLIC WORKS
PROJECT CHANGE ORDER
DATE:6/21/2024
PROJECT NO:112-049
PROJECT NAME:Cleveland Road & Ameritech Drive Intersection Improvements
CONTRACT DATE:11/1/2023
CHANGE ORDER NO:1
SUBJECT OF CHANGE ORDER:PCR #1-Tree stump removal PCR #2-Upgrade traffic controller PCR
#3-Install Gridsmart Camera System PCR #4-Brick Road
Improvements
The original contract sum $ 1,281,000.00
Net change by previously authorized change orders $0.00
The contract sum prior to this change order $ 1,281,000.00
By this Change Order, the project amount is X Increased
150,781.90Decreased $
The new contract sum including this change order $ 1,431,781.90
This Change Order represents a total change of 11.77 %
Total change for entire project 11.77 %
Original contracted completion date/time 7/26/2024
Extension of date/time by previous change orders 0 days
Date/time extension by this change order 0 days
New completion date/time 7/26/2024
CONTRACTOR RECOMMENDED FOR APPROVAL
Contractor Signature CONSTRUCTION MANAGER
CITY OF SOUTH BEND
Printed Name and Title BOARD OF PUBLIC WORKS
Approved Date:
Milestone Contractors North, INC.
Company Name
Elizabeth A. Maradik, President
24358 SR 23
Address
Breana N. Micou, Member
South Bend, IN 46614
City, State, Zip
Joseph R. Molnar, Member
Gary A. Gilot, Member
Murray L. Miller, Member
Kevin Cleek Project Manager
July 23, 2024
INTER-OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
DIVISION OF ENGINEERING
TO: Theresa Heffner, Clerk
Board of Public Works
FROM: Scott Kreeger, Senior Project Engineer
SUBJECT: Change Order #1 - Project No. 122-049
Cleveland Road & Ameritech Drive Intersection Improvements
DATE: June 25, 2024
At the start of construction, it was discovered the vertical alignment of Brick Road onto
Cleveland Road was not adequate to allow trucks with low beds to properly maneuver
onto Cleveland Road. Since the original scope of the project was to expand the edges
of the roadway, it was determined the best course of action would be to fully reconstruct
the road and properly match the grades.
Additional work included the removal of a stump along Brick Road and the replacement
of a TS2 cabinet.
Please see attachments for more details.
Project No:
Date Requested:Date Submitted:
Description of Work:Install 5' shoulder with asphalt millings on Brick Rd. between drives at intersection of Dylan Dr.
Reason for Extra Work:Per COSB.
Has Work Already Been Completed?yes When:22-Apr-24 THROUGH 22-Apr-24
MCLP Project No.239720 Cost Activity Code:
Item:Quantity:???Units ??
Added 5 ' shoulder 1.00 LS 4,325.00$
-$ -$
Total $4,325.00
Unit Price
Extra Days Requested -
5/1/2024
Change Order Request
Milestone Contractors, L.P.
4/17/2024
Ameritech and Cleveland
99950-801
TM2024 NORTH South Bend April 1 2024 to March 31 2025 Page 1
Project No:
Date Requested:Date Submitted:
Description of Work:Install Gridsmart camera Supplied by City of South Bend
Reason for Extra Work:Per Burke Engineering
Has Work Already Been Completed?No When:THROUGH
MCLP Project No.239720 Cost Activity Code:
Item:Quantity:???Units ??
Gridsmart Camera install 1.00 LS 5,136.15$
-$ -$
Total $5,136.15
Unit Price
Extra Days Requested -
4/11/2024
Change Order Request
Milestone Contractors, L.P.
3/27/2024
Ameritech and Cleveland
TM2024 NORTH South Bend April 1 2024 to March 31 2025 Page 1
Biditem Description Quantity Units Unit Price Bid Total
1
8,712.009.90SYS880.000MILL ASPH, 1-1/2 in. @ BRICK & DYLAN100
23,635.00163.00TON145.000HMA 9.5mm SURF(PG 70-22P) @ BRICK & DYLA101
10,760.85132.85SYS81.000PCCP DRIVE, 6 in.102
$43,107.85========>Bid Total
04/15/2024
BID TOTALS
COSB Cleveland & Ameritech Dr. CO
Project No:
Date Requested:Date Submitted:
Description of Work:Remove tree stump on Brick RD
Reason for Extra Work:Per Burke Engineering.
Has Work Already Been Completed?No When:THROUGH
MCLP Project No.239108 Cost Activity Code:
Item:Quantity:Units
Remove tree stump 1.00 LS 2,706.00$
-$ 2,706.00$
Total $2,706.00 0
Unit Price
Extra Days Requested -
3/14/2024
Change Order Request
Milestone Contractors, L.P.
3/5/2024
238720
Tree stump removal quote Page 1
Project No:
Date Requested:Date Submitted:
Description of Work:Upgrade trffic controller to a TS2 in existing cabinet.
Reason for Extra Work:Per Burke Engineering
Has Work Already Been Completed?No When:THROUGH
MCLP Project No.239720 Cost Activity Code:
Item:Quantity:Units
Upgraded traffic controller 1.00 LS 4,715.00$
-$
Total $4,715.00
Unit Price
Extra Days Requested -
3/14/2024
Change Order Request
Milestone Contractors, L.P.
3/5/2024
239720
Upgraded traffic controller Page 1
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 7/2/2024
Name Scott Kreeger
Department Public
Works
BPW Date 7/23/24 Phone Extension 9245
Required Prior to Submittal to Board BPW Attorney Attorney Name Michael Schmidt
Dept. Attorney Attorney Name
Purchasing Mikey Lovy
Check the Appropriate Item Type – Required for All Submissions
Professional Services Agreement Contract Proposal
Open Market Contract Amendment/Addendum Special Purchase, QPA
Bid Opening Bid Award Req. to Advertise Title Sheet
Quote Opening Quote Award Reject Bids/Quotes
Proposal Opening C/O & PCA No. PCA
Chg. Order, No. 1 Traffic Control Resolution
Other: Ease./Encroach
Required Information
Company or Vendor Name Milestone Contractors North, Inc.
New Vendor Yes If Yes, Approved by Purchasing
No
MBE/WBE Contractor MBE
WBE Completed E-Verify Form Attached Yes
No
Project Name Cleveland Rd and Ameritech Dr Intersection Improvements
Project Number 122-049
Funding Source Local Roads/Bridge, Local Streets Traffic Maint.
Account No. 265-436008, 251-06-600-506-436010
Amount $150,781.90
Terms of Contract
Purpose/Description _Change Order#1 – Tree stump removal, Brick Road Reconstruction,
Installation of Gridsmart
For Change Orders Only
Amount of
Increase
Decrease
$ 150,781.90
($ )
Previous Amount $ 1,281,000
Current Percent of Change:
Increase
Decrease
11.77%
( %)
New Amount $ 1,431,781.90
Total Percent of Change:
Increase
Decrease
11.77%
( %)
Time Extension Amount:
New Completion Date: