HomeMy WebLinkAboutChange Order No 6 - Coal Line Trail Phase IIB Proj No. 122-035 - INDOT Milestone1316 COUNTY -CITY BUILDING
227 W. JEFFERSON BOULEVARD
SOUTH BEND, INDIANA 46601-1830
PHONE 574/235-9251
FAx 574/235-9171
CITY OF SOUTH BEND JAMES MUELLER, MAYOR
BOARD OF PUBLIC WORKS
June 11, 2024
Office of LPA and Grant Administration INDOT LaPorte District
Attention: Director of LPA and Grant Administration 315 East Boyd Blvd.
100 North Senate Ave., Room N955-LPA LaPorte, IN 46350
Indianapolis, IN 46204 aholderread(d)indot.in. og_v
cholth&usiconsultant. com
RE: Change Order No. 6 (Final) — Coal Line Trail Phase IIB — Project No. 122-035
Dear Mr. Holth:
At its June 11, 2024 meeting, the Board of Public Works approved the above
referenced Change Order be decreased by $102,370.40, bringing the revised contract amount to
$3,406,165.11.
Enclosed is a copy of the Change Order for your records.
If you have any further questions, please call this office at (574) 235-9251.
Sincerely,
/s/ Theresa Heffner
Theresa Heffner, Clerk
Enclosures
TH/lh
ELIZABETH A. MARADIK JOSEPH R. MOLNAR GARY A. GILOT MURRAY L. MILLER BRIANA N. MIcou
INTER -OFFICE MEMORANDUM
DEPARTMENT OF PUBLIC WORKS
TO: Board of Public Works
FROM: Gemma Stanton, Project Engineer
SUBJECT: Change Order #6
Coal Line Trail Phase IIB
DATE: 6/3/2024
Attached is Change Order 5 for the Coal Line Trail Phase 2B project. The Change Order amount is a
deduct of $-102,370.40.
Original Contract amount: $3,450.217.13
Previously approved change orders: $58,318.38
Percent Decrease Including Requested:-1.277%
New Contract Amount: $3,406,165.11
As this is a federal aid project, INDOT is responsible for the construction contract with Milestone. The
City does not need to appropriate additional funds for this change order.
Please call with your questions. Thank you for your consideration of this request.
Contract No:B -44292 Change Order No.: 006
INDIANA Department of Transportation Page: 1
Construction Change Order and Time Extension Summary
Contract Information Contract No.: B -44292 Letting Date:09/14/2022
District:LAPORTE DISTRICT AE:Hauersperger, Steven PE/S:Holth, Chris Status:Draft
Change Order Information Change Order No.: 006 EWA: N or Force Acct: N
Date Generated: 00/00/0000 Date Approved: 00/00/0000
Reason Code: FINAL QUANTITY ADJUSTMENT
Description: Over/Under Change Order
Original Contract Amount $ 3,450,217.13
Current Change Order Amount $-102,370.40 Percent: -2.967 %
Total Previous Approved Changes $ 58,318.38 Percent: 1.690 %
Total Change To -Date $-44,052.02 Percent: -1.277 %
Modified Contract Amount $ 3,406,165.11
Time Extension Information
Date Initiated 00/00/0000 Date Completed 00/00/0000
Original Contract Time SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SP Date 00/00/0000 or SP Days
(SS = Standard Specification, SP = Special Provision)
Time Element Description:
Current Time Extension
Previous Time Approved
Revised Contract Time
SS Days 0 SP Days 0 SP Days Value $ 0.00
SS Days by AE: DCE: SCE: DDCM:
SS Days
SP Days Value $
SS Completion Date 00/00/0000 or SS Calendar/Work Days 0
SS Date 00/00/0000 or SP Days 0
Contract No:B -44292
INDIANA Department of Transportation
Construction Change Order and Time Extension Summary
Review and Approval Information
Required Approval Authority
($ per Change Order)
(Days per Contract)
Verbal Approval Required?
Total Change To-Date>5%?
Scope/Design Recommendation
Required?
Change Order No.: 006
Page: 2
AE: V DCE: SCE: * DDCM:
(-LE$250K-)(-LE$750K-)(--LE$2M--)(--GT$2M--)
( 50 SS days ) ( 100 SS days) ( 200 SS Days ) ( GT 200 SS days)
®/ N If Y, by S.Hauersperger Date Issued 5/20/24
Y /(E)If Y, Copy to Program Budget Manager.
Y AMIf Y, Referred to Project Manager(PM)
Date to PM Date Returned
Approval Authority Concurs with PM? Q/ N If Y, Concurrence by J.Krueckeberg
LPA Signatures Required?
FHWA Signatures Required?
Date 5/20/24
If N,Resolution: Approved Disapproved
Resolved by
0/ N If Y, Date to LPA 5/22/24
Date
Date Returned
Y /lalf Y, Date to FHWA Date Returned
* Field Engineer Recommendation (Required for SCE or DDCM Approval)
Field Engineer
Comments:
Date
Contract No:B -44292 INDIANA
Change Order No:006 Department of Transportation
Contract: B -44292
Project: 2200199 - State:220019900LC4
Change Order Nbr: 006
Change Order Description: Over/Under Change Order
Reason Code: FINAL QUANTITY ADJUSTMENT
CLN PCN PLN Item Code Unit Unit Price CO Qty Comment
0011 2200199 0011 205-12108 DOL 1.000-30613.850 C
Item Description: STORMWATER MANAGEMENT BUDGET
Supplemental Descriptionl:
Supplemental Description2:
0022 2200199 0022 616-05688 TON 135.000-531.530 C
Item Description: RIPRAP, CLASS 1
Supplemental Descriptionl:
Supplemental Description2:
Date:05/20/2024
Page: 3
Amount Change
Amount:$-30,613.85
Amount:$-71,756.55
Total Value for Change Order 006 = $-102,370.40
Whereas, the Standard Specifications for this contract provides for such work to be performed, the following change is recommended.
General or Standard Change Order Explanation
Item #0011 - This quantity was under due to the two project once being together then getting split into 2 contracts. The budgets were not split
appropriately for this item based on the scope of the project. Item #0022 - This item was underrun due to not needing all of the material. All
material was put in per plan and specification and still had additional material not used.
Change Order Explanation for Specific Line Item
It is the intent of the parties that this change order is full and complete compensation for the work describe above.
Notification and consent to this change order is hereby acknowledged.
Milestone Contractors v �O
Contractor: Signed By:
Date: 5/21/2024
NOTE: Other required State and FHWA signatures will be obtained electronically through the SiteManager system.
Contract No:B -44292 INDIANA
Change Order No:006 Department of Transportation
CITY OF SOUTH BEND, INDIANA
BOARD OF PUBLIC WORKS
tA14 '.�_12M
Elizabeth A. Maradik, President
Gary A. Gilot, Member
7j2w�,
Joseph R. Molnar, Vice President
Briana///Miic�cou, Member
�'V—
Murray L. Miller, Member Attest: Theresa M. Heffner, Clerk
Date: June 11, 2024
PE/S
APPROVED FOR INDIANA DEPARTMENT OF TRANSPORATION
Date:05/20/2024
Page: 4
Approval Level Name of Approver Date Status
BOARD OF PUBLIC WORKS
AGENDA ITEM REVIEW REQUEST FORM
Date 5/31/2024
Name Gemma Stanton Department PW
BPW Date 6/11/2024 Phone Extension 9083
Review and Approval Required Prior to Submittal to Board
Diversity Compliance ❑
Officer Name
and Inclusion Officer
BPW Attorney ❑ Attorney Name
Dept. Attorney ❑
Attorney Name
Purchasing ❑
Ron O'Connor
Check the Appropriate
Item Type — Re uired or All Submissions
❑ Professional Services Agreement
❑ Contract
❑ Proposal
❑ Open Market Contract
❑ Amendment/Addendum
❑ Special Purchase, QPA
❑ Bid Opening
❑ Bid Award
❑ Req. to Advertise ❑ Title Sheet
❑ Quote Opening
❑ Quote Award
❑ Reject Bids/Quotes
❑ Proposal Opening
❑ C/O & PCA No.
❑ PCA
® Chg. Order, No. 6 and Final
❑ Traffic Control
❑ Resolution
n Other:
n Ease./Encroach
Information
Company or Vendor Name
INDOT (Contractor is Milestone)
❑ Yes❑ If Yes, Approved by Purchasing
New Vendor
® No
Yes
MBE
MBE/WBE Contractor
Completed E-Verify Form Attached
❑ ❑ No
Project Name
Coal Line Trail Phase 2B
Project Number
122-035 DES2200199
Funding Source
Account No.
PO-0025244
Amount
$3,406,165.11
Terms of Contract
Purpose/Description
See attached memo.
For Change Orders Only
Amount of ❑ Increase
® Decrease ($ 102,370.4)
Previous Amount
$3,508,535.51
Increase
Current Percent of Change:
Decrease
New Amount
$3,406,165
Increase
Total Percent of Change:
Decrease
Time Extension Amount:
New Completion Date:
967%
(1.277%)