HomeMy WebLinkAboutAmendment No 2 to PSA - WWTP Hydraulic & Clarifier Proj No. 119-069 – Arcadis US Inc. ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BRIANA N. MICOU 1316 COUNTY-CITY BUILDING 227 W. JEFFERSON BOULEVARD SOUTH BEND, INDIANA 46601-1830 PHONE 574/ 235-9251 FAX 574/ 235-9171 CITY OF SOUTH BEND JAMES MUELLER, MAYOR BOARD OF PUBLIC WORKS July 9, 2024 Ms. Amy E. Smitley, PE Arcadis U.S., Inc. 150 W. Market St., Suite 728 Indianapolis, IN 46204 Amy.smitley@arcadis.com RE: Amendment No. 1 to Professional Services Agreement Dear Ms. Smitley: At its July 9, 2024 meeting, the Board of Public Works approved the above referenced amendment to develop engineering plans for the hydraulic improvements at the Wastewater Treatment Plant, upsizing the secondary clarifier and the primary effluent channel expansion, Project No. 119-069 in the amount of $130,220. Enclosed please find a copy of the amendment for your records. If you have any further questions, please call this office at (574) 235-9251. Sincerely, /s/ Theresa Heffner Theresa Heffner, Clerk Enclosures TH/lh BOARD OF PUBLIC WORKS AGENDA ITEM REVIEW REQUEST FORM Date: 07-01-2024 Name: Jacob M. Klosinski Department of Public Works – Engineering Division BPW Date: 07-09-2024 Phone Extension: 9496 Required Prior to Submittal to Board BPW Attorney X Attorney Name Michael Schmidt Dept. Attorney Attorney Name Michael Schmidt Purchasing Mickey Lovy / Ron O'Connor Check the Appropriate Item Type –Required for All Submissions Professional Services Agreement Contract Proposal Open Market Contract Amendment/Addendum Special Purchase, QPA Bid Opening Bid Award Req. to Advertise Title Sheet Quote Opening Quote Award Reject Bids/Quotes Proposal Opening C/O & PCA No. PCA Chg. Order, No. Traffic Control Resolution Other: Ease./Encroach Required Information Company or Vendor Name Arcadis US Inc (V-00000135) New Vendor Yes If Yes, Approved by Purchasing No MBE/WBE Contractor MBE WBE Completed E-Verify Form Attached Yes No Project Name WWTP Secondary and Disinfection Improvements Project Number 119-069 (PO-0000413) Funding Source Wastewater Capital Account No. Fund 642 Amount $130,220 Terms of Contract Lum Sum Fee (Task List included Amendment No. 2, attached) Special Contract Provisions Purpose/Description The Division of Engineering and Wastewater requests the Board of Public Works approval of Amendment No. 2 to a professional services agreement with Arcadis US Inc to develop engineering plans for hydraulic improvements at the Wastewater Treatment Plant, upsizing Secondary Clarifier influent piping and Primary effluent channel expansion (Long Term Control Plan improvement). For Change Orders Only Amount of Increase Decrease $ ($ ) Previous Amount $ Current Percent of Change: Increase Decrease % (%) New Amount $ Total Percent of Change: Increase Decrease % (%) Time Extension Amount: New Completion Date: INTER-OFFICE MEMORANDUM DEPARTMENT OF PUBLIC WORKS DIVISION OF ENGINEERING TO: Members of the Board of Public Works Michael Schmidt, Assistant City Attorney Public Works Theresa Heffner, Clerk of Board of Public Works FROM: Jacob M. Klosinski, P.E., Assistant City Engineer SUBJECT: Agenda Request – Amendment to Professional Services Agreement 119-069 WWTP Secondary and Disinfection Improvements Amendment No. 2 (PO-0000413) DATE: July 1, 2024 The Division of Engineering and Division of Wastewater request the Board of Public Works approval of an Amendment to a Professional Services Agreement with Arcadis US, Inc. for additional engineering services related to hydraulic improvements at the Wastewater Treatment Plant. Project Background In conjunction with Long Term Control Plan and Consent Decree objectives as well as the hydraulic analysis from the 2013 Wastewater Treatment Plant Facilities Plan, the scope of work for this Amendment addresses Primary Clarifier and Secondary Treatment hydraulic improvements to convey 100 MGD wet weather flows through Secondary Treatment. Item 1: Primary Clarifier Effluent Channel Improvements This work includes the expansion of the effluent channel Parshall flumes and removes an existing, non-functional flow meter that has created a restriction in the Primary effluent piping. Item 2: Upsizing Secondary Clarifier Influent Pipe to Final Clarifier 6 & Final Clarifier 7 This work includes the replacement of a 66-inch diameter pipe with an 84-inch diameter pipe as well as structural improvements to junction chambers to carry flow from the Final Clarifier Influent Channel at the Aeration Gallery to Final Clarifier 6 and Final Clarifier 7. The contract amounts will change as follows: Original agreement amount: $793,770.00 Net change for prior amendments: $175,100.00 Amendment No. 2 amount: $130,200.00 Adjusted agreement amount: $1,099,090.00 This project is funded through Wastewater Capital Account: 641-06-605-514-431002. For questions regarding the subject agenda request, contact Jacob M. Klosinski, P.E. (Ext. 9496) at the Division of Engineering. https://arcadiso365.sharepoint.com/teams/SouthBendWWTPSecondaryDisinfectionImprovements/Shared Documents/PM/Amendment 2/SB WWTP Hydraulic Improvements_Amendment No. 2 Ltr.docx Arcadis U.S., Inc. 150 W. Market Street Suite 728 Indianapolis Indiana 46204 Tel 317 231 6500 Fax 317 231 6514 www.arcadis.com Page: 1/1 Jacob Klosinski Assistant City Engineer City of South Bend 1316 County-City Building 227 West Jefferson Boulevard South Bend, IN 46601 Subject: Project 119-069 WWTP Secondary and Disinfection Improvements Amendment No. 2, Hydraulic Improvements Design and CA Dear Jacob: Enclosed are signed copies of Amendment No. 2 for Professional Services associated with the additional design and construction administration (CA) engineering services for WWTP Hydraulic Improvements, as part of the 119-069 WWTP Secondary and Disinfection Improvements project. If the Amendment is acceptable to the Board, please return one fully executed copy for our files. Sincerely, Arcadis U.S., Inc. Amy Smitley, PE Ben Burroughs, PE Vice President Project Manager Date: July 8, 2024 Contact: Ben Burroughs Phone: 317-236-2839 Email: benjamin.burroughs@arcadis.com STANDARD AGREEMENT FOR PROFESSIONAL SERVICES Page 1 of 7 Between City of South Bend and ARCADIS U.S., Inc. Project Number: 30029091 AMENDMENT No. 2 119-069 WWTP Secondary and Disinfection Improvements Amendment No. 2 An Agreement was executed on July 23, 2019 between the City of South Bend, Indiana [Client], having its principal place of business at 1316 County-City Building, 227 West Jefferson Boulevard, South Bend, Indiana 46601, and Arcadis U.S., Inc. [Arcadis], having its principal place of business at 630 Plaza Drive, Highlands Ranch, Colorado 80129 and having an office at 55 Monument Circle, Suite 300B, Indianapolis, Indiana 46204. Under the Agreement, Arcadis provides certain professional engineering services related to design, bid and construction administration engineering services for Final Clarifier Nos. 1 through 5 rehabilitation, Aeration Tank Nos. 1 through 4 modifications and effluent disinfection chemical expansion. Client and Arcadis now desire to amend the Agreement to include the amended Services as described below. In consideration of the mutual promises in the Agreement, Client and Arcadis agree to amend the Agreement as the following: 1.Schedule A-1,Scope of Amended Services. 2.Schedule B-1,Compensation for Amended Services. Other Provisions. Except as amended herein, all other provisions, terms and conditions in the Agreement shall remain in full force and effect. Execution Authority. This Amendment to the Agreement is a valid and authorized undertaking of Client and Arcadis. The representatives of Client and Arcadis who have signed below have been authorized to do so. IN WITNESS WHEREOF, the parties hereto have made and executed this Amendment to the Agreement as of this date: _______________, 2024. CITY OF SOUTH BEND Arcadis U.S., Inc. By: ___________________________________ Title: Vice President July 9, July 9, 2024 STANDARD AGREEMENT FOR PROFESSIONAL SERVICES Page 2 of 7 Between City of South Bend and ARCADIS U.S., Inc. Project Number: 30029091 AMENDMENT No. 2 119-069 WWTP Secondary and Disinfection Improvements Amendment No. 2 Schedule A-1 Scope of Amended Services and Related Matters ENGINEERING SERVICES BY ARCADIS WWTP Hydraulic Improvements. The City of South Bend desires to continue its efforts to rehabilitate, modify and expand the WWTP to work towards achieving the CSO Long-Term Control Plan requirement, which requires an increase in the peak wet weather capacity from 77 MGD to 100 MGD. The South Bend WWTP is a Class IV activated sludge treatment facility required to provide preliminary treatment, primary and secondary treatment, phosphorous removal, and disinfection throughout all seasons. The NPDES permit lists a rated average flow of 48 MGD and a rated peak flow of 77 MGD. The plant’s current average flow is approximately 36 MGD and it can treat a peak flow up to 77 MGD. Liquid treatment processes include screening, grit removal, raw sewage pumping, primary treatment, activated sludge, final clarifiers, and chlorination / dechlorination. Sludge treatment processes include gravity thickening of primary sludge, dissolved air floatation thickening of waste activated sludge, two- stage anaerobic digestion, and belt filter press dewatering. Class B biosolids are reused by land application on farmland. As part of Arcadis’ prior planning projects, a hydraulic model was created for the plant and used to model different flow conditions through each process at the plant to achieve the plant’s future 100 MGD peak flow requirement as part of the CSO Long-Term Control Plan. The hydraulic model was calibrated using recorded plant flows and water surface elevations around the plant. Limiting hydraulic elements, also called bottlenecks, were identified and analyzed further under peak flow and other hydraulic conditions. The City has addressed all bottlenecks except two major areas require hydraulic improvements at the WWTP to achieve the future 100 MGD flow: (1) Primary Effluent and (2) Final Clarifier Nos. 6 and 7 Influent, as further described below. In addition, there are abandoned structures within these areas that may be demolished. Primary Effluent Hydraulic Improvements. The preliminary and primary treatment process consists of the headworks facility (screening, grit removal), raw sewage pumping and the primary clarifiers. After the plant flow leaves the headworks, the raw sewage pumps (located in the Compressor Building) pump flow into the primary influent channel which discharges into eight primary clarifiers. The flow from each individual primary clarifier goes into a common primary effluent conduit and the common primary effluent conduit is a hydraulic bottleneck. The primary clarifier effluent conduit restricts flow leaving the primary clarifiers such that at flows equal to or greater than approximately 65 MGD, the primary clarifier effluent flumes are submerged. At 100 MGD flow, the model predicts that this bottleneck results in no freeboard in the primary clarifiers. Modifying the effluent conduit and primary clarifier effluent Parshall flumes would alleviate this bottleneck. The abandoned in place 48-inch primary effluent meter has also been identified as a hydraulic bottleneck in the primary effluent piping. The following is proposed to alleviate the primary effluent bottleneck. A new open channel located parallel to the existing primary effluent conduit along Primary Clarifier Nos. 1 through 4 only, north of the Primary Scum Building, and utilizing the abandoned east-west bypass channel located above the primary effluent conduit is recommended. The new channel and the existing conduit will flow into the existing east-west conduit and into the re-utilized abandoned bypass channel. Flow from the bypass channel will flow into the primary effluent structure, similar to the existing primary effluent conduit, by removing the bypass channel gates and demolishing a portion of the primary effluent structure wall. With all primary clarifiers in service (with a return sludge flow of 72 MGD and all other tanks in service), these improvements will un- submerge the weirs up to 80 MGD and the flumes up to 100 MGD and provide approximately 12-inches of freeboard in the primary clarifiers up to 100 MGD. The abandoned in place 48-inch primary effluent meter and 48”x72” reducers will be replaced with 72-inch pipe. Final Clarifier Nos. 6 and 7 Influent Hydraulic Improvements. The Final Clarifier Nos. 6 and 7 influent pipe was identified as another plant hydraulic bottleneck. The 60-inch pipe located between the south end of the Final Clarifier Influent Channel and Junction Box NT1 that feeds Final Clarifier Nos. 6 and 7 is the source of the hydraulic bottleneck under peak flow conditions. At the current peak capacity of 77 MGD and at the FEMA 100-year flood elevation, the 60- inch pipe has inadequate flow capacity and can cause flow overtopping upstream within the plant. This pipe segment has been modeled to show inadequate capacity at the future peak flow of 100 MGD under normal river conditions. Replacing the existing 60-inch pipe with a larger size pipe would alleviate this hydraulic bottleneck. As part of the prior planning, upsizing the existing 60-inch pipe in the segment indicated above to 84-inch pipe is recommended. However, another alternative for consideration is instead to provide a new channel from the south end of the Final Clarifier Influent Channel to Junction Box NT1 or potentially to Junction Box NT. This would require channel mixing. The benefits include STANDARD AGREEMENT FOR PROFESSIONAL SERVICES Page 3 of 7 Between City of South Bend and ARCADIS U.S., Inc. Project Number: 30029091 AMENDMENT No. 2 119-069 WWTP Secondary and Disinfection Improvements Amendment No. 2 less dewatering during construction and an open channel for visual inspection. The pipe and channel alternatives for this segment will be evaluated at a high-level. Miscellaneous Demolition Near Hydraulic Improvements. An abandoned concrete pad east of the primary clarifiers and north of the Primary Scum Building will be demolished. The existing Parshall flumes will be evaluated during preliminary design if modification of the flumes is cost effective when the primary effluent hydraulic improvements are constructed. Arcadis will prepare design drawings and specifications as a supplement to the Final Clarifier Nos. 1-3 Improvements project, which is being delivered through a Guaranteed Savings Contract between the City and Bowen Engineering. The City will coordinate with Bowen Engineering to provide associated construction cost estimates for this project. Arcadis will also perform construction administration services. The City will perform construction inspection. A SharePoint site will be established for use during design. The scope of engineering services shall include the following: 1. Project Management. Provide project management including scope, budget and schedule control; project coordination; maintenance of records; project setup, invoicing, and close-out. 2. Kick-off and Design Review Meetings. Meet with the City to kick-off the project including a site visit to perform initial above-ground field investigations. Meet in-person with the City monthly to share progress, resolve outstanding items, perform additional field needs, and review deliverables and design progress for 60% and final designs. In addition to these in-person meetings, up to four conference calls are included. 3. Survey. A survey may be required during design for key spot elevations. Any survey will be provided via subcontract services. A $5,000 allowance, currently not included in the fee pricing, shall be added if survey is needed. 4. Basis of Design. Conduct a preliminary design including the following tasks. a. During the kick-off meeting, inspect the abandoned primary effluent channel from the surface to determine structural rehabilitation needs of the channel for future use. b. Confirm hydraulics to determine extent of hydraulic improvements. c. Confirm structural needs including rehabilitation for all areas. d. Obtain manufacturers’ cut sheets including materials of construction, cost quotes, delivery schedules, and dimensions from vendors for piping and equipment. e. Develop preliminary requirements for construction phasing and for coordination with Owner’s operations including allowable pipe/tank shutdowns and scheduling. f. Perform a constructability review of the design at this time. g. Develop preliminary engineer’s opinion of probable construction costs. h. Prepare preliminary drawings and major equipment specifications. i. Summarize the above tasks in a Basis of Design Meeting. 5. Construction Drawings. Prepare detailed drawings to supplement the Final Clarifier Nos. 1-3 Improvements drawings to show the general scope, extent and character of the work to be furnished and performed by Contractor. The plans will show civil piping configuration and layout, structural components and detail. Record drawings will be recreated in AutoCAD for use as the base sheets. 6. Specifications. Prepare specifications to supplement the Final Clarifier Nos. 1-3 Improvements project manual. The technical specifications will be prepared in conformance with the fifty-division format of the Construction Specifications Institute. 7. Industrial Treatment Evaluation. Arcadis evaluated digestion alternatives for providing treatment to a potential industrial user’s discharge that was proposing to discharge high loads of BOD to the South Bend WWTP. Alternative evaluations included: (1) evaluating the treatment capacity of the existing processes at the South Bend WWTP to treat higher BOD loads and (2) sizing and providing a high-level construction cost estimates of a remote digester facility to treat proposed BOD loads from a new industrial discharger. 8. Construction Schedule. Prepare construction schedule establishing advertisement dates, bid opening, notice-to-proceed, and critical milestone dates for each design deliverable. 9. Guaranteed Maximum Price Assistance. Assist the City in reviewing the guaranteed maximum price. Upon successful completion of the design phase, the following construction services apply. STANDARD AGREEMENT FOR PROFESSIONAL SERVICES Page 4 of 7 Between City of South Bend and ARCADIS U.S., Inc. Project Number: 30029091 AMENDMENT No. 2 119-069 WWTP Secondary and Disinfection Improvements Amendment No. 2 10. General Administration of Construction Contract. Consult with Owner and act as Owner’s representative as provided in the Construction Contract. The extent and limitations of the duties, responsibilities, and authority of Engineer as assigned in the Construction Contract shall not be modified, except as Engineer may otherwise agree in writing. All of Owner’s instructions to Contractor will be issued through Engineer, which shall have authority to act on behalf of Owner in dealings with Contractor to the extent provided in this Agreement and the Construction Contract except as otherwise provided in writing. 11. Pre-Construction Conference. Participate in a Pre-Construction Conference prior to commencement of Work at the Site. The conference will be attended by Engineer. 12. Schedules. Receive, review, and determine the acceptability of schedules that Contractor is required to submit to Engineer, including the Progress Schedule, Schedule of Submittals, and Schedule of Values. 13. Visits to Site and Observation of Construction. In connection with observations of Contractor’s Work while it is in progress: • Make visits to the Site at intervals appropriate to the various stages of construction, as Engineer deems necessary, to observe as an experienced and qualified design professional the progress of Contractor’s executed Work. Such visits and observations by Engineer are not intended to be exhaustive or to extend to every aspect of Contractor’s Work in progress or to involve detailed inspections of Contractor’s Work in progress beyond the responsibilities specifically assigned to Engineer in this Agreement and the Contract Documents, but rather are to be limited to spot checking, selective sampling, and similar methods of general observation of the Work based on Engineer’s exercise of professional judgment, as assisted by the Owner’s Resident Project Representative. Based on information obtained during such visits and observations, Engineer will determine in general if the Work is proceeding in accordance with the Contract Documents, and Engineer shall keep Owner informed of the progress of the Work. Engineer will visit the Site on the same day of each construction progress meeting. The scope of these engineering services is based on up to 10 months of construction progress meetings. • The purpose of Engineer’s visits to the Site will be to enable Engineer to better carry out the duties and responsibilities assigned to and undertaken by Engineer during the Construction Phase, and, in addition, by the exercise of Engineer’s efforts as an experienced and qualified design professional, to provide for Owner a greater degree of confidence that the completed Work will conform in general to the Contract Documents and that Contractor has implemented and maintained the integrity of the design concept of the completed Project as a functioning whole as indicated in the Contract Documents. Engineer shall not, during such visits or as a result of such observations of Contractor’s Work in progress, supervise, direct, or have control over Contractor’s Work, nor shall Engineer have authority over or responsibility for the means, methods, techniques, sequences, or procedures of construction selected or used by Contractor, for security or safety at the Site, for safety precautions and programs incident to Contractor’s Work, nor for any failure of Contractor to comply with Laws and Regulations applicable to Contractor’s furnishing and performing the Work. Accordingly, Engineer neither guarantees the performance of any Contractor nor assumes responsibility for any Contractor’s failure to furnish or perform the Work in accordance with the Contract Documents. 14. Defective Work. Reject Work if, on the basis of Engineer’s observations, Engineer believes that such Work (a) is defective under the standards set forth in the Contract Documents, (b) will not produce a completed Project that conforms to the Contract Documents, or (c) will imperil the integrity of the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. 15. Clarifications and Interpretations; Field Orders. Issue necessary clarifications and interpretations of the Contract Documents as appropriate to the orderly completion of Contractor’s work. Such clarifications and interpretations will be consistent with the intent of and reasonably inferable from the Contract Documents. Subject to any limitations in the Contract Documents, Engineer may issue field orders authorizing minor variations in the Work from the requirements of the Contract Documents. Coordinate a tracking log for clarifications and interpretations as part of the electronic data information system developed by Engineer. 16. Change Orders and Work Change Directives. Recommend change orders and work change directives to Owner, as appropriate, and prepare change orders and work change directives as required. 17. Shop Drawings and Samples. Review and approve or take other appropriate action in respect to Shop Drawings and Samples and other data which Contractor is required to submit, but only for conformance with the information given in the Contract Documents and compatibility with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. Such reviews and approvals or other action will not extend to means, methods, techniques, sequences, or procedures of construction or to safety precautions and programs incident thereto. Engineer shall meet any Contractor’s submittal schedule that Engineer has accepted. Coordinate a tracking log for submittals as STANDARD AGREEMENT FOR PROFESSIONAL SERVICES Page 5 of 7 Between City of South Bend and ARCADIS U.S., Inc. Project Number: 30029091 AMENDMENT No. 2 119-069 WWTP Secondary and Disinfection Improvements Amendment No. 2 part of the electronic data information system developed by Engineer. 18. Substitutes and “or-equal” Requests. Review the Contractor’s requests for product substitutions and “or equal”; Engineer will separately track the time and expense required for such reviews and invoice the Client for such reviews as Additional Services. 19. Inspections and Tests. The Owner’s Resident Project Representative will require such special inspections or tests of Contractor’s work as deemed reasonably necessary, and receive and review all certificates of inspections, tests, and approvals required by Laws and Regulations or the Contract Documents. Any review by Engineer of such certificates will be for the purpose of determining that the results certified indicate compliance with the Contract Documents and will not constitute an independent evaluation that the content or procedures of such inspections, tests, or approvals comply with the requirements of the Contract Documents. Engineer shall be entitled to rely on the results of such tests. 20. Change Proposals and Claims. (a) Review and respond to Change Proposals. Review each duly submitted Change Proposal from Contractor and, within 30 days after receipt of the Contractor’s supporting data, either deny the Change Proposal in whole, approve it in whole, or deny it in part and approve it in part. Such actions shall be in writing, with a copy provided to Owner and Contractor. If the Change Proposal does not involve the design (as set forth in the Drawings, Specifications, or otherwise), the acceptability of the Work, or other engineering or technical matters, then Engineer will notify the parties that the Engineer will not resolve the Change Proposal. (b) Provide information or data to Owner regarding engineering or technical matters pertaining to Claims. 21. Contractor’s Completion Documents. Receive, review, and transmit to Owner maintenance and operating instructions, schedules, guarantees, bonds, certificates or other evidence of insurance required by the Contract Documents, certificates of inspection, tests and approvals, Shop Drawings, Samples and other data approved, and transmit the annotated record documents which are to be assembled by Contractor in accordance with the Contract Documents to obtain final payment. 22. Substantial Completion. Promptly after notice from Contractor that Contractor considers the entire Work ready for its intended use, in company with Owner and Contractor, visit the Project to determine if the Work is substantially complete. If after considering any objections of Owner, Engineer considers the Work substantially complete, Engineer shall deliver a certificate of Substantial Completion to Owner and Contractor. 22. Record Drawings. Prepare Record Drawings showing appropriate record information based on Project annotated record documents received from Contractor and furnishing such Record Drawings to Owner. A hard copy (full size drawings) and electronic copy (in AutoCAD and pdf file format) will be submitted to the Owner. AutoCAD version shall be based on the Owner’s standards. 23. Final Notice of Acceptability of the Work. Conduct a final visit to the Project to determine if the completed Work of Contractor is acceptable so that Engineer may recommend, in writing, final payment to Contractor. Accompanying the recommendation for final payment, Engineer shall also provide a notice in the form attached hereto as Exhibit E (the “Notice of Acceptability of Work”) that the Work is acceptable to the best of Engineer’s knowledge, information, and belief and based on the extent of the services provided by Engineer under this Agreement. The scope of these engineering services is based on the final visit conducted during the regular progress meeting. DELIVERABLES This project includes the following deliverables. 1. Preliminary (60%) Design. This submittal includes documents that communicate the results of the preliminary design and establishes the scope of the construction work.  Preliminary drawings showing layouts  Preliminary construction phasing  Technical specifications  Preliminary construction schedule 2. Final Design Submittal. This submittal includes documents that communicate the detailed design approach and intent of all disciplines.  Design drawings showing required demolitions, layouts, structural details as a supplement to the Final Clarifier 1-3 Improvement Drawings  Project specifications: technical specifications as a supplement to the Final Clarifier 1-3 Improvement Project Manual STANDARD AGREEMENT FOR PROFESSIONAL SERVICES Page 6 of 7 Between City of South Bend and ARCADIS U.S., Inc. Project Number: 30029091 AMENDMENT No. 2 119-069 WWTP Secondary and Disinfection Improvements Amendment No. 2  Opinion of probable construction cost  Preliminary construction schedule  One electronic copy (pdf, searchable format) Schedule Arcadis is prepared to begin work immediately upon written authorization to proceed, which is anticipated to be no later than July 2024. Design services shall be completed in sufficient time for the City to get a GMP from the guaranteed savings provider and within three months from notice-to-proceed. This assumes the City will provide comments on design deliverables within two weeks. It is anticipated construction will be completed within a 10-month period. STANDARD AGREEMENT FOR PROFESSIONAL SERVICES Page 7 of 7 Between City of South Bend and ARCADIS U.S., Inc. Project Number: 30029091 AMENDMENT No. 2 119-069 WWTP Secondary and Disinfection Improvements Amendment No. 2 Schedule B-1 Amended Pricing Schedule The estimated budget for services under this Amendment No. 2 is indicated below and as estimated in the attached table. The overall limit of compensation under this Agreement is as follows: Original Agreement $793,770 Amendment No. 1 $175,100 Amendment No. 2 $130,220 Overall Limit of Compensation $1,099,090 Hourly rates for services performed for this amended scope of work are as follows: Category Hourly Rate Project/Program Director $313 Principal Engineer/Scientist/Architect II $286 Principal Engineer/Scientist/Architect I $254 Senior Engineer/Scientist/Architect II $196 Senior Engineer/ Scientist/Architect I $180 Project Engineer/ Scientist/Architect $170 Staff Engineer/Scientist/Architect $159 Engineer/Scientist $138 Technician/Project Assistant IV $170 Technician/Project Assistant III $142 Technician/Project Assistant II $127 Technician/Project Assistant I $117 Design Tech / Field Technician $71 Amy Smitley(Technical Advisor)John Huston (QAQC)Ben Burroughs(Project Manager)Brett Schnur(Engineer)Joe Bartos(Engineer)Matt Hemmelgarn(Structural Engineer)Matt Palte(Structural Engineer)CAD DrafterShelly Baxter(Assistant)SubconsultantTOTAL LABOR TASK DESCRIPTION HOURS COST EXPENSES TOTAL PM Project Management 4 16 26 46 7,980 7,980 1. Basis of Design 4 2 18 24 8 16 4 40 116 14,680 400 15,080 2. 60% Design 8 2 28 76 16 28 8 80 246 30,620 30,620 3. Final Design 8 2 24 40 8 24 8 80 194 22,660 22,660 4. General Construction Administration 4 4 20 40 8 12 8 96 15,980 400 16,380 5. Meetings and Inspections 4 24 16 4 16 64 11,390 982 12,372 6. Submittals 8 24 4 16 4 56 9,230 9,230 7. Record Drawings 2 8 16 8 40 74 6,610 300 6,910 8 Allowance No. 1: Survey Allowance 5,000 5,000 9 Industrial Treatment Evaluations 5 13 18 3,980 3,980 TOTAL ESTIMATED HOURS 37 12 159 236 48 120 24 240 34 910 128,130 HOURLY RATES $286 $196 $196 $138 $196 $159 $254 $29 $142 TOTAL 10,582$ 2,352$ 31,164$ 32,568$ 9,408$ 19,080$ 6,096$ 7,018$ 4,828$ 128,130$ 2,082$ 130,220$ ESTIMATED NOT-TO-EXCEED COMPENSATION:130,220$ Estimated Compensation - ARCADIS U.S., Inc. 07/08/24 CITY OF SOUTH BEND WWTP Hydraulic Improvements Design and Construction Services DIVISION OF ENVIRONMENTAL SERVICES Wastewater Treatment Plant