•50-unit scattered site affordable housing development
•Plans to break ground this summer and complete units in 2025
•City support: Land and taxabatement
Total Investment:$13M
Advantix Development Corp.
City of South Bend
Indiana
•Improvements from Michigan to Leahy Sts.
•Restriping to 3 lanes to calm traffic, add parking, add signal at Joyce, and add shared use path along Burke Golf Course
•Construction began April 15th, with completion anticipated this summer
Total Investment: $3.3M ($2.3M from UND)
Angela Boulevard Improvements
City of South Bend
Indiana
•New headquarters and expanded cold storage facility
•Construction planned to be completed this summer
•City support: Land and direct funding support
Total Investment: $10M
Cultivate Culinary
City of South Bend
Indiana
•EPA completed remediation of asbestos and
other known contaminants on site in
November 2023
•City team is now managing the next phase of
demolition of collapsed outbuildings and
removal of concrete and streel debris
•City support: Ownership, EPA partnership,
future phases of cleanup
Total Investment: $3M from EPA
Drewrys Cleanup
City of South Bend
Indiana
•Construction expected to begin on 60-unit LIHTC building this summer
•90 market-rate unit buildings to follow
•City support: Land, directing funding support, and tax abatement
Total Investment: $37.3M
Diamond View and Stadium Flats
City of South Bend
Indiana
•New multi-use path to link the downtown to the university
•Construction planned to be completed this year
Total Investment: $11.5M
(shared between City, UND, and Hotel Motel Tax Board)
Downtown-Notre Dame Trail
City of South Bend
Indiana
•108-unit apartment building broke ground this month, with completion planned for 2026
•City support: Tax abatement
Total Investment: $31.5M
Five Corners
City of South Bend
Indiana
•Addition of 2nd deck, expansion of seating, new clubhouse
•Design being finalized, construction to begin in Fall 2024
Total Investment: $45M
Four Winds Field Expansion
City of South Bend
Indiana
•Construction wrapping up on new Indiana Dinosaur Museum and expanded production space for South Bend Chocolate Company
•Opening this summer
•City support: Tax abatement, direct funding support
Total Investment: $14M
Indiana Dinosaur Museum
City of South Bend
Indiana
•New streetscape on LaSalle Avenue to add bump-outs, improve pedestrian connections, add a protected bike lane, and expand on-street parking
•Completed this spring
Total Investment: $7M
LaSalle Avenue Streetscape
City of South Bend
Indiana
•90 new apartments being constructed on floors 18-26
•Rooftop lounge/bar planned for 7th floor
•Construction planned to be completed this year
•City support: Direct funding support, tax abatement
Total Investment: $14.7M
Liberty Tower Phase IV
City of South Bend
Indiana
•Improvements for College to Birdsell in conjunction with MLK Center
•Began construction in March for June completion
Total Investment: $2M
Linden Avenue Streetscape
City of South Bend
Indiana
•Improvements for Beyer/Longfellow to Emerson
•Under engineering design with construction expected to begin in Spring 2025
Total Investment: $3M
Mishawaka Avenue Streetscape
City of South Bend
Indiana
•Remodel of 120 units substantially completed
•48 units set aside for voucher holders per agreement with South Bend Housing Authority
•City support: Direct funding support
Total Investment: $4.95M
MarMain Renovations
City of South Bend
Indiana
•10-story, 300,000 square-foot expansion of Memorial Hospital
•Largest construction project in 129-year history of Memorial Hospital
•Growth from 249 to 302 acute care beds
•City support: Direct funding, potential tax abatement
Total Investment: $330M combined
Madison Lifestyle District and Beacon Patient Tower
City of South Bend
Indiana
•$100M+ redevelopment of two city blocks south of Memorial Hospital
•Will be coming to Common Council in coming months for consideration of tax abatement
Madison Lifestyle District (cont.)
City of South Bend
Indiana
•Planned extension of Coal Line Trail to MLK Dream Center
•Currently under design, construction planned for 2026-2027
Mayor Stephen J. Luecke Coal Line Phase 2 & 3
City of South Bend
Indiana
•Construction of an entrepreneurial hub and commissary kitchen as well as renovation of SoMa apartments to the south.
•Multi-year construction timeline.
•City support: Land, abatement, potential development agreement
Total Investment: $6M
Momentum
City of South Bend
Indiana
•Construction expected to begin this year on 60-unit development
•City support: Land, direct funding support, tax abatement
Total Investment: $16.9M
Monreaux
City of South Bend
Indiana
•Ground broken early this month on building for new grocery store, restaurant, and two tenant spaces on the northwest corner of Olive and Western at the site of the former PNA building
•Construction expected to be completed by the end of 2024
•City support: Land
Total Investment: ~$2.5M
Olive & Western Redevelopment (Former PNA site)
City of South Bend
Indiana
•Construction set to commence on 54-unit affordable housing complex co-located with YSB Center for Youth Success
•City support: Direct funding and supporting infrastructure
Total Investment: $14.5M
South Bend Thrive
City of South Bend
Indiana
•Construction underway on 335 rental apartment units and 26 townhomes
•Completion planned by August 2024
•City support: None
Total Investment: $100M+
The 87 (Toll Brothers)
City of South Bend
Indiana
•Redevelopment of former St. Joseph Hospital office tower into 69-unit apartment building
•Construction completed
•City support: direct funding support, tax abatement
Total Investment: $14M
The Hill
City of South Bend
Indiana
•Southeast Center completed in 2022, now houses El Campito Pre-K facility
•DCI working with United Way to find site for new center in the Far Northwest Neighborhood
•City support: Direct funding
Total Investment: $6M
United Way One Roof SE and Future FNW site
City of South Bend
Indiana
•Phase I planned to break ground this summer to add a portion of new digestor tanks
•Multi-year construction timeline for full project to create first biorefinery in Indiana and one of the largest in the Midwest
•City support: Tax abatement
Total Investment: $230M
Verbio Biorefinery
City of South Bend
Indiana
•Traffic calming and shared use path improvements along Ewing Avenue in conjunction with Walker Field project
•Provides new pedestrian entry to Rum Village Park
•Under engineering design for construction in late 2024 or 2025
Total Investment: $2.5M
Walker Field / Ewing Avenue Improvements
City of South Bend
Indiana
•YSB Center for Youth Success construction has been underway since last year
•The new Center will expand the Safe Station shelter and allow for more programming and consolidated operations of YSB
•City support: Direct funding and supporting infrastructure
Total Investment: $9M
Youth Service Bureau